In August 2001, the City of Coppell notified you of the proposed construction of the
Creekview Drive and Freeport Parkway Project. The project is in the general vicinity of
property owned or controlled by you (Lot 4R, Freeport North Addition) along the
existing section of Creekview Drive. Construction is scheduled to begin on or around
November 12, 2001, with an estimated construction time of 150 days. The contractor for
the project is infrastructure services, inc., and the contact person is Dennis R. Hammock,
General Superintendent.
Should you have any questions during the construction of the project, please contact
Larry Davis, Project Inspector, at 972-304-3684, Dennis Hammock at 214-769-9457, or
me at 972-304-7019.
Sincerely,
aylor
C.I.P.XC~ordinator
CC:
Larry Davis, City of Coppell
Dennis Hammock, isi
CO?FELL
October 26, 2001
Tsi Prime
650 South Royal Lane, Suite 200
Copp¢ll, Texas 75019
Creekview Drive and Freeport Parkway Project
ST 00-01
Notice of Proposed Construction
Dear Sir:
In August 2001, the City of Coppell notified you of the proposed construction of the
Creekview Drive and Freeport Parkway Project. The project is in the general vicinity of
property owned or controlled by you (Lot 4R, Freeport North Addition) along the
existing section of Creekview Drive. Construction is scheduled to begin on or around
November 12, 2001, with an estimated construction time of 150 days. The contractor for
the project is infi-astmcture services, inc., and the contact person is Dennis R. Hammock,
General Superintendent.
Should you have any questions during the construction of the project, please contact
Larry Davis, Project Inspector, at 972-304-3684, Dennis Hammock at 214-769-9457, or
me at 972-304-7019.
Sincerely,
Sc.U~.~ ~nator
CC:
Larry Davis, City of Coppell
Dennis Hammock, isi
COl'FELL
October 26, 2001
Mannatech Incorporated
600 South Royal Lane, Suite 200
Coppell, Texas 75019
Creekview Drive and Freeport Parkway Project
ST 00-01
Notice of Proposed Construction
Dear Sir:
In August 2001, the City of Coppell notified you of the proposed construction of the
Creekview Drive and Freeport parkway Project. The project is in the general vicinity of
property owned or controlled by you (Lot 4R, Freeport North Addition) along the
existing section of Creekview Drive. Construction is scheduled to begin on or around
November 12, 2001, with an estimated construction time of 150 days. The contractor for
the project is infrastructure services, inc., and the contact person is Dennis R. Hammock,
General Superintendent.
Should you have any questions during the construction of the project, please contact
Larry Davis, Project Inspector, at 972-304-3684, Dennis Hammock at 214-769-9457, or
me at 972-304-7019.
Sincerely,
Suzan/OXTaylor
C.I.P.~9~rdinator
CCi
Larry Davis, City of Coppell
Dennis Hammock, isi
255 pARKWAY ~ p O BOx 478 ~ COPPELL TX 75Oi9 ~ TEL 972/462 0022 · FAX 972/304 3673
T H £ C I T Y 0 F
C-OPP-EIJI
October 26, 2001
Durocraft Design Manufacturing
650 South Royal Lane, Suite 100
Coppell, Texas 75019
Creekview Drive and Freeport Parkway Project
ST 00-01
Notice of Proposed Construction
Dear Sir:
In August 2001, the City of Coppell notified you of the proposed construction of the
Creekview Drive and Freeport Parkway Project. The project is in the general vicinity of
property owned or controlled by you (Lot 4R, Freeport North Addition) along the
existing section of Creekview Drive. Construction is scheduled to begin on or around
November 12, 2001, with an estimated construction time of 150 days. The contractor for
the project is infrastructure services, inc., and the contact person is Dennis R. Hammock,
General Superintendent.
Should you have any questions during the construction of the project, please contact
Larry Davis, Project Inspector, at 972-304-3684, Dennis Hammock at 214-769-9457, or
me at 972-304-7019.
Sincerely,
Suz~aylor
C.I.P:,C~rdinator
CCi
Larry Davis, City of Coppell
Dennis Hammock, isi
T H E · C I T Y · O F
CO-15,iSEL£
October 26, 2001
Derse Exhibits
586 South Royal Lane
Coppell, Texas 75019
Creekview Drive and Freeport Parkway Project
ST 00-01
Notice of Proposed Construction
Dear Sir:
In August 2001, the City of Coppell notified you of the proposed construction of the
Creekview Drive and Freeport Parkway Project. The Project is in the general vicinity of
property owned or controlled by you (Lot 3A, Replat of a Portion of 5R, Freeport North
Addition) along the existing section of Creekview Drive. Construction is scheduled to
begin on or around November 12, 2001, with an estimated construction time of 150 days.
The contractor for the project is infrastructure services, inc., and the contact person is
Dennis R. Hammock, General Superintendent.
Should you have any questions during the construction of the project, please contact
Larry Davis, Project Inspector, at 972-304-3684, Dennis Hammock at 214-769-9457, or
me at 972-304-7019.
Sincerely,
C.I.P. {?>obrdinator
Larry Davis, City of Coppell
Dennis Hammock, isi
October 26, 2001
Crafanade Intemational, Inc.
650 South Royal Lane, Suite 100
Coppell, Texas 75019-3852
Creekview Drive and Freeport Parkway Project
ST 00-01
Notice of Proposed Construction
Dear Sir:
In August 2001, the City of Coppell notified you of the proposed construction of the
Creekview Drive and Freeport Parkway Project. The project is in the general vicinity of
property owned by you or controlled by you (Lot 3R, Freeport North Addition) along the
existing section of Creekview Drive. Construction is scheduled to begin on or around
November 12, 2001, with an estimated construction time of 150 days. The contractor for
the project is infrastructure services, inc., and the contact person is Dennis R. Hammock,
General Superintendent.
Should you have any questions during the construction of the project, please contact
Larry Davis, Project Inspector, at 972-304-3684, Dennis Hammock at 214-769-9457, or
me at 972-304-7019.
Sincerely,
Suza taylor
C.I.PkC, obrdinator
CC:
Larry Davis, City of Coppell
Dennis Hammock, isi
T H E · C I T Y 0 F
C-OPP t £
October 26, 2001
Cadillac Plastic
600 South Royal Lane, Suite 100
Coppell, Texas 75019
Creek'view Drive and Freeport Parkway Project
ST 00-01
Notice of Proposed Construction
Dear Sir:
In August 2001, the City of Coppell notified you of the proposed construction of the
Creekview Drive and Freeport Parkway Project. The project is in the general vicinity of
property owned or controlled by you (Lot 4R, Freeport North Addition) along the
existing section of Creekview Drive. Construction is scheduled to begin on or around
November 12, 2001, with an estimated construction time of 150 days. The contractor for
the project is infrastructure services, inc., and the contact person is Dennis R. Hammock,
General Superintendent.
Should you have any questions during the construction of the project, please contact
Larry Davis, Project Inspector, at 972-304-3684, Dennis Hammock at 214-769-9457, or
me at 972-304-7019.
Sincerely,
Suza~a ~. Taylor
C.I.P."C-bordinator
CC:
Lan3, Davis, City of Coppell
Dennis Hammock, isi
COPPELL
October 26, 2001
Michelle Wheeler
Senior Partner
Champion Partners
15601 Dallas Parkway, Suite 100
Addison, TX 75001
Creekview Drive and Freeport Parkway Project
ST 00-01
Notice of Proposed Construction
Dear Ms. Wheeler:
In August 2001, the City of Coppell notified you of the proposed construction of the
Creekview Drive and Freeport Parkway Project. The project is in the general vicinity of
property owned or controlled by you (Remainer Tract of CP-Coppell Industrial, Ltd.)
along the proposed section of Creekview Drive. Construction is scheduled to begin on or
around November 12, 2001, with an estimated construction time of 150 days. The
contractor for the project is infrastructure services, inc., and the contact person is Dennis
R. Hammock, General Superintendent.
Should you have any questions during the construction of the project, please contact
Larry Davis, Project Inspector, at 972-304-3684, Dennis Hammock at 214-769-9457, or
me at 972-304-7019.