Loading...
ST0001-CS020411T H I~ · C I T Y · 0 F COl'FELL April 11, 2002 Mr. Phillip Bennett Infrastructure Services, Inc. P.O. Box 496448 Garland, Texas 75049-6448 Creekview Drive and Freeport Parkway ST 00-01 Working Days Dear Mr. Bennett: The number of working days originally scheduled for the Creekview Drive & Freeport Parkway project was 150 days. Change Order No. I added ten days and Change Order No. 3 added five days for a total of 165 working days. Work began on November 12, 2001 and the 165 days will end on April 25, 2002. As of the date of this letter, 14 working days or 8% of the total time is remaining and approximately 60% of the project remains to be completed. Your attention to this matter is appreciated and should you have any questions or need any additional information, please contact me at 972-304-7019. Sincerely, Suzafi I~. Taylor C.I.P.~Gbordinator