ST9905-CS020208STATUS REPORT
Date: February 8, 2002
To:
Ken Griffin. P.E.
Teresa Turner
Susan Taylor
City of Coppell - Director of Engineering
City of Coppell - Graduate Engineer
City of Coppell - CIP Coordinator
From: Craig Bond, P.E. TranSystems - Project Engineer
CC:
Paul Padilla, P.E.
Joe Masterson, P.E.
Mike Hobbs
Transystems - Project Coordinator
TranSystems - Project Manager
TranSystems - Project Hydrologist
Re:
Bethel Road Project (Dallas/Tarrant County Line to Freeport Road)
Coppell, Texas
Utilities
Preparing letter to send out to utility companies requesting their utility relocation
design based on the 60% plan set.
Roadway Design
· Submitted 60% plan set to City on 1-18-02
Made edits to 60% plan set based on redline comments from City on 11-19-01 plan
set submitted to utilities.
· Finishing up construction estimate. Will submit to City next week.
Hydrology/Hydraulics
· Draft Hydrology & Hydraulics Report submitted to City at 1-18-02 meeting.
· Detention pond options submitted to City for review the week ending 1-25-02.
For Discussion At Next Meeting With City
· City's commems on Draft Hydraulics & Hydrology Report and detention pond
options.
· Meeting with DFW Airport to discuss detention ponds and construction & slope
easements.