W Sandy Lk Addn II Infra-SY211201
PROJECT NO. 24459
DECEMBER, 2021
GEOTECHNICAL INVESTIGATION
OFFICE/WAREHOUSE
NEC WEST SANDY LAKE ROAD AND S.H. 121
COPPELL, TEXAS
Presented To:
MC II DEVELOPMENT, LTD.
DALLAS, TEXAS
December 22, 2021
Project No. 24459
MC II Development, Ltd.
3811 Turtle Creek Boulevard, Suite 1460
Dallas, Texas 75219
ATTN: Mr. Richard Crow
GEOTECHNICAL INVESTIGATION
OFFICE/WAREHOUSE
NEC WEST SANDY LAKE ROAD AND S.H. 121
COPPELL, TEXAS
Gentlemen:
Transmitted herewith are copies of the referenced report. Should you have any
questions concerning our findings or if you desire additional information, do not
hesitate to call.
Sincerely,
REED ENGINEERING GROUP, LTD.
Registration Number F-3114
Kundan K. Pandey, Ph.D., P.E.
Project Engineer
KKP/apv
copy submitted via e-mail only
December 22, 2021
- i -
TABLE OF CONTENTS
PAGE
INTRODUCTION.................................................................................................... 1
Project Description...................................................................................... 1
Authorization................................................................................................ 1
Purpose and Scope....................................................................................... 2
FIELD AND LABORATORY INVESTIGATIONS............................................ 2
General.......................................................................................................... 2
Field Investigation........................................................................................ 3
Laboratory Testing...................................................................................... 4
GENERAL SITE CONDITIONS........................................................................... 5
Physiography................................................................................................ 5
Geology......................................................................................................... 5
Stratigraphy................................................................................................. 6
Ground Water.............................................................................................. 7
Texas Health and Safety Code and TCEQ Comment.............................. 7
Seismic Site Classification........................................................................... 8
ANALYSIS AND RECOMMENDATIONS.......................................................... 8
Potential Vertical Movements..................................................................... 8
Foundation Design....................................................................................... 9
Grade Beams/Tilt-Wall Panels................................................................... 11
Floor Slab...................................................................................................... 12
Retaining Walls............................................................................................ 19
Earthwork, General..................................................................................... 22
Earthwork..................................................................................................... 23
Pavement....................................................................................................... 26
Construction Observation and Testing Frequency................................... 32
- ii -
TABLE OF CONTENTS
(Continued)
ILLUSTRATIONS
PLATE
PLAN OF BORINGS............................................................................................... 1
BORING LOGS....................................................................................................... 2-16
KEYS TO TERMS AND SYMBOLS USED......................................................... 17&18
LABORATORY TEST RESULTS........................................................................ 19-24
ABSORPTION PRESSURE-SWELL TEST RESULTS..................................... 25-28
SPECIFICATIONS
PAGE
WATER INJECTION W/“SELECT” FILL CAP................................................ 1
WATER INJECTION W/”FLEXIBLE BASE” CAP.......................................... 1
WATER INJECTION W/LIME-MODIFIED CAP............................................. 1
Project No. 24459 - 1 - December 22, 2021
INTRODUCTION
Project Description
This report presents the results of a geotechnical investigation performed for the proposed
office/warehouse building to be located on West Sandy Lake Road in Coppell, Texas. The
general orientation of the building is shown on the Plan of Borings, Plate 1 of the report
Illustrations.
The project consists of construction of an approximate 130,030-square foot office/warehouse
building on an approximate 9.01-acre site located at the northeast corner of West Sandy Lake
Road and State Highway (S.H.) 121 in Coppell, Texas. Site paving for parking and drives is
included in the project. Finished floor elevation is currently set at Elev. 520.75. The
recommendations provided herein should be reviewed by this office if finished floor elevation
is changed by more than one foot. This office should be provided with the latest site grading
plan to allow for evaluation and modification of the recommendations, if necessary.
Authorization
This investigation was authorized by Mr. Richard L. Crow by signature of our Proposal No. 10-
32 on November 10, 2021.
Project No. 24459 - 2 - December 22, 2021
Purpose and Scope
The purpose of this investigation has been to evaluate the general subsurface conditions and
provide recommendations for:
design of the foundation system;
floor slab;
lateral earth pressures for design of retaining walls;
pavement subgrade; and
site preparation and earthwork compaction criteria.
The investigation has included drilling sample borings, performing laboratory testing,
analyzing engineering and geologic data and developing geotechnical recommendations. The
following sections present the methodology used in this investigation.
Recommendations provided herein are site-specific and were developed for the project
discussed in the report Introduction. Persons using this report for other than the intended
purpose do so at their own risk.
FIELD AND LABORATORY INVESTIGATIONS
General
The field and laboratory investigations have been conducted in accordance with applicable
standards and procedures set forth in the 2021 Annual Book of ASTM Standards, Volumes
04.08 and 04.09, "Soil and Rock." These volumes should be consulted for information on
specific test procedures.
Project No. 24459 - 3 - December 22, 2021
Field Investigation
Subsurface conditions were evaluated with a total of 15 soil borings drilled to depths of 6 to
31-1/2 feet below existing (November 2021) site grades. The locations of the borings are
shown on Plate 1 of the report Illustrations. Borings were located in the field using a GPS
(global positioning system) unit. The accuracy of this unit is estimated to be within plus or
minus one meter.
Borings were advanced between sampling intervals by means of a truck-mounted drilling rig
equipped with continuous flight augers. Samples of cohesive soils were obtained with 3-inch
diameter Shelby tubes (ASTM D1587). Cohesionless soils (sands and gravels) were sampled
in conjunction with the Standard Penetration test (SPT) (ASTM 1586).
Delayed water level observations were made in the open boreholes to evaluate ground water
conditions. Borings were backfilled at completion of field operations.
Sample depth, description of materials, field tests, water conditions and soil classification
[Unified Soil Classification System (USCS), ASTM D2488] are presented on the Boring Logs,
Plates 2 through 16. Keys to terms and symbols used on the logs are included as Plates 17 and
18.
Elevations shown on the boring logs are based on the nearest one-foot interpolations of the
grades shown on the grading plan provided by the client.
Project No. 24459 - 4 - December 22, 2021
Laboratory Testing
All samples were returned to the laboratory and visually logged in accordance with the USCS.
The consistency of cohesive soils was evaluated by means of a pocket penetrometer. Results of
the pocket penetrometer readings are presented on the boring logs.
Laboratory tests were performed to evaluate index properties, confirm visual classification and
evaluate the undrained shear strength of selected samples. Tests and ASTM designations are
provided in Table 1.
TABLE 1.
TESTS CONDUCTED AND ASTM DESIGNATIONS
Type of Test ASTM Designation
Atterberg Limits D4318
Moisture Content D2216
Partial Gradation D1140
Soil Suction D5298
Unconfined Compression (Soil) D2166
The results of these tests are summarized on Plates 19 through 24.
Project No. 24459 - 5 - December 22, 2021
The expansive characteristics of the upper soils and weathered shale were also evaluated by
means of four absorption pressure-swell tests conducted in accordance with general procedures
discussed by Johnson and Snethen1. Results of the swell tests are presented graphically on
Plates 25 through 28.
GENERAL SITE CONDITIONS
Physiography
The site is located at the northeast corner of West Sandy Lake Road and S. H. 121 in Coppell,
Texas. The site is a moderately sloping undeveloped tract of land covered with grass and
scattered trees. Based on the grading plan, site grades vary from approximate Elev. 509 to
Elev. 522. Finished floor is set at Elev. 520.75. It is estimated approximately up to 2 feet of
cut and 11 feet of fill will be required to achieve finished floor elevation.
Geology
The site is located within terraced alluvial soils overlying the Cretaceous Woodbine Formation.
The Woodbine Formation typically consists of variably stratified silty and sandy clays, clay,
silty and clayey sands, sand, sandstone and shale with occasional interbeds of lignite.
1 Johnson, L.D., & Snethen, D.R. (1978). "Prediction of Potential Heave of Swelling Soil." Geotechnical Testing
Journal, ASTM 1 (3), 117-124.
Project No. 24459 - 6 - December 22, 2021
Stratigraphy
Subsurface conditions encountered in the borings consisted of alluvial soil overlying residual
soil of the Cretaceous Woodbine Formation. The alluvial soil consisted of dark brown to
brown, brownish-yellow, and gray, high to moderate plasticity (CH to CL) clay and sandy clay,
and clayey sand. The alluvial soils were encountered to depths of 14 to 18 feet.
Below depths of 14 to 18 feet, residual soil consisting of brown to brownish-yellow and
reddish-yellow clayey sand, gravelly sand, and poorly graded fine sand was encountered. The
deeper borings drilled within the building footprint were terminated within the dense to very
dense sand and gravelly sand at depths of 29-1/2 to 31-1/2 feet. The dense to very dense sand
and clayey sand represent the severely weathered to weathered sandstone.
Based on the suction profiles, the upper soils were relatively dry to depths of 6 to 10 feet at the
time of the field investigation (November 2021). The upper 10 to 15 feet of the subsurface soil
is anticipated to be seasonally active. The suction profiles are provided in the following graph.
Project No. 24459 - 7 - December 22, 2021
Ground Water
A limited amount of ground water seepage was noted in some borings (Borings B-1 and B-6) at
depths of 29 to 30 feet during drilling. Ground water was not noted in the open bore holes at
completion of drilling. The remaining borings were noted dry during drilling and at the end of
the day of drilling.
Based on post-drilling water level observations, ground water was not present within the depths
explored in November 2021. The depth to ground water will fluctuate with variations in
seasonal and annual rainfall.
Texas Health and Safety Code and TCEQ Comment
Pursuant to the Texas Health and Safety Code, Chapter 361, §361.538 and 30 Texas
Administrative Code 330, §330.953, Reed Engineering Group, Ltd. has performed appropriate
soil tests as required by these regulations to demonstrate that the subject property does not
Project No. 24459 - 8 - December 22, 2021
overlie a closed municipal solid waste landfill. The site observations and subsurface data do
not indicate the presence of buried municipal solid waste at this site. Based on these data,
development of this site should not require a Development Permit, as described in §361.532
and §§330.951-330.963, Subchapter T.
Seismic Site Classification
The site has been classified with respect to seismic design criteria contained in the 2015
International Building Code (IBC), Section 1613, and ASCE 7-10, Chapter 20. The criteria
require characterization of the upper 100 feet of subsurface materials. Based on the ASCE 7-
10 criteria, the site is classified as Site Class C in accordance with Table 20.3-1.
ANALYSIS AND RECOMMENDATIONS
Potential Vertical Movements
Potential Vertical Movements (PVM) were evaluated using an empirical procedure developed
by McDowell2 and modified by the Texas Department of Transportation, TxDOT Test Method
124-E3 in conjunction with the soil suction and absorption pressure-swell tests. Based on the
PVM calculations and past experience, potential movements are estimated to be on the order of
two to four inches. Movement will primarily be associated with seasonal changes in soil
moisture.
2 McDowell, C. "The Relation of Laboratory Testing to Design for Pavements and Structures on Expansive Soils"
(1959). Quarterly of the Colorado School of Mines, Volume 54, No. 4, 127-153.
3 "Method for Determining the Potential Vertical Rise, PVR." (1978). Texas Department of Transportation, Test
Method Tex-124-E.
Project No. 24459 - 9 - December 22, 2021
Ground-supported improvements (i.e., sidewalks and paving) will move in response to changes
in soil moisture. The movement will be observed as heave if the soils are dry at the time the
pavement or sidewalk is constructed. The movement will be observed as settlement if the soils
are moist at the time of construction. Generally, settlement will be limited to the outer
perimeter (outer four to five feet) of larger slabs. Prudent watering during extended dry
climatic periods can control settlement. Recommendations are provided to limit movement
below the building; however, some movement of site paving and sidewalks should be
anticipated.
The estimated PVM is based on current grading plan and finished floor elevation at 520.75. If
finished floor elevation is altered by more than one foot, this office should be consulted for
additional analysis and recommendations.
Foundation Design
Foundation support for concentrated column loads should be provided by reinforced concrete,
underreamed (belled) piers. The piers should be founded at Elev. 506.0 within the brown to
brownish-yellow clay and sandy clay. Considering current finished floor at Elev. 520.75, piers
should be founded at an approximate depth of 15 feet below finished floor elevation. Piers
should be founded on top of the sand or clayey sand stratum if encountered above the
recommended founding depth. Piers should be designed for an allowable bearing pressure of 6
kips per square foot (ksf) considering dead load and 9 ksf considering total (live plus dead)
load, whichever governs.
Project No. 24459 - 10 - December 22, 2021
Piers proportioned in accordance with the allowable bearing value will have a minimum factor
of safety of three with respect to dead load and two with respect to total load, against a
plunging or shear failure. The weight of the pier concrete below final grade may be neglected
in determining foundation loads. Elastic settlement of properly constructed underreamed piers
should be limited to approximately ½ inch.
The recommended end bearing value is based on a minimum center-to-center pier spacing of
two times the average bell diameter. If piers will be closer than two bell diameters, center-to-
center, a reduction in the end bearing is recommended. This office should be contacted for
specific recommendations.
Piers will be subjected to uplift associated with swelling within the upper clays. The piers
should contain reinforcing steel throughout the pier to resist the tensile uplift forces.
Reinforcing requirements may be estimated based on an uplift pressure of 1.2 ksf acting over
the top 6 feet of pier surface area. The recommended uplift value is considered a working load.
Appropriate factors of safety should be applied in calculating the percent of reinforcement.
"Mushrooming", or widening of the upper portion of the pier shaft, will significantly increase
the uplift pressure from the upper clays. "Mushrooms" should be removed from the piers prior
to backfill operations.
Pier caps should not be used with the piers unless a minimum void of 6 inches (factor of safety
of 1.5) is created below the portion of the cap extending beyond the shaft diameter. The void
may be reduced to four inches if remedial earthwork is performed in accordance with the Floor
Slab section.
Project No. 24459 - 11 - December 22, 2021
Uplift resistance for underreamed piers will be provided by the weight of the soil overlying the
bell and the dead load from the structure. A minimum bell-to-shaft diameter ratio of two to one
(2:1) is recommended to resist uplift associated with swelling of the upper soils. A maximum
bell-to-shaft diameter ratio of 3:1 is recommended to limit possible caving of the bells.
Significant quantities of ground water were not encountered within the recommended founding
depths of piers during the field investigation. The use of casing or dewatering of pier
excavations should not be required if close coordination of drilling and concrete placement is
performed.
Pier excavations should be dry and free of deleterious materials prior to concrete placement. In
no case should the pier shaft excavations remain open for more than four hours prior to
concrete placement.
Continuous observation of the pier construction by a representative of this office is
recommended. Observation is recommended to confirm the bearing stratum and that the
excavations are dry prior to placement of concrete.
Grade Beams/Tilt-Wall Panels
Grade beams or tilt-wall panels should be constructed with a minimum void of 6 inches (Factor
of Safety of approximately 1.5) beneath them. A void is recommended to limit potential
foundation movements associated with swelling of the underlying soils. The void may be
reduced to four inches if remedial earthwork is performed in accordance with the Floor Slab
section.
Project No. 24459 - 12 - December 22, 2021
The void can be created below grade beams by use of wax-impregnated cardboard forms or
beneath tilt panels by over-excavating the required void space prior to panel erection. Retainer
boards along the outside of the grade beam or tilt-wall panel will not be necessary.
Grade beams should be double-formed. Earth-forming of beams below ground is not
recommended because of the inability to control the beam excavation width.
Fill on the outside of perimeter grade beams and/or tilt walls should be placed in a controlled
manner. Backfill should consist of site-excavated clays, or equal, placed and compacted in
accordance with the Earthwork section. If bedding soils must be used adjacent to the
perimeter of the building, the clay/bedding soil interface should be sloped to drain away from
the building. Compaction criteria are included in the Earthwork section.
Floor Slab
Potential movements associated with heave from a dry condition to a moist condition are
estimated to be on the order of two to four inches. Additional movement is possible if the clays
become saturated, such as can happen from utility leaks and excessive ponding of water
adjacent to the perimeter walls.
Two types of floor systems are considered feasible; a suspended floor and a ground-supported
(or "floating") slab. The suspended floor is considered the most expensive but does provide the
highest degree of confidence that post-construction movement of the floor will not occur. If
this alternative is desired, a minimum void of 8 inches (approximate F.S. of 2) is recommended
between the soil and the lowest structural element of the floor system. For this alternative,
Project No. 24459 - 13 - December 22, 2021
plumbing lines should be suspended a minimum of four inches above the underlying soils.
Where plumbing lines transition into the soil, they must be free to move up to four inches
without intercepting the structure or distressing plumbing joints.
Use of a ground-supported floor is feasible, provided the risk of some post-construction floor
movement is acceptable. The potential movement can be reduced by proper implementation
(i.e., construction) of remedial earthwork recommended in the following paragraphs. The risk
of the potential movement occurring can be reduced by implementation of positive grading of
surface water away from the building and backfilling immediately adjacent to the structure with
on-site clays.
Several options and alternatives are provided in the following sections. The purpose of the
alternatives is to provide optimum performance of ground-supported slabs while limiting
unnecessary costs. This office can assist with optimization of the alternatives upon review of
proposed finished grades.
The most economical way of limiting the potential for post-construction floor movement, and
the most positive from a design perspective, is to reduce the potential for heave-related
movement prior to construction of the floor. This can be accomplished by either:
mechanically excavating the upper soils, mixing the soils with water, then
recompacting the excavated soils at an elevated moisture in controlled lifts; or
preswelling via multiple passes of water pressure injection.
Project No. 24459 - 14 - December 22, 2021
Of these two, the least expensive, most positive and easiest if performed properly, is to
preswell via the injection process. Both options are presented in the following sections.
At completion of either the injection process or excavation and recompaction process, a surface
seal will be required to maintain the desired moisture. Three types of surface seals can be
provided:
a minimum of 12 inches of "select" fill;
a minimum of 6 inches of flexible base; or
lime stabilization of the top 6 inches of soil with a minimum of 6 percent hydrated
lime at completion of reworking or injection.
Experience has shown comparable performance for each of the recommended surface
treatments. The final selection should be based on cut and fill requirements. For example, if
the site has a net import of fill, then the most economical surface seal consists of "select" fill or
flexible base since imported fill will be required. If site earthwork is balanced or is a net
export, then the most cost-effective alternative would consist of stabilizing the surface soils
with lime.
The specific recommendations and general procedures for each of the alternatives are presented
in the following subsections. Recommendations relevant to both alternatives are presented in
the Other Considerations subsection following the alternative discussions.
Project No. 24459 - 15 - December 22, 2021
Excavation and Recompaction Option - An alternative method of pre-wetting the upper soils
to reduce the potential for post-construction swell consists of excavation of the upper soil,
mechanically mixing the soil with water, then recompaction of the excavated soil in controlled
lifts. This method of pre-wetting the soils is not effective unless the water is uniformly blended
with the soil. Simply wetting the surface of the soil will not achieve the required result.
General procedures are as follows.
1. Strip vegetation and dispose of the organic materials in accordance with the project
specifications.
2. Excavate to Elev. 512.0. Extend the footprint of the excavated areas a minimum of
5 feet beyond the general building lines and a minimum of 10 feet beyond
entrances. The lateral extent of the treated areas should be reviewed by the owner
and design team to address desired reduction of movement outside the structure and
surface paving.
3. Scarify the exposed subgrade to a depth of six inches, water as necessary and
recompact to the density and moisture recommended in the Earthwork section.
4. Compact site-excavated soils in lifts as outlined in the Earthwork section to the
subgrade required for the desired moisture cap. Place and compact soils in
accordance with recommendations in the Earthwork section.
Note: If insufficient on-site fill exists to achieve the proposed subgrade for
the "select" fill or flexible base options, all imported fill for use below the
building should consist of "select" fill, flexible base, or approved common
fill. Balance on-site soils to provide a uniform thickness of the imported fill.
5. Place and compact the surface moisture barrier, consisting of either:
12 inches of "select" fill; or
6 inches of flexible base; or
stabilize the top 6 inches of recompacted soil with a minimum of 6
percent hydrated lime.
Project No. 24459 - 16 - December 22, 2021
Placement recommendations for "select" fill and flexible base are included in the Earthwork
section. Lime stabilization should be conducted in accordance with the Texas Department of
Transportation (TxDOT) "Standard Specifications for Construction and Maintenance of
Highways, Streets, and Bridges," 2014 Edition, Item 260. Lime-stabilized soils should be
compacted to a minimum of 95 percent of Standard Proctor density, ASTM D698.
Consideration should be given to benching the perimeter of the excavations, from the bottom
up, at one horizontal to one vertical (1H:1V) to create a transition between reworked soils and
non-reworked soils. This will decrease the potential for concentrated differential movement
between treated and untreated areas.
Pressure Injection Option - This option consists of performing cut and fill balance followed
by injection, then providing a surface seal. The performance of an injected subgrade is
dependent upon the quality of the workmanship. Therefore, water pressure injection is not
recommended unless a representative of this office is present full-time to observe all injection
operations.
Procedures consist of the following.
1. Strip vegetation and dispose of the organic materials in accordance with the project
specifications. All existing trees should be surveyed prior to start of site grading
work. Tree stumps should be excavated to a minimum depth of five feet and
removed from site. All tree roots larger than two inches in diameter should also be
excavated and removed from the site. The excavated areas should be backfilled
with on-site soils compacted in lifts as described in the Earthwork section.
2. Cut and fill balance with on-site soils to the subgrade required for the desired
moisture cap. Place and compact soils in accordance with recommendations in the
Earthwork section.
Project No. 24459 - 17 - December 22, 2021
Note: If insufficient on-site fill exists to achieve the proposed subgrade for
the "select" fill or flexible base options, all imported fill for use below the
building should consist of "select" fill, flexible base, or approved common
fill. Balance on-site soils to provide a uniform thickness of the imported fill.
3. Preswell the upper clays via pressure injection with water. Perform injections to
Elev. 510.0. Guideline specifications for performance of the injection process are
included in the report Specifications. Three guideline Specifications are included,
one for each of the three surface treatment options.
4. Place and compact the surface moisture barrier, consisting of either:
12 inches of "select" fill; or
6 inches of flexible base; or
stabilize the top 6 inches of injected soil with a minimum of 6
percent hydrated lime.
Placement recommendations for "select" fill and flexible base are included in the Earthwork
section. Lime stabilization should be conducted in accordance with TxDOT "Standard
Specifications for Construction and Maintenance of Highways, Streets, and Bridges," 2014
Edition, Item 260. Lime-stabilized soils should be compacted to a minimum of 95 percent of
Standard Proctor density, ASTM D698.
The actual number of injection passes required will be dependent upon the soil moisture
conditions at the time of construction. For estimating purposes, and considering dry conditions
at the time of construction, a minimum of four injection passes should be anticipated.
The injected areas should be extended laterally a minimum of five feet beyond the general
building lines. The injection footprint should be increased a minimum of 10 feet beyond the
building at entrances to reduce the potential for differential movement between the structure
Project No. 24459 - 18 - December 22, 2021
and sidewalks or entrance pavement. The lateral extent of the treated areas should be reviewed
by the owner and design team to address desired reduction of movement outside the structure
and surface paving.
Other Considerations - The moisture caps should be placed within approximately seven
working days following completion of either the injection process or the excavation and
recompaction operations to limit moisture loss.
Careful consideration should be given to the actual area treated with either of the two
alternatives to reduce movement. The potential for post-construction heave will be reduced in
the treated areas; however, areas left untreated will result in differential movement. In general,
it is recommended the treated area extend beyond the building at entrances to reduce the
potential for differential movement among the building, the sidewalk and entrance pavement or
in areas where site paving is relatively flat because of drainage or ADA considerations. The
lateral extent of the treated area should be reviewed by the owner and design to address desired
reduction of movement outside the structure and surface paving.
Potential post-construction floor movement associated with heave, considering a properly
preswelled or reworked subgrade, is anticipated to be on the order of one inch. Additional
movement is possible if the clays become saturated, such as can happen from utility leaks and
excessive ponding of water adjacent to the perimeter walls.
Positive drainage of water away from the structure must be provided and maintained after
construction. Architectural detailing of interior finishes should allow for approximately one
inch of differential floor movement.
Project No. 24459 - 19 - December 22, 2021
A minimum 10-mil thick polyethylene sheet is recommended below the floor to limit migration
of moisture through the slab from the underlying soils. This is of particular importance below
sections of the floor covered with carpeting, paint or tile. Penetrations and lapped joints should
be sealed with a waterproof tape.
Ground-supported floors over expansive soils may be subject to settlement if the underlying
clays dry during the life of the structure. Natural desiccation will be limited to the outer four to
five feet along the perimeter where surface pavement does not abut the structure. However,
roots from trees and shrubs can grow below the structure and increase the zone of desiccation.
This process typically requires 8 to 10 years to develop. An effective means of limiting plant
root growth is construction of a vertical moisture barrier adjacent to the foundation or extension
of paving to the perimeter of the building. If utilized, the barrier should consist of a minimum
six-inch wide, five-foot deep lean concrete wall, or other suitable material. Trees and shrubs
should be planted outside the barrier.
Retaining Walls
Lateral earth pressures against retaining walls will be a function of the backfill within the
"active zone" of earth pressure. The “active zone” is the wedge of soil defined by the surface
of the wall and a plane inclined 45 from the vertical passing through the base of the wall (or
the base of the heel for a cantilevered wall).
Project No. 24459 - 20 - December 22, 2021
Considering backfill using site-excavated materials, lateral earth pressures can be estimated
based on an equivalent fluid pressure of 65 pounds per cubic foot (pcf) for active conditions, or
80 pcf for at-rest conditions. Rotation, or lateral movement on the top of the wall, equal to 0.02
times the height of the wall will be necessary for on-site soil backfill for the “active” condition.
Alternatively, imported "select" fill may be used as backfill in the active zone. Considering
"select" fill, lateral earth pressures can be estimated based on an equivalent fluid pressure of 40
pcf, active conditions, or 60 pcf at-rest conditions. Lateral movement of the top of the wall
equal to 0.001 times the height of the wall will be necessary for the "active" pressure condition
for "select" fill backfill.
The lateral earth pressures are applicable for horizontal surface grades and non-surcharged,
drained conditions. A drainage system should be installed behind the base of the retaining
walls to limit development of hydrostatic pressure. The drainage system should consist, as a
minimum, of 12-inch by 12-inch pocket drains spaced 10 feet on-center, installed near the base
of the wall.
Fill in the pocket drains should consist of durable crushed stone such as ASTM C33, Size 67 or
coarser, wrapped in filter fabric (Mirafi 140N or equivalent). Backfill around the gravel drain
should consist of site-excavated soils or "select” fill. A compacted clay cap is recommended
within the upper two feet of the surface to limit surface-water infiltration behind the walls.
Retaining walls may be founded on spread or continuous footings placed a minimum of 18
inches into undisturbed, on-site soils or compacted and tested fill. Footings should be
proportioned for a maximum bearing pressure of 3,000 pounds per square foot (psf).
Project No. 24459 - 21 - December 22, 2021
Movement of the footings and walls should be anticipated. Flexible walls are recommended.
Solid concrete walls should be battered into the soil to limit outward rotational movement
caused by differential footing movement.
Passive resistance to lateral movement can be estimated based on an equivalent fluid pressure
of 300 pcf for on-site materials. This value is applicable for footings founded on undisturbed,
on-site soils or compacted and tested fill. In addition to passive resistance, a coefficient of
friction between the base of the footing and the underlying soil equal to 0.35 may be used.
The lateral earth pressure values do not incorporate specific factors of safety. If applicable,
factors of safety should be integrated into the structural design of the wall.
Earth slopes up to a height of eight feet should be graded at 4H:1V or flatter. Earth slopes
greater than eight feet in height should be evaluated for global stability. This also applies to
slopes combined with retaining walls that have a combined height in excess of eight feet.
Global stability analysis was not within the scope of the present investigation. This office can
assist in the preliminary global stability analysis if desired. Final global stability analysis is
typically performed by the wall designer.
All constructed slopes should be vegetated as soon as possible. Use of erosion control fabric is
recommended during vegetation of the slopes.
Project No. 24459 - 22 - December 22, 2021
The recommendations above are applicable for retaining walls that are not subject to
inundation by water. Modification of the recommendations may be necessary for wet
applications (such as detention ponds and water features). This office should be provided with
grading plans and wall layouts to review for any necessary modifications to the
recommendations for wet applications.
Earthwork, General
Proper compaction of soil requires both the correct moisture content and “compactive effort” or
energy. The compactive effort, or energy, imparted into the soil by the equipment used for
compaction, has to be compatible with the lift thickness. The lighter the equipment (lower
contact pressure), the thinner the loose lift of soil has to be to achieve adequate compaction.
If the lift of soil is too thick for the energy (compactive effort) exerted by the equipment,
insufficient energy will be transferred through the full lift thickness, resulting in a lens of loose,
settlement-prone soil at the bottom of the lift.
For example, if track-mounted equipment such as a “dozer” is used for compaction, the
thickness of lift will vary with the track contact pressure. For a Caterpillar D-6, with a contact
pressure of approximately 1,000 psf, a maximum loose lift thickness of 6 inches (compacted lift
of 4 inches) is needed to achieve compaction. For a Caterpillar D-10, with a contact pressure
of approximately 3,000 psf, a maximum loose lift thickness of 8 inches (compacted lift of 6
inches) is needed to achieve compaction.
Project No. 24459 - 23 - December 22, 2021
If the upper five to six inches of an excessively thick lift is well compacted, it can meet density,
and therefore the loose, relatively thin lens at the bottom of the lift will not be detected by
density testing resulting in the potential for settlement of under-compacted lenses. Accurately
determining lift thickness is virtually impossible after the fact in large-scale mass earthwork
operations, and can only be controlled by the earthwork contractor by “experience”.
Alternatively, if the earthwork contractor’s field personnel do not have sufficient experience, a
surveyor would need to be hired to accurately survey each lift to evaluate if excessive lifts are
being placed.
For equipment with a relatively light contact pressure (any type of equipment with a contact
pressure of less than approximately 2,000 psf), there is virtually no “factor of safety” relative to
the lift thickness. It is therefore recommended that, if track-mounted equipment is used for
compaction, equipment with a minimum contact pressure of 2,500 psf be specified for mass
earthwork operations.
Earthwork
All vegetation and topsoil containing organic material should be cleared and grubbed at the
beginning of earthwork construction. Areas of the site that will underlie fill or within the
building should be scarified to a depth of 6 inches and recompacted to a minimum of 95
percent and a maximum of 100 percent of the maximum density, as determined by ASTM
D698, "Standard Proctor". The moisture content should range from +1 to +5 percentage points
above optimum.
Project No. 24459 - 24 - December 22, 2021
It is recommended that one-point swell tests at a pressure of 450 psf be performed on
laboratory samples compacted to the above recommended density and moisture. If test results
indicate that the swell will exceed one percent, the field moisture should be adjusted to limit
the potential for swell to less than one percent.
Site-excavated soils should be placed in maximum eight-inch loose lifts (note, loose lift
thickness must be compatible with the compaction equipment) and compacted to the moisture
and density requirements outlined above. The soils should be uniformly blended with water to
achieve the required moisture content.
The final 6 inches of subgrade below pavement should be compacted to a minimum of 95
percent of Standard Proctor, at or above optimum moisture.
All tree stumps within the building and paving areas should be excavated to a minimum depth
of five feet and removed from the site. Tree roots larger than two inches in diameter should
also be excavated and removed from the site. The excavated areas should be backfill with on-
site soils as described above.
Proper backfilling around the building perimeter will reduce the potential for water seepage
beneath the structures. Fill against the perimeter of the foundations should consist of site-
excavated clays, or equal, placed and compacted in accordance with the recommendations
outlined above.
Project No. 24459 - 25 - December 22, 2021
"Select" fill is defined as uniformly blended clayey sand with a Plasticity Index (PI) of between
4 and 15. “Select” fill should be placed in maximum 8-inch loose lifts and compacted to at
least 95 percent of the Standard Proctor density, at a moisture content between -2 to +3
percentage points of optimum moisture.
Flexible base for use below the building slabs is defined as crushed stone or crushed concrete
meeting the requirements of the 2014 Edition of TxDOT, “Standard Specifications for
Construction and Maintenance of Highways, Streets and Bridges”, Item 247 Grade 1 or 2, Type
D or better. Flexible base should be compacted to a minimum of 95 percent of Standard
Proctor density, at a moisture content between -2 to +3 percentage points of optimum moisture.
Lime stabilization should be conducted in accordance with TxDOT "Standard Specifications
for Construction and Maintenance of Highways, Streets, and Bridges," 2014 Edition, Item 260.
Lime-stabilized soils should be compacted to a minimum of 95 percent of Standard Proctor
density, ASTM D698 at or above optimum moisture content.
The moisture cap should be placed within approximately seven working days over the injected
or reworked subgrade to limit moisture loss within the underlying soils.
Crushed stone utilized for the drainage system behind retaining walls should consist of durable
gravel meeting ASTM C33 Size 67 or coarser. Gravel should be placed in maximum 8-inch
loose lifts and compacted to a minimum of 60 percent of the relative density as determined by
ASTM D4254.
Project No. 24459 - 26 - December 22, 2021
Pavement
As stated above, the PVR on this site is two to four inches. If this magnitude of potential
movement of the pavement is acceptable, no remedial earthwork will be necessary. If it is not
acceptable, it is recommended that subgrade modification be performed. This office can assist
with different depths of subgrade modification versus PVR, if desired. If subgrade
modification is limited to the building envelopes, site grading should account for the potential
movements beyond the treated area of the building.
The specific pavement section will be dependent upon:
1. traffic loads and frequency;
2. pavement type and strength;
3. desired pavement life; and
4. strength and condition of the subgrade.
Information regarding the specific traffic loads and frequency is not available. Therefore,
analysis was performed for a range of traffic conditions, and design thickness versus traffic
load diagrams were developed. The pavement designer, typically the civil engineer, should
review the anticipated traffic with the building owner or end user. If the anticipated traffic will
vary from the stated values in the following paragraphs, this office can provide alternative
sections upon request.
Project No. 24459 - 27 - December 22, 2021
The pavement type has been identified as concrete. Analysis was performed for both 3,000
pounds per square inch (psi) and 4,000-psi compressive strength concrete. A 20-year life was
used for the analysis. Total pavement life was based on a six-day week. Analysis was
performed in accordance with procedures developed by the American Association of State
Highway and Transportation Officials (AASHTO).
The upper surface soils consist of CH clays. When these soils are moist, they are relatively
soft. For purposes of pavement analysis, the subgrade was assumed to be recompacted in
accordance with the density and moisture recommendations in the Earthwork section and in a
moist condition. An effective modulus of subgrade reaction, k, of 100 pounds per cubic inch
(pci) was used for the analysis.
The effective k value of the subgrade can be increased to 200 pci by stabilization of the upper 6
inches with a minimum of 6 percent hydrated lime. Lime should be placed and compacted in
accordance with Item 260 of the current edition of TxDOT "Standard Specifications for
Construction of Highways, Street and Bridges." The lime-stabilized subgrade should be
compacted to a minimum of 95 percent Modified Proctor, ASTM D1557, at or above optimum
moisture.
Generally, it is more cost-effective to increase the pavement thickness than to lime-stabilize the
subgrade. However, stabilization does provide an all-weather working platform for the
contractor, and this may be beneficial from a construction perspective, especially if
construction will occur during the wetter part of the year. Stabilization is also recommended if
the traffic speed exceeds 30 miles per hour (mph).
Project No. 24459 - 28 - December 22, 2021
Considering the above discussion, analysis was made for both unlimited repetitions of cars and
light trucks and for multiple repetitions of loaded tractor trailers. Analysis indicates a
pavement thickness of 4.5 inches of 3,000-psi concrete will be adequate for car and light truck
traffic. A minimum five-inch section over a scarified and recompacted subgrade is
recommended.
Pavements subject to multiple repetitions of tractor-trailer traffic were analyzed using both
3,000- and 4,000-psi concrete. Trailers were assumed to be loaded to the maximum allowable
weight, 80 kips, consisting of two sets of tandem axles loaded to 32 kips and one 16-kip axle.
Recommended sections for various rates of truck traffic, based on number of repetitions per
day for a 6-day week, are provided in the following tables considering a subgrade k value of
100 pci and 200 pci. The sections are based on 20-year service life.
The values presented in Tables 2 through 5 below represent the minimum thickness of the
pavement section that should be constructed for the corresponding traffic volume. Allowance
for variations that can occur during construction should be incorporated in the plan.
Project No. 24459 - 29 - December 22, 2021
TABLE 2. (K=100 PCI)
NUMBER OF TRUCK REPETITIONS VS. PAVEMENT THICKNESS
3,000-PSI COMPRESSIVE STRENGTH
Pavement Thickness
(inches)
No. of Repetitions
(per day)
6 (minimum recommended for fire lanes) 12
7 30
8 65
9 140
10 280
TABLE 3. (K=100 PCI)
NUMBER OF TRUCK REPETITIONS VS. PAVEMENT THICKNESS
4,000-PSI COMPRESSIVE STRENGTH
Pavement Thickness
(inches)
No. of Repetitions
(per day)
6 18
7 45
8 105
9 220
10 440
Project No. 24459 - 30 - December 22, 2021
TABLE 4. (K=200 PCI, LIME-STABILIZED SUBGRADE)
NUMBER OF TRUCK REPETITIONS VS. PAVEMENT THICKNESS
3,000-PSI COMPRESSIVE STRENGTH
Pavement Thickness
(inches)
No. of Repetitions
(per day)
6 (minimum recommended for fire lanes) 18
7 42
8 90
9 185
10 350
TABLE 5. (K=200 PCI, LIME-STABILIZED SUBGRADE)
NUMBER OF TRUCK REPETITIONS VS. PAVEMENT THICKNESS
4,000-PSI COMPRESSIVE STRENGTH
Pavement Thickness
(inches)
No. of Repetitions
(per day)
6 28
7 65
8 140
9 280
10 550
The values are based on Terminal Serviceability Index (pt) of 2.0, Overall Standard Deviation
(Sd) of 0.35, Reliability (R) of 90 percent, Load Transfer Coefficient (J) of 3.2, and Drainage
Coefficient (Cd) of 1.0.
Project No. 24459 - 31 - December 22, 2021
Analysis of Tables 2 and 3 indicates an approximate 50 to 57 percent increase in the number of
truck repetitions can be obtained by increasing the concrete strength from 3,000 psi to 4,000
psi. An increase of approximately 100 to 150 percent is realized by increasing the thickness of
the pavement by 1 inch.
Analysis of the allowable repetitions was also performed considering a stabilized subgrade
(Tables 4 and 5). For any given pavement thickness and strength of concrete, an increase in the
number of repetitions equal to 25 to 50 percent of the non-stabilized repetitions is realized.
Considering the relative costs associated with stabilizing the subgrade, a greater increase in
repetitions (i.e., pavement life) is realized by increasing the pavement thickness or strength
versus stabilization of the subgrade.
Pavements should be lightly reinforced if shrinkage crack control is desired. Reinforcing for 5-
and 6-inch pavements should consist of the equivalent of #3 bars (metric #10) at 24 inches on-
center, and 18 inches on-center for pavements of 7-inch thickness or greater.
Pavement sections should be saw-cut at an approximate spacing in feet of 2.5 to 3 times the
pavement thickness expressed in inches, not to exceed a maximum spacing of 20 feet. (For
example, a 5-inch pavement should be saw-cut in approximate 12.5- to 15-foot squares.) The
actual joint pattern should be carefully designed to avoid irregular shapes. Load transfer
Project No. 24459 - 32 - December 22, 2021
devices at transverse joints should be provided as necessary. Recommended jointing
techniques are discussed in detail in "Guide for Design and Construction of Concrete Parking
Lots," published by the American Concrete Institute4.
At the truck courts where the pavement abuts the building, it is recommended that the last six
inches of pavement be swept up three to four inches to decrease the chances of water ponding
adjacent to the building.
The above sections are based on the stated analysis and traffic conditions. The pavement
designer, typically the civil engineer, should review the anticipated traffic with the building
owner or end user. If the anticipated traffic will vary from the stated values above, this office
can provide alternative sections upon request. Additional thickness or subgrade stabilization
may be required to meet the City of Coppell development code.
Construction Observation and Testing Frequency
It is recommended the following items (as a minimum) be observed and tested by a
representative of this office during construction.
Observation:
Fill placement and compaction.
Pressure-injection operations.
Pier construction and concrete placement.
4 "Guide for Design and Construction of Concrete Parking Lots" (1987). American Concrete Institute, Publication
MSP 34, Silver Spring, MD.
Project No. 24459 - 33 - December 22, 2021
Testing:
Earthwork
One test per 5,000 square feet per lift within fills below the building.
One test per 10,000 square feet per lift within fills in the paving area.
One test per 150 linear feet per lift in utility and grade beam backfill.
One test per 100 linear feet per lift in retaining wall backfill.
Post-injection borings, one boring per 10,000 square feet of injected area.
The purpose of the recommended observation and testing is to confirm the proper foundation
bearing stratum and the earthwork and building pad construction procedures.
ILLUSTRATIONS
B-13B-15B-14B-11B-10B-5B-7B-8B-6B-4B-3B-2B-9B-1B-12REED ENGINEERINGGROUPOffice / WarehouseNEC West Sandy Lake Road and S.H. 121Coppell, TexasProject No. 24459PLATE 1APLAN OF BORINGS0 50' 100'200'
Seepage during drilling
50 Blows = 4-1/2 inches
50 Blows = 4-1/2 inches
50 Blows = 4 inches
517
513
511
508
499
494
489
SILTY CLAY, dark brown, hard, w/trace of sand (CH)
SILTY CLAY, brownish-yellow, brown & gray, hard, w/sand &
some iron stains (CH - CL)
-w/trace of root @ 6'
SILTY CLAY, brownish-yellow, light brown & gray, hard, w/iron
stains & some sand (CH)
GRAVELLY SAND, light brown, very dense, w/gravel, fine to
coarse (SW)
SAND, light brown, very dense, fine (SW)
SAND, light brown & brownish-yellow, very dense, w/some
gravel, fine to coarse (SP)
Total Depth = 29.5 feet
Seepage encountered @ 29' during drilling. Dry & blocked @
28-1/2' @ end of day. Dry & blocked @ 26' on 11/29/2021.
BORING LOG B-01 PLATE 2
Location: See Plate 1
GraphicLogrec %(rqd %)SampleProject Number : 24459
Date Completed : 11/24/2021
REED ENGINEERING
GROUP
Pocket Penetrometer Readings
Tons Per Sq. Ft. -
1 2 3 4 5 612344.5+4.5++
Depth
(ft)
5
10
15
20
25
30
35
Standard Penetration Tests
Blows per Foot -
10 20 30 40 50 60 Elev.
(ft)DESCRIPTION OF STRATA
GEOTECHNICAL CONSULTANTS -
locNEC West Sandy Lake Road and S.H. 121
POffice/Warehouse
loc2Coppell, Texas
50 Blows = 5-1/2 inches
520
518.5
515.5
511.5
507
504
497.5
SILTY CLAY, brown & yellowish-red, very stiff, w/trace of sand
(CL)
SILTY CLAY, dark brown, hard, w/some sand, trace of iron stains
& ironstones (CH)
SILTY CLAY, brown & brownish-yellow, hard, w/trace of
calcareous deposits, calcareous concretions & sand (CL)
SANDY CLAY, light brown, hard, w/trace of gravel & iron stains
(CL - CH)
SILTY CLAY, light brown, hard, w/trace of iron stains (CL)
SAND, light brown, very dense, w/trace of silty clay, fine (SP)
SAND, light brown, dense to very dense, fine to medium (SP)
Total Depth = 30.5 feet
Dry after 5 minutes. Dry & blocked @ 30' @ end of day. Dry &
blocked @ 29-1/2' on 11/29/2021.
BORING LOG B-02 PLATE 3
Location: See Plate 1
GraphicLogrec %(rqd %)SampleProject Number : 24459
Date Completed : 11/24/2021
REED ENGINEERING
GROUP
Pocket Penetrometer Readings
Tons Per Sq. Ft. -
1 2 3 4 5 612344.5+4.5++
Depth
(ft)
5
10
15
20
25
30
35
Standard Penetration Tests
Blows per Foot -
10 20 30 40 50 60 Elev.
(ft)DESCRIPTION OF STRATA
GEOTECHNICAL CONSULTANTS -
locNEC West Sandy Lake Road and S.H. 121
POffice/Warehouse
loc2Coppell, Texas
50 Blows = 2 inches
50 Blows = 4 inches
72
520
515.5
514
506
501.5
497.5
496
SILTY CLAY, dark brown, hard, w/some sand & trace of
ironstones (CH)
-w/trace of calcareous concretions below 4.5'
SILTY CLAY, brownish-yellow & reddish-yellow, hard, w/sand,
calcareous concretions & calcareous deposits (CL - CH)
SANDY CLAY, light brown & brownish-yellow, hard, w/calcareous
deposits (CL)
SAND, light brown, very dense, fine (SP)
GRAVELLY SAND, fine to coarse (SW)
SAND, light brown, very dense, fine
(weathered sandstone) (SP)
Total Depth = 29.5 feet
Dry after 5 minutes. Dry & blocked @ 29-1/2' @ end of day. Dry
& blocked @ 29' on 11/29/2021.
BORING LOG B-03 PLATE 4
Location: See Plate 1
GraphicLogrec %(rqd %)SampleProject Number : 24459
Date Completed : 11/24/2021
REED ENGINEERING
GROUP
Pocket Penetrometer Readings
Tons Per Sq. Ft. -
1 2 3 4 5 612344.5+4.5++
Depth
(ft)
5
10
15
20
25
30
35
Standard Penetration Tests
Blows per Foot -
10 20 30 40 50 60 Elev.
(ft)DESCRIPTION OF STRATA
>>
GEOTECHNICAL CONSULTANTS -
locNEC West Sandy Lake Road and S.H. 121
POffice/Warehouse
loc2Coppell, Texas
50 Blows = 1/2 inch
520
511.5
506
502
497
492.5
SILTY CLAY, dark brown, hard, w/some sand & trace of
ironstones (CH)
SILTY CLAY, brownish-yellow, yellowish-brown & reddish-yellow,
very stiff to hard, w/sand & trace of iron stains (CH - CL)
SILTY CLAY, reddish-yellow & brownish-yellow, hard, w/some
sand (CH)
CLAYEY SAND, light brown, brownish-yellow & reddish-yellow,
w/trace or iron stains, fine (SC)
CLAYEY SAND, light brown & reddish-yellow, w/some gravel &
iron stains, fine to coarse (SC)
GRAVEL, brown, very dense, w/sand (GP)
Total Depth = 29.5 feet
Dry after 5 minutes. Dry & blocked @ 28-1/2' @ end of day. Dry
& blocked @ 28' on 11/29/2021.
BORING LOG B-04 PLATE 5
Location: See Plate 1
GraphicLogrec %(rqd %)SampleProject Number : 24459
Date Completed : 11/24/2021
REED ENGINEERING
GROUP
Pocket Penetrometer Readings
Tons Per Sq. Ft. -
1 2 3 4 5 612344.5+4.5++
Depth
(ft)
5
10
15
20
25
30
35
Standard Penetration Tests
Blows per Foot -
10 20 30 40 50 60 Elev.
(ft)DESCRIPTION OF STRATA
GEOTECHNICAL CONSULTANTS -
locNEC West Sandy Lake Road and S.H. 121
POffice/Warehouse
loc2Coppell, Texas
50 Blows = 4 inches
50 Blows = 4 inches
521
516.5
515
514.5
509
504.5
497.5
495
SILTY CLAY, dark brown, hard (CH - CL)
-w/trace of sand @ 4.5'
-w/brown @ 6'
SILTY CLAY, light brown & reddish-yellow, hard, w/trace of
calcareous concretions, calcareous deposits & sand (CL)
SANDY CLAY, light brown & brownish-yellow, hard, w/trace of
calcareous concretions (CL - CH)
SAND, reddish-yellow & light brown, dense, w/trace of silty clay
seams, fine (SP)
GRAVEL, brown, very dense, w/sand (GP)
SAND, light brown, w/trace of gravel, fine
(severely weathered sandstone) (SP)
Total Depth = 31 feet
Dry after 5 minutes. Dry & blocked @ 28-1/2' @ end of day. Dry
& blocked @ 29' on 11/5/2021.
BORING LOG B-05 PLATE 6
Location: See Plate 1
GraphicLogrec %(rqd %)SampleProject Number : 24459
Date Completed : 11/23/2021
REED ENGINEERING
GROUP
Pocket Penetrometer Readings
Tons Per Sq. Ft. -
1 2 3 4 5 612344.5+4.5++
Depth
(ft)
5
10
15
20
25
30
35
Standard Penetration Tests
Blows per Foot -
10 20 30 40 50 60 Elev.
(ft)DESCRIPTION OF STRATA
GEOTECHNICAL CONSULTANTS -
locNEC West Sandy Lake Road and S.H. 121
POffice/Warehouse
loc2Coppell, Texas
Seepage during drilling
519
516
510.5
506
502
496
490
SANDY CLAY, brown & yellowish-red, hard, w/trace of ironstones
(CL)
SILTY CLAY, dark brown, hard, w/some sand & trace of
ironstones (CH)
SILTY CLAY, brownish-yellow & reddish-yellow, hard, w/some
sand (CL - CH)
SANDY CLAY, light brown & reddish-yellow, hard (CL - CH)
SAND, light brown, reddish-yellow & gray, medium dense,
w/some silty clay seams, fine (SC - SP)
GRAVELLY SAND, brown, dense, fine to coarse (SW)
SANDY CLAY, light brown, very stiff, w/iron stains (CL)
Total Depth = 30.5 feet
Seepage encountered @ 30' during drilling. Dry after 7 minutes.
Dry & blocked @ 29-1/2' @ end of day. Dry & blocked @ 29' on
11/29/2021.
BORING LOG B-06 PLATE 7
Location: See Plate 1
GraphicLogrec %(rqd %)SampleProject Number : 24459
Date Completed : 11/24/2021
REED ENGINEERING
GROUP
Pocket Penetrometer Readings
Tons Per Sq. Ft. -
1 2 3 4 5 612344.5+4.5++
Depth
(ft)
5
10
15
20
25
30
35
Standard Penetration Tests
Blows per Foot -
10 20 30 40 50 60 Elev.
(ft)DESCRIPTION OF STRATA
GEOTECHNICAL CONSULTANTS -
locNEC West Sandy Lake Road and S.H. 121
POffice/Warehouse
loc2Coppell, Texas
50 Blows = 1/2 inch
520
515.5
514
513
504
496
SILTY CLAY, dark brown, hard (CH)
-w/trace of calcareous concretions below 4.5'
-w/brown & reddish-yellow below 6'
SILTY CLAY, light brown & reddish-yellow, hard, w/trace of sand
(CH)
CLAYEY SAND, light brown & reddish-yellow, fine (SC)
SAND, light brown & reddish-yellow, dense to very dense, w/trace
of gravel, fine to coarse (SP)
Total Depth = 31 feet
Dry after 3 minutes. Dry @ end of day. Dry & blocked @ 29-1/2'
on 11/24/2021.
BORING LOG B-07 PLATE 8
Location: See Plate 1
GraphicLogrec %(rqd %)SampleProject Number : 24459
Date Completed : 11/23/2021
REED ENGINEERING
GROUP
Pocket Penetrometer Readings
Tons Per Sq. Ft. -
1 2 3 4 5 612344.5+4.5++
Depth
(ft)
5
10
15
20
25
30
35
Standard Penetration Tests
Blows per Foot -
10 20 30 40 50 60 Elev.
(ft)DESCRIPTION OF STRATA
GEOTECHNICAL CONSULTANTS -
locNEC West Sandy Lake Road and S.H. 121
POffice/Warehouse
loc2Coppell, Texas
518
513.5
512.5
510.5
504
496
488.2
488
SILTY CLAY, dark brown, very stiff to hard, w/trace of sand (CL)
-w/brown & trace of calcareous concretions below 4.5'
SILTY CLAY, brownish-yellow & reddish-yellow, hard, w/some
calcareous deposits, calcareous concretions & trace of sand
(CL)
SILTY CLAY, light brown & reddish-yellow, very stiff to hard,
w/trace of calcareous concretions & sand (CL)
CLAYEY SAND, light brown & reddish-yellow, dense, fine to
medium (SC)
GRAVELLY SAND, brown & light brown, dense, fine to coarse
(SW)
-w/cobble @ 30'
SAND, light brown & reddish-yellow, very dense, w/trace of
gravel, fine to coarse (SW)
Total Depth = 31.5 feet
Dry after 3 minutes. Dry & blocked @ 30' @ end of day. Dry &
blocked @ 29-1/2' on 11/24/2021.
BORING LOG B-08 PLATE 9
Location: See Plate 1
GraphicLogrec %(rqd %)SampleProject Number : 24459
Date Completed : 11/23/2021
REED ENGINEERING
GROUP
Pocket Penetrometer Readings
Tons Per Sq. Ft. -
1 2 3 4 5 612344.5+4.5++
Depth
(ft)
5
10
15
20
25
30
35
Standard Penetration Tests
Blows per Foot -
10 20 30 40 50 60 Elev.
(ft)DESCRIPTION OF STRATA
GEOTECHNICAL CONSULTANTS -
locNEC West Sandy Lake Road and S.H. 121
POffice/Warehouse
loc2Coppell, Texas
512
510.5
SILTY CLAY, brown, hard, w/trace of sand, iron stains &
ironstones (CH)
SANDY CLAY, yellowish-brown & reddish-yellow, hard, w/trace of
iron stains & calcareous concretions (CH - CL)
Total Depth = 6 feet
Dry after 5 minutes. Dry & blocked @ 6' @ end of day.
BORING LOG B-09 PLATE 10
Location: See Plate 1
GraphicLogrec %(rqd %)SampleProject Number : 24459
Date Completed : 11/24/2021
REED ENGINEERING
GROUP
Pocket Penetrometer Readings
Tons Per Sq. Ft. -
1 2 3 4 5 612344.5+4.5++
Depth
(ft)
5
10
15
20
25
30
35
Standard Penetration Tests
Blows per Foot -
10 20 30 40 50 60 Elev.
(ft)DESCRIPTION OF STRATA
GEOTECHNICAL CONSULTANTS -
locNEC West Sandy Lake Road and S.H. 121
POffice/Warehouse
loc2Coppell, Texas
519
517.5
SANDY CLAY, dark brown, hard, w/iron stains (CL - CH)
SILTY CLAY, dark brown, hard, w/trace of sand & iron stains
(CH)
Total Depth = 6 feet
Dry after 5 minutes. Dry @ end of day.
BORING LOG B-10 PLATE 11
Location: See Plate 1
GraphicLogrec %(rqd %)SampleProject Number : 24459
Date Completed : 11/24/2021
REED ENGINEERING
GROUP
Pocket Penetrometer Readings
Tons Per Sq. Ft. -
1 2 3 4 5 612344.5+4.5++
Depth
(ft)
5
10
15
20
25
30
35
Standard Penetration Tests
Blows per Foot -
10 20 30 40 50 60 Elev.
(ft)DESCRIPTION OF STRATA
GEOTECHNICAL CONSULTANTS -
locNEC West Sandy Lake Road and S.H. 121
POffice/Warehouse
loc2Coppell, Texas
520
517
515.5
SILTY CLAY, dark brown, stiff to hard, w/trace of sand (CH)
-w/trace of calcareous concretions below 3'
SILTY CLAY, brown & yellowish-brown, hard, w/trace of
calcareous concretions, calcareous deposits & sand (CH)
Total Depth = 6 feet
Dry after 5 minutes. Dry @ end of day.
BORING LOG B-11 PLATE 12
Location: See Plate 1
GraphicLogrec %(rqd %)SampleProject Number : 24459
Date Completed : 11/24/2021
REED ENGINEERING
GROUP
Pocket Penetrometer Readings
Tons Per Sq. Ft. -
1 2 3 4 5 612344.5+4.5++
Depth
(ft)
5
10
15
20
25
30
35
Standard Penetration Tests
Blows per Foot -
10 20 30 40 50 60 Elev.
(ft)DESCRIPTION OF STRATA
GEOTECHNICAL CONSULTANTS -
locNEC West Sandy Lake Road and S.H. 121
POffice/Warehouse
loc2Coppell, Texas
520
515.5
514.2
SILTY CLAY, dark brown, very stiff to hard (CH)
-w/trace of calcareous concretions below 4.5'
-w/brownish-yellow & reddish-yellow @ 6'
Total Depth = 6 feet
Dry after 5 minutes. Dry @ end of day.
BORING LOG B-12 PLATE 13
Location: See Plate 1
GraphicLogrec %(rqd %)SampleProject Number : 24459
Date Completed : 11/23/2021
REED ENGINEERING
GROUP
Pocket Penetrometer Readings
Tons Per Sq. Ft. -
1 2 3 4 5 612344.5+4.5++
Depth
(ft)
5
10
15
20
25
30
35
Standard Penetration Tests
Blows per Foot -
10 20 30 40 50 60 Elev.
(ft)DESCRIPTION OF STRATA
GEOTECHNICAL CONSULTANTS -
locNEC West Sandy Lake Road and S.H. 121
POffice/Warehouse
loc2Coppell, Texas
521SILTY CLAY, dark brown, stiff to hard, w/trace of sand (CH)
Total Depth = 6 feet
Dry after 5 minutes. Dry @ end of day.
BORING LOG B-13 PLATE 14
Location: See Plate 1
GraphicLogrec %(rqd %)SampleProject Number : 24459
Date Completed : 11/23/2021
REED ENGINEERING
GROUP
Pocket Penetrometer Readings
Tons Per Sq. Ft. -
1 2 3 4 5 612344.5+4.5++
Depth
(ft)
5
10
15
20
25
30
35
Standard Penetration Tests
Blows per Foot -
10 20 30 40 50 60 Elev.
(ft)DESCRIPTION OF STRATA
GEOTECHNICAL CONSULTANTS -
locNEC West Sandy Lake Road and S.H. 121
POffice/Warehouse
loc2Coppell, Texas
518
513.5
SILTY CLAY, dark brown, hard (CL)
-w/trace of calcareous concretions & sand below 4.5'
Total Depth = 6 feet
Dry after 5 minutes. Dry @ end of day.
BORING LOG B-14 PLATE 15
Location: See Plate 1
GraphicLogrec %(rqd %)SampleProject Number : 24459
Date Completed : 11/23/2021
REED ENGINEERING
GROUP
Pocket Penetrometer Readings
Tons Per Sq. Ft. -
1 2 3 4 5 612344.5+4.5++
Depth
(ft)
5
10
15
20
25
30
35
Standard Penetration Tests
Blows per Foot -
10 20 30 40 50 60 Elev.
(ft)DESCRIPTION OF STRATA
GEOTECHNICAL CONSULTANTS -
locNEC West Sandy Lake Road and S.H. 121
POffice/Warehouse
loc2Coppell, Texas
518
516.5
515
SILTY CLAY, dark brown, very stiff, w/some sand (CH)
SILTY CLAY, brownish-yellow & gray, hard, w/trace of iron stains
& sand (CH)
-w/red @ 3'
Total Depth = 6 feet
Dry after 5 minutes. Dry @ end of day.
BORING LOG B-15 PLATE 16
Location: See Plate 1
GraphicLogrec %(rqd %)SampleProject Number : 24459
Date Completed : 11/23/2021
REED ENGINEERING
GROUP
Pocket Penetrometer Readings
Tons Per Sq. Ft. -
1 2 3 4 5 612344.5+4.5++
Depth
(ft)
5
10
15
20
25
30
35
Standard Penetration Tests
Blows per Foot -
10 20 30 40 50 60 Elev.
(ft)DESCRIPTION OF STRATA
GEOTECHNICAL CONSULTANTS -
locNEC West Sandy Lake Road and S.H. 121
POffice/Warehouse
loc2Coppell, Texas
517
513
511
508
499
494
489
SILTY CLAY, dark brown, hard, w/trace of sand (CH)
SILTY CLAY, brownish-yellow, brown & gray, hard, w/sand & some iron
stains (CH - CL)
-w/trace of root @ 6'
SILTY CLAY, brownish-yellow, light brown & gray, hard, w/iron stains &
some sand (CH)
GRAVELLY SAND, light brown, very dense, w/gravel, fine to coarse
(SW)
SAND, light brown, very dense, fine (SW)
SAND, light brown & brownish-yellow, very dense, w/some gravel, fine
to coarse (SP)
Total Depth = 29.5 ft
Seepage encountered @ 29' during drilling. Dry & blocked @ 28-1/2' @
end of day. Dry & blocked @ 26' on 11/29/2021.
50 Blows = 4-1/2 inches
50 Blows = 4-1/2 inches
50 Blows = 4 inchesSeepage during drilling
Project Number : 24459
Date Completed : 11/24/2021
REED ENGINEERING
1 3 4 4.5+
(weathered)
LIMESTONE
(unweathered)
(weathered)
SANDSTONE
(unweathered)
(weathered)
SHALE
(unweathered)
CLAYEY GRAVEL
(GRAVELLY CLAY)
SILTY SAND
(SM)
CLAYEY SAND
(SC)
Location: See Plate 1
SAND
(SP-SW)
Elev.
(ft)
Pocket Penetrometer Readings Tons Per Sq. Ft. -
1 2 3 4 5 6
BORING LOG B-01 PLATE 2
UNDISTURBED
(Shelby Tube &
NX-Core)
STANDARD
PENETRATION
TEST = Water level at time of drilling.
DISTURBED
THD CONE
PENETROMETER
TEST
4.5++
GROUP
2rec %(rqd %)SampleDepth
(ft)
5
10
15
20
25
.Office/Warehouse
GraphicLogPLATE 17
.NEC West Sandy Lake Road and S.H. 121
GRAVEL
(GP-GW)
SPT N VALUE
10 20 30 40 50 60
Fill
Type of Fill
Clay (CL)
(LL<50)
Clay (CH)
(LL>50)
SILT (ML)
(LL<50)
SILT (MH)
(LL>50)
= Subsequent water level and date.
KEYS TO SYMBOLS USED ON BORING LOGS
REED ENGINEERING
GROUP
DESCRIPTION OF STRATA
.
.Coppell, Texas
GEOTECHNICAL CONSULTANTS -
.
GEOTECHNICAL CONSULTANTS -
SPT
N-Values
(blows / foot)
Relative
Density
Pocket
Penetrometer
(T.S.F.)
Consistency
0 - 4 .....................Very Loose
4 - 10 .....................Loose
10 - 30 .....................Medium Dense
30 - 50 .....................Dense
50 + .....................Very Dense
<0.25 .................... Very Soft
0.25-0.50 ............... Loose
0.50-1.00 ............... Medium Stiff
1.00-2.00 ............... Stiff
2.00-4.00 ............... Very Stiff
4.00 + .................... Hard
SOIL PROPERTIES
COHESIONLESS SOILS
HARDNESS DIAGNOSTIC FEATURES
ROCK PROPERTIES
DEGREE OF WEATHERING DIAGNOSTIC FEATURES
COHESIVE SOILS
Very Soft ...............
Soft .......................
Moderately Hard ...
Hard ......................
Very Hard ..............
Can be dented with moderate finger pressure.
Can be scratched easily with fingernail.
Can be scratched easily with knife but not with fingernail.
Can be scratched with knife with some difficulty; can be broken by light to moderate
hammer blow.
Cannot be scratched with knife; can be broken by repeated heavy hammer blows.
Slightly Weathered .........
Weathered ......................
Severely Weathered .......
Completely Weathered ...
Slight discoloration inwards from open fractures.
Discoloration throughout; weaker minerals decomposed; strength somewhat less
than fresh rock; structure preserved.
Most minerals somewhat decomposes; much softer than fresh rock; texture becoming
indistict but fabric and structure preserved.
Minerals decomposes to soil; rock fabric and structure destroyed (residual soil).
KEYS TO DESCRIPTIVE TERMS ON BORING LOGS
REED ENGINEERING
GROUP
PLATE 18
GEOTECHNICAL CONSULTANTS -
SUMMARY OF LABORATORY TEST RESULTS PLATE 19
GEOTECHNICAL INVESTIGATION
OFFICE/WAREHOUSE
NEC WEST SANDY LAKE ROAD AND S.H. 121
COPPELL, TEXAS
Summary of Classification and Index Property Tests
Total Percent Percent
Moisture Liquid Plastic Plasticity Soil Passing Passing
Boring Depth Content Limit Limit Index Suction No. 200 No. 4
No. (feet) (%) (%) (%) (PI) (psf) Sieve Sieve
B-1 0.0 - 1.5 19.0 -- -- -- 7,440 -- --
1.5 - 3.0 14.6 54 17 37 29,220 -- --
3.0 - 4.5 13.6 -- -- -- 33,820 -- --
4.5 - 6.0 15.3 -- -- -- 32,360 -- --
9.0 - 10.0 11.1 51 17 34 26,670 -- --
14.0 - 15.0 15.6 -- -- -- 23,010 81 --
19.0 - 20.0 3.0 -- -- -- -- -- --
B-2 0.0 - 1.5 18.2 38 16 22 1,270 -- --
1.5 - 3.0 11.9 -- -- -- 40,160 -- --
3.0 - 4.5 12.6 -- -- -- 30,790 -- --
4.5 - 6.0 15.8 45 17 28 15,090 -- --
9.0 - 10.0 13.1 -- -- -- 1,320 59 --
14.0 - 15.0 14.4 -- -- -- 1,300 87 --
19.0 - 20.0 6.2 -- -- -- -- -- --
B-3 0.0 - 1.5 14.3 -- -- -- 24,210 -- --
1.5 - 3.0 15.6 -- -- -- 47,510 -- --
3.0 - 4.5 13.5 48 18 30 45,310 79 --
4.5 - 6.0 14.5 -- -- -- 45,180 -- --
9.0 - 10.0 13.9 -- -- -- 29,000 -- --
14.0 - 15.0 8.3 32 12 20 33,170 -- --
19.0 - 20.0 0.3 -- -- -- -- 3 --
SUMMARY OF LABORATORY TEST RESULTS PLATE 20
GEOTECHNICAL INVESTIGATION
OFFICE/WAREHOUSE
NEC WEST SANDY LAKE ROAD AND S.H. 121
COPPELL, TEXAS
(Continued)
Summary of Classification and Index Property Tests
Total Percent Percent
Moisture Liquid Plastic Plasticity Soil Passing Passing
Boring Depth Content Limit Limit Index Suction No. 200 No. 4
No. (feet) (%) (%) (%) (PI) (psf) Sieve Sieve
B-4 0.0 - 1.5 15.6 -- -- -- 2,340 -- --
1.5 - 3.0 14.9 50 18 32 27,370 -- --
3.0 - 4.5 13.6 -- -- -- 23,860 -- --
4.5 - 6.0 14.2 -- -- -- 13,750 -- --
9.0 - 10.0 20.1 -- -- -- 1,340 -- --
14.0 - 15.0 23.6 60 19 41 7,280 -- --
19.0 - 20.0 9.3 -- -- -- 6,230 43 --
24.0 - 25.0 7.6 -- -- -- 1,550 11 72
B-5 0.0 - 1.5 17.7 -- -- -- 25,380 -- --
1.5 - 3.0 14.7 -- -- -- 57,300 -- --
3.0 - 4.5 14.6 -- -- -- 63,540 -- --
4.5 - 6.0 14.9 48 15 33 47,010 81 --
9.0 - 10.0 17.3 -- -- -- 37,320 -- --
14.0 - 15.0 10.9 -- -- -- 23,770 54 --
19.0 - 20.0 4.2 -- -- -- -- -- --
B-6 0.0 - 1.5 14.3 -- -- -- 1,510 -- --
1.5 - 3.0 13.7 40 16 24 71,540 72 --
3.0 - 4.5 12.7 -- -- -- 62,740 -- --
4.5 - 6.0 12.8 -- -- -- 52,870 -- --
9.0 - 10.0 16.5 44 13 31 19,850 -- --
14.0 - 15.0 14.2 37 11 26 9,010 56 --
19.0 - 20.0 5.5 -- -- -- 6,390 -- --
SUMMARY OF LABORATORY TEST RESULTS PLATE 21
GEOTECHNICAL INVESTIGATION
OFFICE/WAREHOUSE
NEC WEST SANDY LAKE ROAD AND S.H. 121
COPPELL, TEXAS
(Continued)
Summary of Classification and Index Property Tests
Total Percent Percent
Moisture Liquid Plastic Plasticity Soil Passing Passing
Boring Depth Content Limit Limit Index Suction No. 200 No. 4
No. (feet) (%) (%) (%) (PI) (psf) Sieve Sieve
B-7 0.0 - 1.5 21.0 -- -- -- 11,280 -- --
1.5 - 3.0 17.1 -- -- -- 40,000 -- --
3.0 - 4.5 17.2 60 16 44 34,500 84 --
4.5 - 6.0 19.6 -- -- -- 29,690 -- --
9.0 - 10.0 17.3 56 18 38 18,410 92 --
14.0 - 15.0 16.1 -- -- -- 14,960 88 --
19.0 - 20.0 8.5 -- -- -- 24,060 38 --
24.0 - 25.0 2.5 -- -- -- -- -- --
B-8 0.0 - 1.5 21.6 47 18 29 1,590 -- --
1.5 - 3.0 16.4 -- -- -- 21,720 -- --
3.0 - 4.5 17.2 -- -- -- 16,420 -- --
4.5 - 6.0 14.0 45 16 29 12,450 -- --
9.0 - 10.0 20.5 -- -- -- 2,850 88 --
14.0 - 15.0 8.3 -- -- -- 1,300 22 --
19.0 - 20.0 5.9 -- -- -- -- 15 --
B-9 0.0 - 1.5 17.1 52 16 36 -- -- --
1.5 - 3.0 12.4 -- -- -- -- 77 --
3.0 - 4.5 13.6 -- -- -- -- -- --
4.5 - 6.0 14.7 -- -- -- -- -- --
B-12 0.0 - 1.5 21.5 -- -- -- -- -- --
1.5 - 3.0 12.5 53 16 37 -- 82 --
3.0 - 4.5 14.2 -- -- -- -- -- --
4.5 - 6.0 13.9 -- -- -- -- -- --
SUMMARY OF LABORATORY TEST RESULTS PLATE 22
GEOTECHNICAL INVESTIGATION
OFFICE/WAREHOUSE
NEC WEST SANDY LAKE ROAD AND S.H. 121
COPPELL, TEXAS
(Continued)
Summary of Classification and Index Property Tests
Total Percent Percent
Moisture Liquid Plastic Plasticity Soil Passing Passing
Boring Depth Content Limit Limit Index Suction No. 200 No. 4
No. (feet) (%) (%) (%) (PI) (psf) Sieve Sieve
B-14 0.0 - 1.5 17.8 45 16 29 -- 77 --
1.5 - 3.0 19.3 -- -- -- -- -- --
3.0 - 4.5 13.8 -- -- -- -- -- --
4.5 - 6.0 15.2 -- -- -- -- -- --
SUMMARY OF LABORATORY TEST RESULTS PLATE 23
Summary of Unconfined Compression Tests
Dry Unconfined
Moisture Unit Compressive
Sample Boring Depth Content Weight Strength
Legend No. (feet) (%) (pcf) (ksf)
A B-1 14.0 - 15.0 15.4 111.7 15.6
B B-2 9.0 - 10.0 12.5 115.3 5.0
C B-4 9.0 - 10.0 16.6 114.5 3.9
D B-4 14.0 - 15.0 23.4 103.8 9.4
E B-5 9.0 - 10.0 16.0 116.0 14.3
F B-6 4.5 - 6.0 12.2 118.6 29.5
SUMMARY OF LABORATORY TEST RESULTS PLATE 24
Summary of Unconfined Compression Tests
Dry Unconfined
Moisture Unit Compressive
Sample Boring Depth Content Weight Strength
Legend No. (feet) (%) (pcf) (ksf)
A B-7 14.0 - 15.0 15.3 113.0 15.7
B B-8 9.0 - 10.0 18.9 111.8 5.1
SUMMARY OF LABORATORY TEST RESULTS PLATE 25
Absorption Pressure Swell Test
Initial Final
Project No. 24459 Moisture Content (%) 10.9 18.6
Boring No. B-1 Penetrometer (tsf) 4.5++ 3.5
Depth (ft) 9-10 Dry Unit Weight (pcf) 111.1 108.6
Liquid Limit 51 Specific Gravity 2.71 2.71
Plasticity Index 34 Void Ratio 0.522 0.558
Cs 0.035 Saturation (%) 57 91
alpha 0.17 Spec. Volume 0.56 0.57
Percent Swell 2.3 Swell Pressure (psf) 2,590 250
SUMMARY OF LABORATORY TEST RESULTS PLATE 26
Absorption Pressure Swell Test
Initial Final
Project No. 24459 Moisture Content (%) 8.9 17.0
Boring No. B-3 Penetrometer (tsf) 4.5++ 3
Depth (ft) 14-15 Dry Unit Weight (pcf) 113.9 111.3
Liquid Limit 32 Specific Gravity 2.71 2.71
Plasticity Index 20 Void Ratio 0.485 0.519
Cs 0.039 Saturation (%) 50 88
alpha 0.16 Spec. Volume 0.55 0.56
Percent Swell 2.3 Swell Pressure (psf) 1,940 250
SUMMARY OF LABORATORY TEST RESULTS PLATE 27
Absorption Pressure Swell Test
Initial Final
Project No. 24459 Moisture Content (%) 17.3 22.4
Boring No. B-6 Penetrometer (tsf) 4.5++ 3
Depth (ft) 9-10 Dry Unit Weight (pcf) 111.9 105.8
Liquid Limit 44 Specific Gravity 2.73 2.73
Plasticity Index 31 Void Ratio 0.523 0.610
Cs 0.058 Saturation (%) 90 100
alpha 0.63 Spec. Volume 0.56 0.59
Percent Swell 5.7 Swell Pressure (psf) 7,780 250
SUMMARY OF LABORATORY TEST RESULTS PLATE 28
Absorption Pressure Swell Test
Initial Final
Project No. 24459 Moisture Content (%) 17.8 22.6
Boring No. B-7 Penetrometer (tsf) 4.5++ 3
Depth (ft) 9-10 Dry Unit Weight (pcf) 110.5 106.0
Liquid Limit 56 Specific Gravity 2.75 2.75
Plasticity Index 38 Void Ratio 0.553 0.618
Cs 0.050 Saturation (%) 88 100
alpha 0.49 Spec. Volume 0.56 0.59
Percent Swell 4.2 Swell Pressure (psf) 5,180 250
SPECIFICATIONS
Project No. 24459 - 1 - Water Injection Specifications
December 22, 2021 w/“Select” Fill Cap
GUIDELINE SPECIFICATIONS
SOIL MODIFICATION
WATER INJECTION W/“SELECT” FILL CAP
FOR
OFFICE/WAREHOUSE
NEC WEST SANDY LAKE ROAD AND S.H. 121
COPPELL, TEXAS
Site Preparation
Prior to the start of injection operations, the building pad should be brought to finished
subgrade, minus select fill, and staked out to accurately mark the areas to be injected.
Allowance should be made for two to four inches of swelling that may occur as a result of the
injection process.
Materials
1. The water shall be potable, with added surfactant, agitated as necessary to ensure
uniformity of mixture.
2. A nonionic surfactant (wetting agent) shall be used according to manufacturer's
recommendations; but in no case shall proportions be less than one part (undiluted)
per 3,500 gallons of water.
Equipment
1. The injection vehicle shall be capable of forcing injection pipes into soil with
minimum lateral movement to prevent excessive blowback and loss of slurry around
the injection pipes. The vehicle may be a rubber tire or trac machine suitable for the
purpose intended.
2. Slurry pumps shall be capable of pumping at least 3,000 GPH at 100 - 200 pounds
per square inch (psi).
Application
1. The injection work shall be accomplished after the building pad has been brought to
finished subgrade, minus select fill, and prior to installation of any plumbing,
utilities, ditches or foundations.
2. Adjust injection pressures within the range of 100 - 200 psi at the pump.
Project No. 24459 - 2 - Water Injection Specifications
December 22, 2021 w/“Select” Fill Cap
3. Space injections not to exceed five feet on-center each way and inject a minimum of
five feet outside building area. Inject 10 feet beyond building at entrances.
4. Inject to Elev. 510 or impenetrable material, whichever occurs first. Impenetrable
material is the maximum depth to which two injection rods can be mechanically
pushed into the soil using an injection machine having a minimum gross weight of 5
tons.
Injections to be made in 12-inch to 18-inch intervals down to the total depth with a
minimum of 7 stops or intervals. The lower portion of the injection pipes shall
contain a hole pattern that will uniformly disperse the slurry in a 360 radial pattern.
Inject at each interval to "refusal." Refusal is reached when water is flowing freely
at the surface, either out of previous injection holes or from areas where the surface
soils have fractured.
Fluid coming up around, or in the vicinity, of one or more of the injection probes
shall not be considered as soil refusal. If this occurs around any probe, this probe
shall be cut off so that water can be properly injected through the remaining probes
until refusal occurs for all probes. In any event, no probe shall be cut off within the
first 30 seconds of injection at each depth interval.
5. Multiple injections with water and surfactant will be required. The second injection
shall be orthogonally offset from the initial injection by 2-1/2 feet in each direction.
Subsequent injections shall be offset such that existing probe holes are not utilized.
6. A minimum of 48 hours shall be allowed between each injection pass.
7. Injections will be continued until a pocket penetrometer reading of 3.0 tsf or less is
obtained on undisturbed soil samples throughout the injected depth. The engineer
of record can waive this requirement if, in his opinion, additional injections will not
result in additional swelling.
8. At the completion of injection operations, the exposed surface shall be scarified and
recompacted to at least 95 percent of maximum density, ASTM D698, at or above
optimum moisture. A minimum of 12 inches of select fill shall be placed over the
injected subgrade as soon as is practical after completion of injection operations.
Select fill should be placed in maximum loose lifts of 8 inches and compacted to at
least 95 percent of maximum density, ASTM D698, at a moisture content between -
2 to +3 percentage points of optimum.
Project No. 24459 - 3 - Water Injection Specifications
December 22, 2021 w/“Select” Fill Cap
Observation and Testing
1. A full-time representative of Reed Engineering Group, Ltd. will observe injection
operations.
2. Undisturbed soil samples will be obtained continuously throughout the injected
depth, at a rate of one test hole per 10,000 square feet of injected area for
confirmation. Sampling will be performed a minimum of 48 hours after the
completion of the final injection pass.
Project No. 24459 - 1 - Water Injection Specifications
December 22, 2021 w/“Flexible Base” Cap
GUIDELINE SPECIFICATIONS
SOIL MODIFICATION
WATER INJECTION W/“FLEXIBLE BASE” CAP
FOR
OFFICE/WAREHOUSE
NEC WEST SANDY LAKE ROAD AND S.H. 121
COPPELL, TEXAS
Site Preparation
Prior to the start of injection operations, the building pad should be brought to finished
subgrade, minus flexible base, and staked out to accurately mark the areas to be injected.
Allowance should be made for two to four inches of swelling that may occur as a result of the
injection process.
Materials
1. The water shall be potable, with added surfactant, agitated as necessary to ensure
uniformity of mixture.
2. A nonionic surfactant (wetting agent) shall be used according to manufacturer's
recommendations; but in no case shall proportions be less than one part (undiluted)
per 3,500 gallons of water.
Equipment
1. The injection vehicle shall be capable of forcing injection pipes into soil with
minimum lateral movement to prevent excessive blowback and loss of slurry around
the injection pipes. The vehicle may be a rubber tire or trac machine suitable for the
purpose intended.
2. Slurry pumps shall be capable of pumping at least 3,000 GPH at 100 - 200 pounds
per square inch (psi).
Application
1. The injection work shall be accomplished after the building pad has been brought to
finished subgrade, minus flexible base, and prior to installation of any plumbing,
utilities, ditches or foundations.
2. Adjust injection pressures within the range of 100 - 200 psi at the pump.
Project No. 24459 - 2 - Water Injection Specifications
December 22, 2021 w/“Flexible Base” Cap
3. Space injections not to exceed five feet on-center each way and inject a minimum of
five feet outside building area. Inject 10 feet beyond building at entrances.
4. Inject to Elev. 510 or impenetrable material, whichever occurs first. Impenetrable
material is the maximum depth to which two injection rods can be mechanically
pushed into the soil using an injection machine having a minimum gross weight of 5
tons.
Injections to be made in 12-inch to 18-inch intervals down to the total depth with a
minimum of 7 stops or intervals. The lower portion of the injection pipes shall
contain a hole pattern that will uniformly disperse the slurry in a 360 radial pattern.
Inject at each interval to "refusal". Refusal is reached when water is flowing freely
at the surface, either out of previous injection holes or from areas where the surface
soils have fractured.
Fluid coming up around, or in the vicinity, of one or more of the injection probes
shall not be considered as soil refusal. If this occurs around any probe, this probe
shall be cut off so that water can be properly injected through the remaining probes
until refusal occurs for all probes. In any event, no probe shall be cut off within the
first 30 seconds of injection at each depth interval.
5. Multiple injections with water and surfactant will be required. The second injection
shall be orthogonally offset from the initial injection by 2-1/2 feet in each direction.
Subsequent injections shall be offset such that existing probe holes are not utilized.
6. A minimum of 48 hours shall be allowed between each injection pass.
7. Injections will be continued until a pocket penetrometer reading of 3.0 tsf or less is
obtained on undisturbed soil samples throughout the injected depth. The engineer
of record can waive this requirement if, in his opinion, additional injections will not
result in additional swelling.
8. At the completion of injection operations, the exposed surface shall be scarified and
recompacted to at least 95 percent of maximum density, ASTM D698, at or above
optimum moisture. A minimum of 6 inches of flexible base shall be placed over the
injected subgrade as soon as is practical after completion of injection operations.
Flexible base is defined as material meeting TxDOT Specifications, Item 247, Type
D, Grade 1 or 2 or better. This may include crushed concrete. Flexible base should
be compacted to at least 95 percent of the Standard Proctor density, at a moisture
content between -2 to +3 percentage points of optimum moisture.
Project No. 24459 - 3 - Water Injection Specifications
December 22, 2021 w/“Flexible Base” Cap
Observation and Testing
1. A full-time representative of Reed Engineering Group, Ltd. will observe injection
operations.
2. Undisturbed soil samples will be obtained continuously throughout the injected
depth, at a rate of one test hole per 10,000 square feet of injected area for
confirmation. Sampling will be performed a minimum of 48 hours after the
completion of the final injection pass.
Project No. 24459 - 1 - Water Injection Specifications
December 22, 2021 w/Lime-Modified Cap
GUIDELINE SPECIFICATIONS
SOIL MODIFICATION
WATER INJECTION W/LIME-MODIFIED CAP
FOR
OFFICE/WAREHOUSE
NEC WEST SANDY LAKE ROAD AND S.H. 121
COPPELL, TEXAS
Site Preparation
Prior to the start of injection operations, the building pad should be brought to finished
subgrade and staked out to accurately mark the areas to be injected. Allowance should be made
for two to four inches of swelling that may occur as a result of the injection process.
Materials
1. The water shall be potable, with added surfactant, agitated as necessary to ensure
uniformity of mixture.
2. A nonionic surfactant (wetting agent) shall be used according to manufacturer's
recommendations; but in no case shall proportions be less than one part (undiluted)
per 3,500 gallons of water.
Equipment
1. The injection vehicle shall be capable of forcing injection pipes into soil with
minimum lateral movement to prevent excessive blowback and loss of slurry around
the injection pipes. The vehicle may be a rubber tire or trac machine suitable for the
purpose intended.
2. Slurry pumps shall be capable of pumping at least 3,000 GPH at 100 - 200 pounds
per square inch (psi).
Application
1. The injection work shall be accomplished after the building pad has been brought to
finished subgrade and prior to installation of any plumbing, utilities, ditches or
foundations.
2. Adjust injection pressures within the range of 100 - 200 psi at the pump.
3. Space injections not to exceed five feet on-center each way and inject a minimum of
five feet outside the building footprint. Inject 10 feet beyond building at entrances.
Project No. 24459 - 2 - Water Injection Specifications
December 22, 2021 w/Lime-Modified Cap
4. Inject to Elev. 510 or impenetrable material, whichever occurs first. Impenetrable
material is the maximum depth to which two injection rods can be mechanically
pushed into the soil using an injection machine having a minimum gross weight of 5
tons.
Injections to be made in 12-inch to 18-inch intervals down to the total depth with a
minimum of 7 stops or intervals. The lower portion of the injection pipes shall
contain a hole pattern that will uniformly disperse the slurry in a 360 radial pattern.
Inject at each interval to "refusal". Refusal is reached when water is flowing freely
at the surface, either out of previous injection holes or from areas where the surface
soils have fractured.
Fluid coming up around or in the vicinity of one or more of the injection probes shall
not be considered as soil refusal. If this occurs around any probe, this probe shall be
cut off so that water can be properly injected through the remaining probes until
refusal occurs for all probes. In any event, no probe shall be cut off within the first
30 seconds of injection after refusal at each depth interval.
(The 30-second criterion is not the maximum time for each depth interval but a
minimum time. Additional time may be required to achieve refusal, dependent upon
the contractor's equipment.)
5. Multiple injections with water and surfactant will be required. The second injection
shall be orthogonally offset from the initial injection by 2-1/2 feet in each direction.
Subsequent injections shall be offset such that existing probe holes are not utilized.
6. A minimum of 48 hours shall be allowed between each injection pass.
7. Injections will be continued until a pocket penetrometer reading of 3.0 tsf or less is
obtained on undisturbed soil samples throughout the injected depth. The engineer
of record can waive this requirement if, in his opinion, additional injections will not
result in additional swelling.
8. At the completion of injection operations, the exposed surface shall be scarified and
blended with a minimum of 6 percent hydrated lime, or 27 pounds of lime per
square yard, to a depth of 6 inches. The subgrade shall then be recompacted to at
least 95 percent of maximum density, ASTM D698, at or above optimum moisture.
Project No. 24459 - 3 - Water Injection Specifications
December 22, 2021 w/Lime-Modified Cap
Observation and Testing
1. A full-time representative of Reed Engineering Group, Ltd. will observe injection
operations.
2. Undisturbed soil samples will be obtained continuously throughout the injected
depth, at a rate of one test hole per 10,000 square feet of injected area for
confirmation. Sampling will be performed a minimum of 48 hours after the
completion of the final injection pass.