Freeport NIP(7.5)-LR010724 GEOTECNNICAL AND J~i F=J I--1 I I ~
ENVIRONMENTAL CONSULTANTS
REPORT OF REINFORCING
STEEL PLACEMENT OBSERVATION
Freeport 9
Coppell Road at Bethel Road
Coppell, Texas
REPORTED TO: Duke-Weeks Realty Corporation REPORT NO. 76
5495 Belt Line Road, Suite 360 REPORT DATE: 07-24-01
Dallas, Texas 75240 REG PROJECT NO. 7888
ATTN: Mr. Jeff Langston DATE OBSERVED: 07-05-01
TECHNICIAN: L. Johnson
PAGE: 1 of 1
CONTRACTOR: Butler Construction
J Items Observed: J Tilt Wall Panels: 13, 14, 15, 16, 17, 18, 19, 20, 21, 22,
23, 24, 25, 26, 27, 28, 29, 30, 31, 32 and 33.
J Reference Plans or Notes Used: J Sheets S9, 10, 11 and 12.
JList Deviations Noted: il) All panels needs to be cleaned.
2) Panel #24 needs additional ties and chairs.
3) Panel #29 missing two//4, 4' diagonal bars at one corner of
the opening.
The noted deviations were reported to: Gary Green with Butler Construction
J x JThe noted deviations were corrected.
The reinforcing steel placed at the above referenced locations was observed with
respect to the referenced portions of the contract documents.
Mail Submitted by:
Distribution: (1) Duke-Weeks Realty Corporation/
Mr. Jeff Langston REED ENGINEERING GROUP, INC.
(1) Butler Construction/
Mr. David Husted Original Signed By
(1) Pacheco Koch, Inc./Mr. Jack Evans
(1) City of Coppel/Mr. Lee Stone James F. Phipps, P.E.
(1) City of Coppel/Mr. Larry Davis KA/cg
(1) HBC Engineering/Mr. Bob Baker
~.424 STUTZ DP,. · SUITE 400 · DALLAS, TX 757.35 · TEL [~-J~J] 350 5600 · FAX [214] 350 0019
GEOTECHNICAL AND [~ J=~J I--1 U F~
ENVIRONMENTAL CONSULTANTS
REPORT OF PIER OBSERVATION
Freeport 9
Coppell Road at Bethel Road
Coppell, Texas
REPORTED TO: Duke-Weeks Realty Corporation REPORT NO. 70
5495 Belt Line Road, Suite 360 REPORT DATE: 07-24-01
Dallas, Texas 75240 REG PROJECT NO. 7888
ATTN: Mr. Jeff Langston TECHNICIAN: J. Johnson
PAGE: 1 of 1
CONTRACTOR: Butler Construction
J J Pier Diameter Bell Diameter Depth Before I Final Depth Concrete
Date Pier No. I (inches) (inches) Bell (feet) I of Pier (feet) Length (feet)
06-29-01 G.2-2.1 18 48 13.0 13.3 13.0
G.4-2.1 18 48 13.0 13.6 13.3
Screen wall N.E. corner of building
J Pier Diameter Bell Diameter Depth Before I Final Depth Concrete
Date Pier No. (inches) (inch,es) Bell (feet) J of Pier (feet) Length (feet)
06-29-01 OL.1-20.7 24 60 13.0 13.6 11.6
OL.2-20.7 24 60 12.0 13.2 11.4
OL.4-20.7 24 60 11.0 13.0 10.9
OL.5-20.7 24 60 10.5 11.0 10.0
OL.6-20.7 24 60 11.7 13.3 11.2
Screen wall N.W. corner of building
Pier No. (inches) (inches) Bell (feet) of Pier (feet) ILength (feet)
06-29-01 OL. 1-3.9 24 60 11.6 12.2 10.4
Mail Submitted by:
Distribution: (1) Duke-Weeks Realty Corporation/
Mr. Jeff Langston REED ENGINEERING GROUP, INC.
(1) Butler Construction/Mr. David Husted
(1) Pacheco Koch, Inc./Mr. Jack Evans Original Signed By
(1) City of Coppel/Mr. Lee Stone
(1) City of Coppel/Mr. Larry Davis James F. Phipps, P.E.
(1) HBC Engineering/Mr. Bob Baker KA/cg