Amberpoint BP-LR020129WATER INJECTION OBSERVATION
Date of Service:
Client No.:
Client:
01/29/02
3181
Transwestern Commercial Services
5001 Spring Valley Rd., Suite 600 W
Dallas, TX 75244
Report No.:
Project No.:
Project:
94021029.0024
94021029
Amberpoint Building No. 1
Amberpoint Bus. Pk ~ Coppell
Coppell, Texas
Location:
Building Pad
General Contractor: Hill & Wilkinson
Injector: Jowell
Procedure:
On this date, a representative of HBC Engineering, Inc. observed the injection of water at this
site. During the injection process, the following observations were recorded.
Pass No.: 3rd No. of Probes: 4 Probe Length: 12 feet
OBSERVATION
SPECIFICATION Yes No N/A
Surfactant added to each load. X
Injection pressure 50 to 200 psi at manifold. X
Injection downward in 18 inch intervals. X
Total depth of injection was 10 feet. X
Spacin8 of injection was 5 feet maximum. X
Iniection to refusal at each location. X
comments: On this date, four rigs were working this area.
Technician: S. Campbell
Report Distribution:
( 1 ) Transwestern Cormnercial Services
(1) O'Brien & Associates. Inc.
(1) TechniStmctures, Inc.
(1) City of Coppoll - Constr. Insp.
(1) City of Coppell - Bidg Insp.
(1) ltill & Wilkinson, Ltd.
IBC Engineering, Inc.
Eu~our
Principal
9911W This report is exclusively for the use of the client indicated above and shall not be reproduced in full without written approval of HBC Engineer