WA9701-AG020409 REQUEST FORM
COFFELL AGENDA
~ ~' ~ ~ '~,~ ~*~~CITY COUNCIL MEETING: April 9, 2002 ITEM # 8/D
ITEM CAPTION: Consider approval of entering into a contract with Birkhoff, Hendricks & Conway
Consulting Engineers for the design of a 16" water line on Belt Line/Denton Tap from Bethel Road to
Airline Drive in an amount not to exceed $57,240; and authorizing the City Manager to sign.
APPROVED BY
CITY COUNCIL
ON ABOVE DATE
Motion to Approve
M - Tunnell
S - York
Vote - 7-0
SUBMITTED BY: Kenneth M. Griffin, P.E.
TITLE: Director of Engineering/Public Works
STAFF COMMENTS:
This water line was identified in the Water Distribution System Master Plan as an undersized water line.
Currently, there is a 16" water line north of Bethel Road up to S.H. 121 and there is a 12" water line south of
Airline Drive to Lakeshore Drive. This water line currently exists as an 8" water line. Upgrading this water
line to a 16" water line will complete all deficiencies along Belt Line Road/Denton Tap Road from Lakeshore
to S.H. 121.
Staff recommends approval of the contract with Birkhoff, Hendricks & Conway in an amount not to exceed
$57,240. Staff will be available to answer any questions at the Council meeting.
BUDGET AMT. $
FINANCIAL COMMENTS:
project.
AMT. EST. $ +k-BID $
Funds have been allocated in the 1991 Water/Sewer CIP account for this
DIR. INITIALS: ~ . -='
~Grlffin g.?
Agenda Request Form - Revised 5/00
FIN. REVIEW:
CITY MANAGER REVIEW:
Document Name: #engl-lAR.doc
JOlflq W. BIKICHOFF, P E.
RONALD V COIqWAY, PE
CO2kY C HENDRICKS, PE.
BIRKHOFF, HENDRICKS & CONWAY, L.L.P.
CONSULTING ENGINEERS
7502 Greenville Ave., #220 Dallas, Texas 75231 Fax (214) 361-0204
March 25, 2002
Phone(214) 361-7900
Mr. Kenneth M. Grif£m, P.E.
City of Coppell
Post Office Box 478
Coppell, Texas 75019
Attention: Ms. Suzan C. Taylor, C.I.P. Coordinator
Re: Denton Tap/Beltline Road Water Line (WA 97-01)
Revised Engineering Services Agreement
Dear Mr. Griffin:
We are pleased to submit this revised proposal for furnishing engineering services required for the preparation
of plans, specifications, bidding documents and construction administration of the Denton Tap/Beltline Road
Water Line Project.
The project consists of approximately 4,000 linear feet of 16-inch waterline along Denton Tap/Beltline Road,
fi.om Airline Drive to Bethel Road. The enclosed project location map more specifically defines the project
limits. We recommend the City budget a construction amount in the range of $440,000 for this project and are
enclosing our itemized opinion of construction cost for your review.
We have made a preliminary investigation of a proposed ~vater line route. Although it appears the water line
can be placed within the fights-of-way of Denton Tap/Beltline Road, we are including a nominal amount for
boundary surveys, deed research, and preparation of plats and field note descriptions in our special sen-ices
phase of the agreement in the event these service are required.
Our engineering services for this project shall include the following:
BASIC SERVICES
A. Design Phase
Preparing construction plans, specifications and bidding documents for construction of the Denton
Tap/Beltline Road Water Line project. The design phase of this project shall include:
· Construction Plan- Profile Sheets prepared at a scale of not less than 1"= 40'
· Standard Details
· Special Details
· Cover Sheet, Location Map and Sheet Index
Mr. Kenneth M. Griffin, P.E.
Director of Engineering & Public Works
City of Coppell
Denton Tap/Beltline Road Water Line Engineering Fee Proposal
March 25, 2002
Page Number 4
· Submittals to State Regulatory Agencies, as required
· Preparation of required Highway, Railroad and Utility Permits, as required
· Coordination with other Utility Companies
· Design Review Meetings
· Opinion of Probable Construction Estimate
· Preparation of Specifications and Contract Documents
· Assist in procuring Geotechnical Engineering information or reports as the project requirements
dictate
· After review and approval of conceptual plan, print preliminary plans and specifications for review
by the City and the Utility Companies.
Bidding Phase
· Assist in Advertising for Bids
· Opening, Tabulation and Evaluating Bids received
· Reviewing the qualification of the low bidder(s) and preparing recommendations for award of a
Construction Contract
Construction Administration
· Assist in development of Quality Control and Materials Testing contract
· Consult with Owner as to actions based on Engineering matters
· Assist in execution of Contract Documents by preparing five (5) sets of conformed contract
specifications
Assist in and attend a Pre-Construction Conference as Required
· Make periodic visits to the job-site
· Preparing and issuing routine Field Changes with the Owners approval
· Preparing and issuing routine Change Orders with the Owners approval
· Review of Shop Drawings, Test Reports and other data
· Preparation of Monthly and Final Pay Requests
· Conduct a Final Inspection w/th the Owner
· Preparation and delivery of one set of record drawings on mylar sepias to the City
Mr. Kenneth M. Griffin, P.E.
Director of Engineering & Public Works
City of Coppell
Denton Tap/Beltline Road Water Line Engineering Fee Proposal
March 25, 2002
Page Number 4
II.
SPECIAL SERVICES
Design Surveys
· Construction Surveys
· Property Surveys, if required
· Deed Research, if required
· Preparation of Easement Documents, if required
· Printing of final plans and specifications for dism'oution to prospective bidders and the successful
contractor. Plans are to be distributed from the offices of Birkhoff, Hendricks & Conway, L.L.P.
Geotechnical Evaluation
above-described services, we propose to be compensated on the following basis:
For the
BASIC SERVICES
Compensation for basic services shall be on a lump sum basis of $38,500 in accordance with the schedule
below:
$30,800
A. Design Phase ....................................................................................................
B. Bidding Phase ...................................................................................................... $ !,925
C. Construction Phase ............................................................................................. $5,775
II. SPECIAL SERVICES
Compensation for Special Services shall be based on our actual salary cost times 2.35, with expenses
invoiced at actual cost times 1.15.
We suggest you budget an amount not to exceed $18,740 in the following amounts for the Special Services:
A. Design Surveys ................................................................................................... $7,680
B. Construction Surveys .......................................................................................... $1,800
C. Boundary Surveys (if required) ................................................................................ $960
D. Preparation of Easement Documents (if required) ................................................. $4,000
E. Printing of Final Plans and Specifications ........................................................... $1,800
F. Geotechnical Evaluation ..................................................................................... $2,500
Mr. Kenneth M. Griffirg P.E.
Director of Engineering & Public Works
City of Coppell
Denton Tap/Beltline Road Water Line Engineering Fee Proposal
March 25, 2002
Page Number 4
If you are in agreement with this proposal, please have one copy executed on behalf of the City of Coppell and
returned to our office, or if you prefer we will be pleased to assist in the preparation of the standard engineering
agreement on the City's contract form. We stand ready to begin work hmnediately on this project upon your
authorization to proceed and look forward to our continued working relationship with you, your staff and the
City of Coppell. We are available at your convenience to discuss this proposal further.
· :; ......... ~ ..... ,._:
' PROPOSED WATER LINE
BIRKHOFF, HENDRICKS & CONWAY, L.L.P.
CONSULTING ENGINEERS
Project No.
Client:
Project:
CITY OF COPPELL, TEXAS
Denton Tap Road Water Line
16-inch Water Line from Airline Drive to Bethel Road
Date:
3/7/02
By: G.C.H.
ENGINEER'S OPINION OF CONSTRUCTION COST
ltemNo. I Description I Quantity I Unit I Price I Amount
I Furnishing and Installing 16-Inch PVC Waterline with Embedment 3,600 L.F. $ 42.00 $ 151,200.00
Furnish & Install 16" PVC Waterline in 24" Dia., 3/8" Thick
2 Encasement Pipe by Other than Open Cut 400 L.F. $ 275.00 $ 110,000.00
3 Furnishing and Installing 16-Inch Butterfly Valve 5 Ea. $ 3,800.00 $ 19,000.00
4 Furnishing and Installing 24-inch Butterfly Valve 2 $ 4,800.00
5 Connecting to Existing 12-Inch Waterline 1 Ea. $ 2,500.00 $ 2,500.00
6 Connection to Exsiting 24-inch Water Line 1 Ea. $ 8,500.00 $ 8,500.00
7 Connection to Existing 16-inch Water Line I Ea. $ 5,000.00 $ 5,000.00
8 Furnishing and Installing Ductile Iron Fittings 10,000 Lbs. $ 1.75 $ 17,500.00
9 Removing and Replacing Existing Asphalt Pavement 80 S.Y. $ 45.00 $ 3,600.00
10 Removing and Replacing Existing Concrete Pavement 213 S.Y. $ 65.00 $ 13,866.67
11 Extra Concrete Encasement 40 C.Y. $ 120.00 $ 4,800.00
12 Extra Crushed Stone Embedment 60 C.Y. $ 60.00 $ 3,600.00
13 Furnish, Install and Maintain Solid Block Sod 4,000 S.Y. $ 6.50 $ 26,000.00
14 Fumish, Install and Maintain Hydromulch seed and Fertilizer 4,000 S.Y. $ 2.50 $ 10,000.00
Furnishing, Installing, Maintaining and Removal of Erosion Control
15 Devices I L.S. $ 7,000.00 $ 7,000.00
16 iFurnishin$, Installin~ and Maintaining Traffic Control Dev/ces 1 L.S. $ 9,000.00 $ 9,000.00
17 iDesin~ingTrench Safely System 1 L.S. $ 4,500.00 $ 4,500.00
18 Desil~ing and Installing Trench Safety Systems 3,600 L.F. $ 2.00 $ 7,200.00
Subtotal: $ 403,266.67
Continl~encies and Miscellaneous Items 10% $ 40,326.67 1
Total: $ 443,593.33
USE: $ 443,600.00..