ST9801-AG001212AGENDA REQUEST FORM COl'FELL ~ ~~'~° CITY COUNCIL MEETING: December 12, 2000 ITEM ITEM CAPTION: Consider approval of Change Order #5 to the Coppell Road Project #ST98-01 for the installation of approximately 236 additional sprinkler heads to the irrigation system to accommodate the ten foot Hike and Bike Trail in the amount of $41,964.00 to Ed Bell Construction Company; and authorizing the City Manager to sign. TITL~ __Asst. City EngineerJ STAFF COMM~: ~ APPROVED BY CiTY coUNCIL DATE ~ See attached memo. BUDGET AMT. $ AMT. EST. $ +¥BID $ .~ FINANCIAL COMMENTS: The funds for this item are available from the Street CIP Funds. Agenda Request Form - Revised 5/00 Document Name: #eng3 MEMORANDUM FROM THE DEPARTMENT OF ENGINEERING To: Mayor and City Council Members From: Michael A. Martin, P.E., Asst. City Engineer Date: December 12, 2000 Consider approval of Change Order #5 to the Coppell Road Project #ST 98-01 for the installation of approximately 236 additional sprinkler heads to the irrigation system to accommodate the ten foot Hike and Bike Trail in the amount of $41,964.00 to Ed Bell Construction Company; and authorizing the City Manager to sign. Ed Bell Construction Company is in the final stages of completing the reconstruction of Coppell Road. All utilities and concrete paving for the roadway and Hike and Bike Trail have been installed. Major items that need to be completed by the contractor are the installation of the guardrails, reestablishing the irrigation systems along the east side of Coppell Road and the placement of sod. It has been brought to the City's attention by the contractor that the estimated 20 sprinkler heads indicated in the contract document need to be increased to approximately 236 sprinkler heads. The increase has been brought about due to the construction of the roadway, the installation of the 1 O-foot Hike and Bike Trail and sidewalks. When the project was bid it was unclear how much of the existing irrigation system would be affected. There were no available irrigation plans in the Engineering Department showing the location of the underground irrigation systems. As the project progressed, it became evident that all five irrigation systems along the east side of Coppell Road would be affected by the construction. Because the number of sprinkler heads increased from 20 to approximately 236, staff asked the contractor to revise its cost per sprinkler head. Currently, the contract has a bid price of $250 per sprinkler head at a total cost of $5,000. If the same bid price was used for the additional sprinkler heads, the total cost to adjust the heads would total $59,000. The contractor has agreed to revise his bid price to a total lump sum cost of $46,964. This amount breaks down to a cost of approximately $199 per sprinkler head, a cost difference of $51 per sprinkler head. In reality, adjusting the sprinkler heads means: installing new irrigation lines, sprinkler heads, wiring, and valves; repairing damaged controllers; designing a parallel system to irrigate on both sides of the sidewalk and Hike and Bike Trail; and any other incidentals necessary to ensure all systems are fully functional at the completion of the project. Providing a lump sum price for all the irrigation systems on the east side of Coppell Road ensures that the contractor will be responsible for making sure all the irrigation systems are working at the completion of the project. Staff recormnends approval of Change Order #5 and will be available to answer any questions at the Council meeting. "CITY OF COPPELL ENGINEERING - EXCELLENCE BY DESIGN" CITY OF COPPELL CHANGE OR EXTRA WORK ORDER PROJECT: CONTRACTOR: OWNER: CHANGE ORDER NO.: Item Coppell Road Reconstruction Project # ST98-O1 Ed Bell Construction CiO~ of Coppell $ Description DATE: 12/12,00 Quanffiy Unit Unit Price Total Irrigation System Revisions ADD: - DELETE: lb-64R Fully functional irrigation I LS 46,964.00 46,964.00 systems Install new irrigation systems along the east side of Coppell Road from approximately Sra. 3+00 to 38+00 including all materials needed to make the system operational Ib-64 Adj. existing irrigation sprinklers Total Revision to Contract Amount Previous contract amount Net increase in contract amount Revised contract amount Net increase in contract time of completion Revised Contract time of completion 20 EA 250.00 (5,000.00) $41,964.00 $2,060,958.73 $41,964.00 $2,102,922.73 .~3~alendar Days The contractor hereby accepts this Contract adjustment as a final and complete adjustment in full accord and satisfaction of all past and future liability originating under any clause in the Contract by reason of this revision to the Contract. commended I~y C-/] ~,~/~.f/~]r Date. FAX (2,14~ 352:~201 TELEPHONE (214) 358-6581 ED BELL CONSTRUCTION COMPANY POST OFFICE BOX 540787 10605 HARRY HINES DALLAS, TEXAS 75354-0787 DALLAS, TEXAS 75220 Novembc~ I 7. 2000 Mr. Michae! A Martin, P.E. Engineering and Public Works City of Coppcll 255 Parkwa) Blvd. Coppell, Texas 75019-4409 Coppc}l Road Reconstruction SII 12 1 to Sandy Lake Road Coppc}l Project #: ST 98-01 In response to your request for revised pricing for the sprinkler head adjustment pay item, we have been concerned about the open cuded nature of the bid item and the additional risk assumed by EBCC if we lower our price per head. Thc pay ilcnl description defines the project limits for which EBCC must ensure that all sprinkler systems are fully functional. The pay item also states that EBCC is responsible for all work necessary to ensure that all sprinkler systems wilhm Ihe defined limits are fully functional and that all costs associated with ensuring that the sprinkler systems arc i,dly l'unctioual must be incorporated into the sprinkler head ac[iustment pay item. With a quantity of only t~vcnt? hca,is set up in th contract, it was our belief that the work would primarily involve investigating the location o1' Iht heads, capping sprinkler leads at the ROW, and extending those leads into the ROW after completion of the Based upon Ibc investigations completed to date and evaluations conducted by our irrigator, it is our belief that 236 heads will be ~cquired and the majority of the problems with the existing systems have been identified. Within the defined projccl Imfits, EBCC has encountered five separate sprinkler systems that had to be completely removed and replaced x~ ithin the City's ROW. These systems are spread out over 3500 LF of the project and will require valve work, xx n'ing, new water line, and new heads. Our lump sum price for this work is $46,964. As stated p~ cx iously, EBCC has removed the sprinkler systems and and is currently in the process of replacing the systems. Wc a~ e proceeding with the work necessary to complete this prqiect and the sprinkler work that must be completed p~ n~t to completion of the parkway. The work in question is withio the scope of work defined by the sprinkler head a4justment pay item and must be completed prior to completion of the parkway. If it is the City's iutent to oct pa3 ibr tiffs work or to remove tiffs wink liom EBCC's con~act, then please dflcct EBCC to stop wink on this item l'Icase note that EBCC has already incurred costs associated with this bid item and would expect to be compeusatcd lin fllose costs should the City eject to remove this item fi'om the contract If you ha~c anx qoestions regarding this information, don't hesitate to contact our office. M~ \ Scott Maughn, E.I.T., Freese and Nichols, Inc., 1701 N. Market Street ~uitc 500 LB51, Dallas, Texas 75202 AN EQUAL OPPORTUNITY EMPLOYER December 14, 2000 Doug Teter, Vice President Ed Bell Construction 10605 Harry Hines Blvd. P.O. Box 540787 Dallas, TX 75354-0787 Re: Coppell Road Project # ST98-01 Change Order #5 Dear Mr. Teter: Attached are three originals of Change Order #5 for the referenced project. Please review the change order, sign and return two originals to me. Keep one copy for your file. If you have any questions concerning this issue please feel free to contact me at 972/304-3686. Sincerely, Kenneth M. GrilTm, P.E. Director of Engineering/Public Works FA~((314) 352-3201 TELEPHONE (214) 358-6581 ED BELL CONSTRUCTION COMPANY POST OFFICE BOX 540787 10605 HARRY HINES DALLAS, TEXAS 75354-0787 DALLAS, TEXAS 75220 January 31, 2002 Mr. Kenneth M. Griffin, P.E. Director of Engineering and Public Works City of Coppell 255 Parkway Blvd. Coppell, Texas 75019-4409 Re~ Coppell Road Reconstruction SH 121 to Sandy Lake Road Coppell Project #: ST 98-01 Dear Mr. Griffin: Enclosed for your review and incorporation into the contract are two executed copies of change order #5 for the referenced project. crely, q~tr~l°n Robert D. Weber Project Manager Company XC~ Mr. A. Scott Maughn, E.I.T., Freese and Nichols, Inc., 1701 N. Market Street Suite 500 LB51, Dallas, Texas 75202 AN EQUAL OPPORTUNITY EMPLOYER