PA1905-CS231108
Rebcon, LLC Date: 11-08-2023
1868 W. Northwest Hwy
Dallas, Texas 75220
RE: Final Acceptance Letter
Moore Road Park Boardwalk and Strom Improvements
Dear Jim Schumann:
Representatives of the City of Coppell have confirmed a final inspection of the
construction work for the referenced project. The two-year maintenance bonds have been
received. Maturity on the bonds will be two years from the date of this letter.
You may notify MS4 (City of Coppell) at any time during the two-year maintenance
period if stabilization of the site per the SWPPP permit can be demonstrated. If so,
complete and submit a Notice of Termination (NOT) to discontinue coverage under the
SWPPP permit.
A follow up inspection of the facilities will be conducted prior to the lapse of the two-
year bond period. If any punch list items are noted at that time, you will be contacted to
make repairs.
Sincerely,
Darryl Zbranek
Chief Construction Inspector
(469) 507-9095
dzbranek@coppelltx.gov
cc:
Michael Garza, P.E., Director of Public Works
Aaron Tainter, P.E., Assistant Director of Public Works
Steve Schubert, Chief Building Official
Tim Oates, Deputy Fire Chief
Jennifer Miller, Finance Director