ST0001-CS020104 FROM THE DEPARTMENT OF ENGINEERING To-' From: Date: RE: File Suzan Taylor, C.I.P. Coordinator January 4, 2002 Creekview Drive & Freeport Parkway ST 00-01 January 3, Site Meeting The biweekly site meeting was held on the above referenced project. Below is a summary of the items discussed with Schrickel Rollins & Associates, Inc., and infrastructure services. Ramps at intersection of Creekview Drive and Freeport Parkway: · No ramp is required on the south side of the intersection. Developer will construct when the property is developed. · Contractor is required to construct ramps to ADA and TAS specifications. 2. Utility contractor is to start the installation of 12-inch water line on 01-04-02. 3. Contractor is scheduled to work on Saturday, January 5, 2002. 4. City Inspector advised isi that Freeport Parkway must be completed by March 1, 2002, in order to avoid a conflict with Wagon Wheel Park activities. Fence issue was resolved. · No additional compensation for filling stock pond on east side of Freeport Parkway. · SPA will prepare change order for fence and street lights. 6. Contractor will send over three copies of the updated schedule. 7. Contractor will send over the revised traffic control plan. "CITY OF COPPELL ENGINEERING - EXCELLENCE BY DESIGN"