SS9701-CN 930713 CITY OF COPPELL
CHANGE OR EXTRA WORK ORDER
PROJECT: Grapevine Creek Sewer Trunk Project
Branches I and II
CONTRACTOR: Kenko Inc. Contractors
OWNER: City of Coppell
CHANGE ORDER NO.: 3 DATE: 7/13/93
CHANGE OR EXTRA WORK TO BE DONE
Delete 589 feet of 30" PVC Sewer Pipe (20-25) - $ 57,722.00
589 feet @ $98.00 per foot
Add 589 feet of Micro-tunnel & pipe
589 feet of Micro-tunnel & pipe @ $270.00 per foot $159,030.00
Total cost of proposed changes $101,308.00
Previous contract amount $2,815,005.50
Net increase in contract amount $ 101,308.00
Revised contract amount $2,916,313.50
Net increase in contract time of completion N/A
Revised contract time of completion No Change
The contractor hereby accepts this Contract adjustment as a final and complete adjustment in full
accord and satisfaction of all past and future liability originating under any clause in the Contract
by reason of this revision to the Contract.
Recommended by the City Engineer:
~Date: 7/13/93
to by the Contractor:
_ Zz:/-~. ~'~/;f~~,._.~ Date:
by the Owner)
~t/~ Date: