Amberpoint BP-LR020611REPORT OF DRILLED BELLED PIER OBSERVATION
Report Number: 94021029.0290
Service Date: May 29, 2002
8901 Carpenter Fnvy,, Suite #100
Dallas, Texas 75247
(214) 630-1010
Client: Transwestern Commercial Services
Attn: Jim Gaspard
5001 Spring Valley Rd. Suite 600W
Dallas TX 75244
Report Date: June 11, 2002
Project: Amberpoint Building No. 1
Amberpoint Bus. Pk. @ Coppell
Coppell, Texas
Project Number: 94021029
Services: Drilled belled pier observation.
On this date, an HBC Engineering technician arrived at the above referenced jobsite as scheduled for
drilled belled pier observation. See the attached sheet for recorded data.
Technician: Brad Rengstorff
Report Distribution:
(1) Transwestem Comrnemial Sen, ices
(1) O'Brien & Associates Inc
(1) TechniStructures Inc
(1) City of Coppell - Constr Insp
(1) City of Coppell - Bldg Insp
(1) Hill & Wilkinson Ltd
(1) Halff Associates
(1) State Farm Insurance
Reviewed by:
Principal
The tests were performed in general accordance with applicable ASTM, AASHTO, or DOT test methods. This report is exclusively fur the use of the client
indicated above and shall not be reproduced except in full without the written approval of Terracen. Test results transmitted herein are only applicable
to the actual samples tested at the location(s) referenced and are not necessarily indicative of the properties of other apparently similar or identical
materials.
Page 1 of I ~-~,~,~