ST9905-CS020104STATUS REPORT 5'77-~ ~) 05
Date: January 4, 2002
To~
Ken Griffin. P.E.
Teresa Turner
Susan Taylor
City of Coppell - Director of Engineering
City of Coppell - Graduate Engineer
City of Coppell - CIP Coordinator
From: Craig Bond, P.E. TranSystems - Project Engineer
CC:
Paul Padilla, P.E.
Joe Masterson, P.E.
Mike Hobbs
Transystems - Project Coordinator
TranSystems - Project Manager
TranSystems - Project Hydrologist
Bethel Road Project (Dallas/Tarrant County Line to Freeport Road)
Coppell, Texas
Utilities
· Have been contacted by TXU and provided with facility maps. TXU indicated 19
distribution poles will need to be relocated, as well as all gas lines in the project area.
· Have been contacted by a local Touch America representative. He will prepare a
letter identifying potential conflicts.
· Received a "Utility Reply Form" from SWBT. They provided a number to call to
make an appointment with SWBT to locate and/or expose facilities for our survey
crew to take elevation shots.
Roadway Design
Added the following items to the plan view of plan & profile sheets:
recessed curb inlet locations
· centerline driveway stationing & turn lane stationing
· proposed construction easements & proposed slope easements
· proposed wall/channel modifications at Royal Lane and Post Office drives
Hydrology/Hydraulics
· Draft Hydrology & Hydraulics Report in QA/QC review.
· Storm sewer design complete, with the exception of HGL.Items
For Discussion At Next Meeting With City
· Relocation of existing water/sewer lines and preferred locations.
· Relocation of existing fiber, cable, telephone, electric and gas. Several utilities asked
about leaving in place and using traffic rated manholes.
· Drain outlets between R/W and top of back slope for poor drainage areas.
· Meeting with DFW Airport to discuss detention ponds and construction & slope
easements.