ST22-02-PT250613A copy of the approved permit must be on the job site at all times
Page 1 of 5RIGHT-OF-WAY USE PERMIT APPLICATION Rev.08/2020
Permit Valid for 120 Days From Date of Approval
All activity authorized by this permit shall be in accordance with
CHAPTER 283 of the Texas Local Government Code and the City of
Coppell Public Rights-of-Way Management ordinance No. 2001-944
Date of Submittal:__________________ Applicant’s Job # / Work Order #_____________________
Project Name / Location and Address:__________________________________________________
Permit Fee: $100.00 (No fee for applications submitted on behalf of Utility Companies with a current Public
Rights-of-Way Management Ordinance Registration). S.P.C.O.A. Certificate # ____________________
Utility Company Information:
Oncor Electric Delivery Atmos Energy Frontier Spectrum
Level 3 Other:________________________________________________________
Utility Company Representative:____________________________________________________
E-mail Address:__________________________________Telephone:______________________
Contractor Information:
General Contractor:______________________________________________________________
General Contractor Representative:_________________________________________________
E-mail Address:__________________________________Telephone:______________________
Project Information:
General Description of Proposed Construction (Attach Plan & Profile, See Page 5 for Example):
Estimated Start Date:_______________ Estimated Completion Date:_________________
Has 811 and/or utility companies been contacted 48 hours prior to locate existing utilities?
Yes No If No, state reason:_________________________________________________
Is removal of existing streets, alleys or sidewalks necessary? Yes No
If YES, repair must have a City inspection prior to completion. Call 972-304-3679.
Is closure of any traffic lanes or driveway approaches necessary? Yes No
If YES, a traffic control plan in accordance with TMUTCD standards must be submitted, and
the following departments must be notified of the location and duration of the closure:
Police Department, 972-304-3600 Fire Department, 972-304-3512
Street Department, 972-462-5150 Engineering Department, 972-304-3679
Traffic lane closures are allowed from 9:30 a.m until 3:30 p.m. ONLY unless otherwise
approved by the City Engineer.
--Work activity is permitted from 7:00 a.m. until 7:00 p.m., Monday through Friday only.--
06/12/2025
Howell and Bullock Relocation near 817 Howell Dr, Coppell, TX 75019
n
Patrick McKenzie
Patrick.Mckenzie@atmosenergy.com (972) 360-4428
Prime Utility Services
Jennifer Mosier
jmosier@primeutilityservices.com (469) 261-3011
INSTALL 500 FEET OF 4 INCH HDPE IP GAS MAIN. INSTALL 350 FEET OF 2 INCH IP HDPE GAS MAIN. REPLA
06/16/2025 10/15/2025
n
n
n
Right of Way Use Permit Application Page 2 of 5
This application, with signatures of Utility and Contractor representatives, must be submitted to the
Engineering Department for approval prior to commencing work. Printing your name and date on this
form indicates your acceptance of the terms and conditions of this application.
Applicant shall indemnify and forever hold harmless against the City of Coppell each and every claim,
demand, or cause of action that may be made or come against it by reason of or if any way arising out of
the closure, blocking, excavating, cutting, tunneling, or other work by the applicant under permit from
the City, if such permit is granted.
________________________________________ ___________________________________
Signature of Utility Company Representative Date
________________________________________ ___________________________________
Signature of Contractor Representative Date
________________________________________ ___________________________________
APPROVED City Representative Date
DENIED
Comments:
E-mail address to return completed permit:__________________________________________________
Submit permit application by e-mail to engineer@coppelltx.gov, or deliver application to the
Engineering Department, Town Center Business Park, 265 E Parkway Blvd, Coppell, TX 75019
SUMMARY OF REQUIREMENTS FOR WORK WITHIN
THE CITY OF COPPELL RIGHTS-OF-WAY OR EASEMENTS
1.A copy of the valid approved City of Coppell permit is required on the project site at all times.
2.Property owners (commercial and residential) adjacent to the project must be notified of the
project timeline and provided contractor names and phone numbers. No access to private
property without prior coordination with property owner.
3.Proper erosion control measures must be taken, in accordance with the Coppell Erosion Control
Ordinance No. 91-514.
4.Follow Texas MUTCD standards for work in traffic zones. Lane closures require the use of a
flashing arrow board for advance warning.
5.Grading shall be restored or improved, and sod replaced when necessary.
06/12/2025
06/12/2025
patrick.mckenzie@atmosenergy.com
Patrick McKenzie
Jennifer Mosier
X
Marcus Marion 06/13/2025
CONTACT CITY OF COPPELL ROW INSPECTOR TYLER BOYER (469-978-0818,
tboyer@coppelltx.gov) AT LEAST 48 HOURS PRIOR TO ANY CONSTRUCTION ACTIVITY
Right of Way Use Permit Application Page 3 of 5
6.Irrigation repairs must be performed in a timely manner.
7.Follow OSHA trench safety guidelines at all times.
8.Repair existing utilities that are damaged, including but not limited to: Clean-outs, water valves,
wastewater manholes, water lines, wastewater lines and storm sewer lines.
9. Density tests may be required, at applicant’s expense, in trench lines (ASTM).
10.Protection and repair of traffic control devices and signage is the responsibility of the contractor.
11.No work is to be done in collector roadways before 9:30 a.m. or after 3:30 p.m.
12.Prior request of work activity on weekends and holidays must be submitted in writing.
13.Utility line locates must be performed in advance of construction by calling 811 or logging on
to the Texas811 Portal at: http://www.texas811.org. Additional utility contacts are as follows:
COPPELL PUBLIC WORKS - OPERATIONS COPPELL PUBLIC WORKS - ENGINEERING
972-304-3679
DENTON COUNTY LEVEE DISTRICT
972-315-5019
T.C.E.Q. Region 4
817-588-5800
IRVING WATER UTILITIES
972-721-2281
ATMOS ENERGY
888-286-6700
EXPLORER PIPELINE
918-493-5100
ONCOR ELECTRIC DELIVERY
888-313-6862
972-462-5150
HOMEOWNER ASSOCIATIONS
Planning Department: H.O.A. List
F.E.M.A.
940-898-5399
DALLAS WATER UTILITIES
214-670-5111
AT&T
800-924-9420
COSERV Gas & Electric
940-321-7800
FRONTIER COMMUNICATIONS
800-584-3384
SPECTRUM CABLE
833-780-1880
14. Debris must be removed from work area daily and disposed of properly outside the City.
15.Streets, sidewalks and alleys must be kept clear of construction materials and debris.
16.“Clean-up” requires returning work area to pre-construction condition or better.
Right of Way Use Permit Application Page 4 of 5
Contact Coppell Public Works Operations at 972/462-5150 to schedule an inspection with
Utility and Streets personnel to verify that your project has been completed to City of
Coppell specifications. Failure to schedule verification inspection may delay future projects.
Franchise Utility Name:___________________________________________________________
Project Location or Address:_______________________________________________________
Sub-contractor Company Name:____________________________________________________
24 hr. Contact Number:____________________________________________________________
Date of Verification Appointment:_________________________ Time:____________________
-INFORMATION BELOW TO BE COMPLETED BY CITY OF COPPELL PUBLIC WORKS PERSONNEL-
Inspected by:_________________ of Utilities Maintenance Division on _______________
and found to be acceptable, not acceptable because:___________________________
Follow-up needed? No Yes, follow-up scheduled for:__________________________
Inspected by:__________________ of Streets Maintenance Division on _______________
and found to be acceptable, not acceptable because:___________________________
Follow-up needed? No Yes, follow-up scheduled for:__________________________
A copy of this completed notice can be e-mailed to the Coppell Public Works
Operations Division, or delivered to the address below:
City of Coppell Public Works Department, Operations Division
816 S. Coppell Road
Coppell, TX 75019
COMPLETION VERIFICATION NOTICE
Atmos Energy Corp
817 Howell Dr, Coppell, TX 75019
Prime Utility Services
(214) 620-7832
NO.DATE REVISION
DESIGN DRAWN DATE SHEET NO.JOB NO.
CITY OF COPPELL , DALLAS COUNTY, TEXAS
STREET RECONSTRUCTION (NORTH OF SOUTHWESTERN BOULEVARD)
HOWELL DRIVE AND BULLOCK DRIVE HOWELL DRIVE AND BULLOCK DRIVE7557 RAMBLER ROAD SUITE 1400
DALLAS, TX 75231
972.235.3031
TX REG. ENGINEERING FIRM F-14439
TX REG. SURVEYING FIRM LS-10193805
MATCH LINE - LINE WW-2 STA 3+00MATCH LINE - LINE WW-2 STA 3+00, LINE W-1 STA 4+308
WATER & WASTEWATER PLAN
TIE IN TO
EXISTING 3
INCH PE GAS
MAIN
INSTALL 500
FEET OF 4
INCH IP HDPE
GAS MAIN
INSTALL 350
FEET OF 2
INCH IP HDPE
GAS MAIN
INSTALL 4 INCH HPDE
GAS MAIN W/ 3' OF
CLEARANCE FROM
CITY UTILITIES INSTALL 3/4" SERVICE
LINE W/ 3' OF
CLEARANCE FROM
CITY UTILITIES
INSTALL 3/4" SERVICE
LINE W/ 3' OF
CLEARANCE FROM
CITY UTILITIES
INSTALL 3/4" SERVICE
LINE W/ 3' OF
CLEARANCE FROM
CITY UTILITIES
INSTALL 3/4" SERVICE
LINE W/ 3' OF
CLEARANCE FROM
CITY UTILITIES
RETIRE 500
FEET OF 3
INCH PE, 50
FEET OF 2
INCH PE, AND
575 FEET OF 2
INCH STEEL IP
GAS MAIN.
Assume a 48" depth of cover
for the proposed 8" water line
INSTALL 500 FEET OF 4
INCH HDPE IP GAS MAIN.
INSTALL 350 FEET OF 2
INCH IP HDPE GAS MAIN.
REPLACE 7 SERVICE LINES.
RETIRE 500 FEET OF 3 INCH
PE, 50 FEET OF 2 INCH PE,
AND 575 FEET OF 2 INCH
STEEL IP GAS MAIN.
· A gauge will be required near the
cut location. This gauge should be
installed before the line is blown
down, to verify that the line in
question is live. After blowdown, the
gauge will be rechecked to verify that
the line is now fully depressurized.
· A gauge will be required on both
sides of each shut-in location. These
gauges will monitor the pressure
upstream and downstream of the pipe
segment being taken out of service, to
ensure that pressures remain within
operational limits.
MATCH LINE - STA 4+00MATCH LINE - STA 4+00
NO.DATEREVISIONDESIGNDRAWNDATESHEET NO.JOB NO.CITY OF COPPELL , DALLAS COUNTY, TEXAS STREET RECONSTRUCTION (NORTH OF SOUTHWESTERN BOULEVARD)HOWELL DRIVE AND BULLOCK DRIVEHOWELL DRIVE AND BULLOCK DRIVE7557 RAMBLER ROAD SUITE 1400DALLAS, TX 75231972.235.3031TX REG. ENGINEERING FIRM F-14439TX REG. SURVEYING FIRM LS-10193805STA 4+00 TO STA 7+93.1125HOWELL DRIVE PLAN AND PROFILERETIRE 50 FEET OF 3 INCH PE, 50 FEET OF 2 INCH PE, AND 575 FEET OF 2 INCH STEEL IP GAS MAIN.INSTALL 500 FEET OF 4 INCH HDPE IP GAS MAIN. INSTALL 350 FEET OF 2 INCH IP HDPE GAS MAIN. REPLACE 7 SERVICE LINES. RETIRE 500 FEET OF 3 INCH PE, 50 FEET OF 2 INCH PE, AND 575 FEET OF 2 INCH STEEL IP GAS MAIN.· A gauge will be required near the cut location. This gauge should be installed before the line is blown down, to verify that the line in question is live. After blowdown, the gauge will be rechecked to verify that the line is now fully depressurized. · A gauge will be required on both sides of each shut-in location. These gauges will monitor the pressure upstream and downstream of the pipe segment being taken out of service, to ensure that pressures remain within operational limits.
NO.DATE REVISION
DESIGN DRAWN DATE SHEET NO.JOB NO.
CITY OF COPPELL , DALLAS COUNTY, TEXAS
STREET RECONSTRUCTION (NORTH OF SOUTHWESTERN BOULEVARD)
HOWELL DRIVE AND BULLOCK DRIVE HOWELL DRIVE AND BULLOCK DRIVE7557 RAMBLER ROAD SUITE 1400
DALLAS, TX 75231
972.235.3031
TX REG. ENGINEERING FIRM F-14439
TX REG. SURVEYING FIRM LS-10193805
10
WATER & WASTEWATER PLAN
INSTALL 350
FEET OF 2
INCH IP HDPE
GAS MAIN
INSTALL 2 INCH HDPE
GAS MAIN MIN 3' OF
CLEARANCE FROM
PROPOSED CITY
UTILITY
MATCH LINE - STA 4+00MATCH LINE - STA 4+00
NO.DATEREVISIONDESIGNDRAWNDATESHEET NO.JOB NO.CITY OF COPPELL , DALLAS COUNTY, TEXAS STREET RECONSTRUCTION (NORTH OF SOUTHWESTERN BOULEVARD)HOWELL DRIVE AND BULLOCK DRIVEHOWELL DRIVE AND BULLOCK DRIVE7557 RAMBLER ROAD SUITE 1400DALLAS, TX 75231972.235.3031TX REG. ENGINEERING FIRM F-14439TX REG. SURVEYING FIRM LS-10193805STA 0+00 TO STA 4+0035BULLOCK DRIVE PLAN AND PROFILETIE IN TO EXISTING 3 INCH PE GAS MAININSTALL 550 FEET OF 4 INCH IP HDPE GAS MAINRETIRE 500 FEET OF 3 INCH PE, 50 FEET OF 2 INCH PE, AND 575 FEET OF 2 INCH STEEL IP GAS MAIN.INSTALL 550 FEET OF 4 INCH HDPE IP GAS MAIN. INSTALL 350 FEET OF 2 INCH IP HDPE GAS MAIN. REPLACE 7 SERVICE LINES. RETIRE 500 FEET OF 3 INCH PE, 50 FEET OF 2 INCH PE, AND 575 FEET OF 2 INCH STEEL IP GAS MAIN.· A gauge will be required near the cut location. This gauge should be installed before the line is blown down, to verify that the line in question is live. After blowdown, the gauge will be rechecked to verify that the line is now fully depressurized. · A gauge will be required on both sides of each shut-in location. These gauges will monitor the pressure upstream and downstream of the pipe segment being taken out of service, to ensure that pressures remain within operational limits.