SC-Coppell MSW-LR020729 ~~"'~ ~ ~ 2880 Virgo Lane; Dallas, Texas 75229 FUGRO SOUTH, INC.  Ph (972) 484-8301; Fax (972) 820-7328 OBSERVATION OF C NCRETE PLACEMENT CLIENT: Coppell lSD, c/o K A Sparks ~'~ REPORT DATE: July 29, 2002 PROJECT:~ PROJECT NO: 0701-2192 DATE PERFORMED: July 26, 2002 I General Contractor: Cortez Group Inc. Method of Test: Applicable ACI Recommendations and ASTM Standards Results / Remarks: Concrete placement observation was performed at the Paving on Wrangler Circle following location: Time placement began: Time placement ended: Total cubic yards placed: Slump range (inches): Slump required (inches): Concrete supplier and plant: Concrete temperature range (°F): Strength required (psi/days): Number of cylinders made: Superplasticizer used: 4:OO 11:00 2OO 4-1/2 to 5-1/2 5 Hanson - Plant No. 27 78 - 89°F 7/28 8 No Julio Villarreal Fugro South Technician SMH/bg Distribution: FUGRO SOUTH, INC. Reviewed By: "~"~' "~\ ' K A Sparks Contractors Inc, - Jim Schooler K A Sparks Contractors Inc. - Jerry Jones (Fax: 972-393-1228) City of Coppell - Lee Stone City of Coppell - Garreth CampbelP""-" Coppell lSD - Mickey Harper SHW Group - Mike Elmore SHW Group - Dale Lilljedahl FUGRO SOUTH, INC. 2880 Virgo Lane; Dallas, Texas 75229 Ph (972) 484-8301; Fax (972) 620-7328 REINFORCING STEEL PLACEMENT OBSERVATION CLIENT: Coppell lSD, cio K A Sparks REPORT DATE: July 29, 2002 PROJECT: Coppell Middle School West, Coppell, Texas PROJECT NO: 0701-2192 DATE PERFORMED: July 26, 2002 General Contractor: Cortez Group inc. Method of Test: Applicable ACl Recommendations and ASTM Standards Results / Remarks: On the above sample date, a representative of Fugro South observed the reinforcing steel placed at the following location: · Wrangler Circle and parking lot next to Building "A". The steel was checked for proper size, grade, quantity, vertical location, horizontal spacing, correctness of bends and splices, firmness and security of support and ties and clearances between reinforcement and forms. No discrepancies were noted this date. Julio Villarreal Fugro South Technician FUGRO SOUTH, INC. Reviewed By: SMH/bg Distribution: K A Sparks Contractors Inc. - Jim Schooler K A Sparks Contractors Inc. - Jerry Jones (Fax: 972-393-1228) City of Coppell - Lee Stone City of Coppell - Garreth Campbell Coppell lSD - Mickey Harper SHW Group - Mike EImore SHW Group - Dale Lilljedahl FUGRO SOUTH, INC. 2880 Virgo Lane; Dallas, Texas 75229 Ph (972) 484-8301; Fax (972) 620-7328 CLIENT: PROJECT: OBSERVATION OF CONCRETE PLACEMENT Coppell lSD, c/o K A Sparks REPORT DATE: July 29, 2002 Coppell Middle School West, Coppell, Texas PROJECT NO: 0701-2192 DATE PERFORMED: July 25, 2002 General Contractor: Cortez Group Method of Test: Applicable ACl Recommendations and ASTM Standards Results / Remarks: Concrete placement observation was performed at the Paving at firelane and bus drop-off and pick-up following location: Time placement began: Time placement ended: Total cubic yards placed: Slump range (inches): Slump required (inches): Concrete supplier and plant: Concrete temperature range (°F): Strength required (psi/days): Number of cylinders made: Superplasticizer used: 3:30 11:30 250 5.0 to 6.0 5.0 Hanson - Plant No. 27 .°F 4000/28 12 No Julio Perez Fugro South Technician SMH/bg Distribution: FUGRO SOUTH, INC. Reviewed By: K A Sparks Contractors Inc. - Jim Schooler K A Sparks Contractors Inc. - Jerry Jones (Fax: 972-393-1228) City of Coppell - Lee Stone City of Coppell - Garreth Campbell Coppell lSD - Mickey Harper SHW Group - Mike Elmore SHW Group - Dale Lilljedahl