Amberpoint BP-LR020227WATER INJECTION OBSERVATION
ENGINEERING, 1NC.
Date of Service:
Client No.:
Client:
Location:
Procedure:
02/27/02
3181
Transwestem Commercial Services
5001 Spring Valley Rd. Suite 600 W
· Dallas, TX 75244
Report No.:
Project No.:
Project:
94021029.0079
94021029
Amberpoint Building No. 1
Amberpoint Bus. Pk. @ Coppell
Coppell, Texas
Building Pad
General Contractor: Hill & Wilkinson
Injector: Jowell
On this date, a representative of HBC Engineering, Inc. observed the injection of water at this
site. During the injection process, the following observations were recorded.
Pass No.: 5th No. of Probes: 4 Probe Length: 12 feet
OBSERVATION
SPECIFICATION Yes No N/A
Surfactant added to each load. X
Injection pressure 50 to 200 psi at manifold. X
Injection downward in 18 inch intervals. X
Total depth of injection was 10 feet. X
Spacing of injection was 5 feet maximum. X
I[iection to refusal at each location. X
Comments:
Technician: K. Douglas
Report Distribution:
(l)Transwestern Commercial Services
(1) O'Bfien & Associates, Inc.
(1) TechniStmctures, Inc.
(I) City of Coppell - Constr. lnsp.
(1) City of Coppell - Bldg Insp.
(1) Hill & Wilkinson, Ltd.
( I ) Halff Associates
(1) State Farm Insurance
Engineering, Inc.
Eugene Harbour
Principal
9911w This report is exclusively for the use of the client indicated above and shall not be reproduced in full without wdtten approval of HBC Engineer
WATER INJECTION OBSERVATION
Date of Service: 02/27/02 Report No.:
Client No.: 3181 Project No.:
Client: Transwestern Commercial Services Project:
5001 Spring Valley Rd. Suite 600 W
Dallas, TX 75244
94021029.0078
94021029
Amberpoint Building No. 1
Amberpoint Bus. Pk. @ Coppell
Coppell, Texas
Location: Building Pad
General Contractor: Hill & Wilkinson
Injector: Jowell
Procedure:
On this date, a representative of HBC Engineering, Inc. observed the injection of water at this
site. During the injection process, the following observations were recorded.
Pass No.: 3rd No. of Probes: 4 Probe Length: 12 feet
OBSERVATION
SPECIFICATION Yes No N/A
Surfactant added to each load. X
Injection pressure 50 to 200 psi at manifold. X
Injection downward in 18 inch intervals. X
Total depth of injection was 10 feet. X
Spacing of iniection was 5 feet maximum. X
Injection to refusal at each location. X
Comments:
Technician: S. Campbell
Report Distribution:
( I )Transwestera Commercial Services
(1) O'Brien & Associates, Inc
( 1 ) TechniStructures, Inc.
(I) City of Coppell - Constr. Insp.
( 1 ) City of Coppell - Bldg. Insp.
(1) Hill & Wilkinson, Ltd
( I ) Halff Associates
(1) State Farm Insurance
Engineering, Inc.
Eugene Harbour
Principal
9911w This report is exclusively for the use of the client indicated above and shall not be reproduced in full without written approval of HBC Engineer