Amberpoint BP-LR020329REPORT OF REINFORCING STEEL OBSERVATION
ENGINEERING, [NC.
8901 Carpenter Frwy., Suite #100
Dallas, Texas 75247
Date of Service: 03/29/02
Client No.: 3181
Client: Transwestern Commercial Services
5001 Spring Valley Rd, Suite 600 W
Dallas, TX 75244
Report No.: 94021029.0169
Project No.: 94021029
Project: Amberpoint Building No. 1
Amberpoint Bus. Pk @ Coppell
Coppell, Texas
Services:
Drawings Utilized:
Locations/Items Observed:
Observe placement of reinforcing for compliance with furnished drawings.
PROJECT DATA
Working Drawing, S3.1/06
Pier Cap at !d7
Test Method: Visual Observation
REPORT OF OBSERVATION
ITEMS OBSERVED CORRECT INCORRECT ITEMS OBSERVED CORRECT INCORRECT ! ITEMS ORSERVED CORRECT INCORRECT
Placing Drawings Approved X Bar Length and Shape X Column Tie Spacing & Type
Bar Size X Proper Bar Placement X Stirrup Spacing & Type X
Bar Grade X Propedy Tied X
Rebar Clean X Dowel Bars in Ptace X Welded Splices
Form Clean X Proper Bar Supports X Mechanical Splices
Number of Bars X Proper Cover X Lapped Splices
Discrepancies/Comments: Any discrepancies found were corrected at the time of this observation unless otherwise
noted.
Field Results Report To:
Technician: G. Graham
Reoort Distribution:
(I) Transwestem Commercial Services
(1) O'Brien & Associates, Inc.
(1) TechniStructures, Inc.
( 1 ) City of Coppell - Constr. lnsp.
309[Iw
(1) City of Coppell - Bldg. b~sp. ~ Eng~C.
(I) Hill & Wilkinson, Ltd.
(1) Halff Associates
(1) State Farm Associates Eugene Harbour
Principal
This roper[ is exclusively ~or the use et the client indicaled above and shall not be reproduced without written approval et HBO Engineering, Inc.