April 11, 2002
Mr. Phillip Bennett
Infrastructure Services, Inc.
P.O. Box 496448
Garland, Texas 75049-6448
Creekview Drive and Freeport Parkway
ST 00-01
Working Days
Dear Mr. Bennett:
The number of working days originally scheduled for the Creekview Drive & Freeport
Parkway project was 150 days. Change Order No. I added ten days and Change Order
No. 3 added five days for a total of 165 working days. Work began on November 12,
2001 and the 165 days will end on April 25, 2002. As of the date of this letter, 14
working days or 8% of the total time is remaining and approximately 60% of the project
remains to be completed.
Your attention to this matter is appreciated and should you have any questions or need
any additional information, please contact me at 972-304-7019.