TR9901-CS020108COPPgL
January 8, 2002
Jeffrey C. Bryan, President
Durable Specialties, Inc.
P.O. Box 381788
Duncanville, TX 75138
Traffic Signal Installation MacArthur Blvd. at Condor Drive TR 99-01
Change Order #1
Dear Mr. Bryan:
Attached are three copies of Change Order #1 for the referenced project. The change order includes
the addition of one 3M Opticom Detector plus necessary conduit. Please sign and return two
originals to the City of Coppell Engineering Department. We will need the executmt Change Order
prior to final acceptance of the project.
If you should have questions concerning this issue please feel free to contact Garreth or myself at
972/304-3679.
Sincerely,
Kenneth M. Griffin, P.E.
Director of Engineering and Public Works
cc: Garreth Campbell, Construction Inspector
CITY OF COPPELL
CHANGE OR EXTRA WORK ORDER
PROJECT:
MACARTHUR BLVD. ~ CONDOR TRAFFIC SIGNAL
Project # TR 99-01
CONTRACTOR:
OWNER: City of Coppell
CHANGE ORDER NO.: One
DurableSpecialties, Inc.
DATE: January 8, 2002
Item Description Quantity Unit Unit Total
Price
# 1 2" PVC Conduit - Trenched 240 LF 4.00
# 8 OPTICOM Cable 3 Conductor//20 AWG 240 LF 0.50
# 9 3M Opticom Detector I EA 1,700
960
120
1.700
Total Revision to Contract Amount
$2,780
Previous contract amount
Net increase in contract amount
Revised contract amount
Net increase in contract time of completion
Revised Contract time of completion
$ 57,700.00
$2,780.00
$60,480.00
200 Calendar Days
The contractor hereby accepts this Contract adjustment as a final and complete adjustment in full
accord and satisfaction of all past and future liability originating under any clause in the Contract by
reason of this revision to the Contract.
R~rne ty Engineer Date
/Agreed to by Contractor Date
Acce,.pted~y Owner Date