ST0001-RP020814ST GO -G1 U t- IMrsstractwo sKrk»s, Inc. August 14, 2002 Mr. Ken Griffin, P.E. City of Coppell 255 Parkway Blvd. Coppell, TX 75019 Project: Creekview Drive and Freeport Project Contract No: ST 00 -01 Dear Mr. Griffin, This request for consideration of equitable compensation pertains to labor and equipment required to install, remove, and maintain temporary roads inside the phased area, not originally phased on the contract drawings. This work occurred at the intersection of Freeport Parkway and Ruby Road. We request equitable compensation required for the extra costs and markup incurred to complete the task. ISI is also requesting 24 days for duration associated with this item. Item No. Description Unit Quan Price Total I Temporary Roads LS 1 $14,286.53 $14,286.53 If you have any questions or desire any additional information, please feel free to call me at 972- 399 -8001. Sincerely, Dennis Hammock 1306 LEYFAIR DRIVE GRAND PRAIRIE, TEXAS 75050 (872) 388 -8001 Request for Change Order #4 Project: City of Coppel Ceekvlaw and Freeport Parkway Re: RFI Description: Install, Rename, and Maintain Base Material LABOR Regular Overtime Qty Days Rate Hours Hours Trial Operator 1 24 $ 14.00 8 $ 2,688.00 Labor 1 24 $ 12.00 8 $ 2,304.00 S 4,892.00 EQUIPMENT Daily Rabe Total Bacldm 1 24 $ 237.00 $ 5,688.00 RENTALS Roller Compactor Water Truck 900.00 $ 900.00 1,500.00 $ 1,500.00 = 2,400.00 i1MATERUIUSUPPLIES Unit Qty Price Total Flex Base Ids 20 120.00 $ 2,400.00 E 2,400.00 SUBCONTRACTORS r7PF7 Qty Price Total 0 Base Labor $ 4,992.00 Burden 55% $ 2,745.60 Markup 15% $ 748.80 Sub -Total $ 8,486.40 Equipment $ 2,400.00 Markup 15% $ 360.00 Sub -Total $ 2,760.00 Materials, Supplies $ 2,400.00 15% $ 360.00 Sub-Total $ 2,760.00 Subcontractors $ - 15% $ Sub -Total $ Bond 2% $14,006.40 Sub -Total $ 280.13 Total Price $ 14,286.63 Mfr -- tracts services, in¢. U� 4.. August 14, 2002 Mr. Ken Griffin, P.E. City of Coppell 255 Parkway Blvd. Coppell, TX 75019 Project: Creekview Drive and Freeport Project Contract No: ST 00 -01 Dear Mr. Griffin, This request for consideration of equitable compensation pertains to labor and equipment for the extended time period due to phasing. Phasing was not designated in the contract documents. ISI was directed to phase the Freeport Parkway and Ruby Road intersection. The additional time to phase cost ISI additional supervision time and general conditions for the project. We request equitable compensation required for the extra costs and markup incurred to complete the task. Item No. Description Unit QL= Price Total 1 General Conditions LS 1 $52 $52,620.37 If you have any questions or desire any additional information, please feel free to call me at 972- 399 -8001. Sincerely, Dennis Hammock 1306 LEYFAIR DRIVE GRAND PRAIRIE, TEXAS 76050 (872) 398-8001 �.v m +w. www wwww Request for Change Order #8 Project: City of Coppel Ceekview and Freeport Parkway Re: RFI Description:General Conditions f Regular Overtime Qty Days Rate Hours Hours Total Field Supervisor 1 112 $ 30.00 8 $26,880.00 EQUIPMENT Daily F Q Days Rate Total 112 to pickup 1 112 $ 44.00 $4,928.00 RENTALS MATERIAUSUPPL.IES r Unit Oty Price Tol =1 Port -a- toilet DAYS 112 1.75 $196.00 Markup 15% 1 z 00 SUBCONTRACTORS Unit Qty Price Total $ 5,667.20 Materials, Supplies $ 196.00 0 Base labor $26,880.00 Burden 55% $14,784.00 Markup 15% $ 4,032.00 Sub -Total $45,696.00 Equipment $ 4,928.00 Markup 15% $ 739.20 Sub -Total $ 5,667.20 Materials, Supplies $ 196.00 15% $ 29.40 Sub -Total $ 225.40 Subcontractors $ - 15% $ Sub-Total $ Bond 2% $51,588.60 Sub -Total $ 1,031.77 Total Price 52,620.37 U 4-- �L iMrastn�cturs services, August 14, 2002 Mr. Ken Griffin, P.E. City of Coppell 255 Parkway Blvd. Coppell, TX 75019 Project: Creekview Drive and Freeport Project Contract No: ST 00 -01 Dear Mr. Griffin, This request for consideration of equitable compensation pertains to labor to maintain barricades while constructing the Freeport Parkway street construction. ISI was directed by the City of Coppell to construct the street paving and liming in three phases despite no indication on the contract drawings or specifications. A supervisor from ISI was required to come in every weekend to check and correct the barricades during this period. We request equitable compensation required for the extra costs and markup incurred to complete the task. ISI is also requesting 16 days for duration associated with this item. Item No. Description Unit Qum Price Total 1 Barricade Maintenence LS 1 $9,399.72 $9,399.72 If you have any questions or desire any additional information, please feel free to call me at 972- 399 -8001. Sincerely, Dennis Hammock 1306 LEYFAIR DRIVE GRAND PRAIRIE, TEXAS 76060 (872) 398 -8001 r w v m +w. www noon Request for Change Order #6 Project: City of Coppel Ceekview and Freeport Parkway Re: RFI Description: Barricades and Maintenance LABOR Regular Overtime Qty Days Rate Hours Hours Total Field Supervisor 1 16 $ 30.00 3 $ 1,440.00 rr - 1,4 - 4 - 0 - 0 - 01 EQUIPMENT Daily Days Rate Total RENTALS MATERIALISUPPLIES Unit Qty Price dot 0 SUBCONTRACTORS Unit Qty Price Total Barricade Subcontractor mo 4 1500.00 $ 6,000.00 6,000.00 Base Labor $ 1,440.00 Burden 55% $ 792.00 Markup 15% $ 216.00 Sub -Total $ 2,448.00 Equipment $ Markup 15% $ Sub-Total $ Materials, Supplies $ 15% $ Sub -Total $ Subcontractors $ 6,000.00 15% $ 900.00 Sub -Total $ 6,900.00 Bond 2% $ 2,566.00 Sub -Trial $ 51.72 Total Price S 9,389.72 r` nfrashuctu services, inc. August 14, 2002 Mr. Ken Griffin, P.E. City of Coppell 255 Parkway Blvd. Coppell, TX 75019 Project: Creekview Drive and Freeport Project Contract No: ST 00 -01 Dear Mr. Griffin, This request for consideration of equitable compensation pertains to labor and equipment required for additional excavation on the project. This additional excavation was in relation to the redesign of the sidewalk. ISI was required to relocate the stockpile, previously relocated, and cut out the existing berms to install the corrected sidewalk. We request equitable compensation required for the extra costs and markup incurred to complete the task. ISI is also requesting 7 days for duration associated with this item. Item No. Description Unit (Quan Price Total 1 Extra Excavation LS 1 $18 $18,041.01 If you have any questions or desire any additional information, please feel free to call me at 972- 399 -8001. Sincerely, Dennis Hammock 1306 LEYFAIR DRIVE GRAND PRAIRIE, TEXAS 75050 (972) 3994001 Request for Change Order #6 ProjeaL City of Coppei Ceekview and Freeport Parkway Re: RFI Desariptlon: Extra Excavation 2,856. EQUIPMENT Regular Overtime Qty Days Rate Hours Hours Total Foreman 1 7 $ 25.00 8 $1,400.00 Labor 1 7 $ 12.00 8 $ 672.00 Operator 1 7 $ 14.00 8 $ 784.00 2,856. EQUIPMENT Daily Qty Days Rate Total Backhoe 1 7 $ 237.00 $ 1,659.00 Excavator 1 7 $ 550.00 $ 3,850.00 REPITAL.S MATERLAUSUPPLIES Unit Qty Price Total SUBCONTRACTORS r Unit Total Qty Price Trucking hm 144 40.00 $ 5,760.00 Base Labor $ 2,856.00 Burden 55% $ 1,570.80 Markup 15% $ 428.40 Sub -Total $ 4,855.20 Equipment $ 5,509.00 Markup 15% $ 826.35 Sub -Total $ 6,335.35 Materials, Supplies $ 15% $ Sub -Total $ - Subcontractors $ 5,760.00 15% $ 864.00 Sub -Total $ 6,624.00 Bond 2% $11,323.03 Sub -Total $ 226.46 Total Price 18,041.01 UE: 1L— iMnst�ucturI services, August 14, 2002 Mr. Ken Griffin, P.E. City of Coppell 255 Parkway Blvd. Coppell, TX 75019 Project: Creekview Drive and Freeport Project Contract No: ST 00 -01 Dear Mr. Griffin, This request for consideration of equitable compensation pertains to labor and equipment to haul dirt excess off -site. Originally Schrickel Rollins represented that disposal of excavated materials would be allowed on site at the new stockpile location. Change in conditions cause ISI to incur off -site trucking charges as outlined attached. We request equitable compensation required for the extra costs and markup incurred to complete the task. ISI is also requesting 35 days for duration associated with this item. Item No. Degmr ion Unit Excess Dirt LS Haul Off -site Q44n— Price Total 1 $68 $68,121.98 If you have any questions or desire any additional information, please feel free to call me at 972- 399 -8001. Sincerely, Dennis Hammock 1309 LEYFAIR DRIVE GRAND PRAIRIE, TEXAS 76060 (972) 399 -8001 ��v iw +w. www nwwn Request for Change Order #7 Project: City of Coppel Ceekview and Freeport Parkway Re: RFI Description:Excess Dirt Haul Off EQUIPMENT Daily Q ty Days Rate Total F/E Loader 1 40 $ 325.00 $13,000.00 RENTALS S - LIATERIAUSUPPUES I Unit Qty Price Total Trucking hrs 1163 35.00 $40,705.00 dump fees LS 1 4370.00 $ 4,370.00 Sub-Total rJW. 0 - 7TM SUBCONTRACTORS Unit Qty Price Total 0 Base Labor $ Burden 55% $ Markup 15% $ Sub -Total $ Equipment Markup Sub -Total Materials, Supplies Sub-Total Subcontractors Sub-Total Bond Sub-Total Total Price $ 13,000.00 15% $ 1,950.00 $ 14,950.00 $ 45,075.00 15% $ 6,761.25 $ 51,836.25 15% $ 2% $ 66,786.25 $ 1,335.73 88,121.88 ti iMrsstructw+1 sewices, August 14, 2002 Mr. Ken Griffin, P.E. City of Coppell 255 Parkway Blvd. Coppell, TX 75019 Project: Creekview Drive and Freeport Project Contract No: ST 00 -01 Dear Mr. Griffin, This request for consideration of equitable compensation pertains to labor to account for the inefficiency in the schedule. ISI's original schedule initially displayed as a single phase of work at the Freeport Parkway and Ruby Road intersection. After direction from the City of Coppell, ISI had to reschedule and construct the work in a completely different sequence of operations not indicated in the contract documents. While constructing the seven -inch paving on Creekview, ISI was able to pour 2,560 SY per day for 5 days which fell into ISI's original estimate of the work. On the paving installed on Freeport Parkway, ISI was only able to pour an average of 510 SY of paving per day for 10 days. This rate on Freeport Drive grossly fell outside of the estimates parameters for this work due to the phasing of the work in this area. Originally ISI estimated to complete this work in approximately 16 days. With the segmented operations, it took ISI an additional 14 days, which correlates to a 46% inefficiency. We request equitable compensation required for the extra costs and markup incurred to complete the task. ISI is also requesting 14 days for duration associated with this item. Item No. Description Unit Quan Price Total 1 Concrete Labor LS 1 $30,081.23 $30,081.23 Inefficiency If you have any questions or desire any additional information, please feel free to call me at 972- 399 -8001. Sincerely, Dennis Hammock 1306 LEYFAIR DRIVE GRAND PRAIRIE, TEXAS 75050 (872) 388 -8001 Request for Change Order #3 Project: City of Coppel Ceekview and Freeport Parkway Re: RFI Description: Labor Inefficiency 1 8 .110 EQUIPMENT Daily City Days Rate Total Power Screed 1 5 $ 350.00 $1,750.00 Delivery of Screed 2 5 $ RENTALS 1,7 .00 MATERIAUSUPPLIES Unit Qty Price Total Delivery of Screed EA 5 110.00 $ 550.00 SUBCONTRACTORS r - UnitCfty Price Total Base Labor $ 15,792.00 Burden 55% $ 8,685.60 Markup 15% $ 2,368.80 Sub -Total $ 26,846.40 Equipment $ 1,750.00 Markup 15% $ 262.50 Sub -Total $ 2,012.50 Materials, Supplies $ 550.00 15% $ 82.50 Sub -Total $ 632.50 Subcontractors $ 5% $ Sub -Total $ Bond 2% $ 29,491.40 Sub -Total $ 589.83 Total Price 30,081.23 Regular Overtime city Days Rate Hours Hours Total Foreman 1 14 $ 30.00 8 $ 3,360.00 Labor 3 14 $ 12.00 8 $ 4,032.00 Finisher / Formsetter 5 14 $ 15.00 8 $ 8,400.00 1 8 .110 EQUIPMENT Daily City Days Rate Total Power Screed 1 5 $ 350.00 $1,750.00 Delivery of Screed 2 5 $ RENTALS 1,7 .00 MATERIAUSUPPLIES Unit Qty Price Total Delivery of Screed EA 5 110.00 $ 550.00 SUBCONTRACTORS r - UnitCfty Price Total Base Labor $ 15,792.00 Burden 55% $ 8,685.60 Markup 15% $ 2,368.80 Sub -Total $ 26,846.40 Equipment $ 1,750.00 Markup 15% $ 262.50 Sub -Total $ 2,012.50 Materials, Supplies $ 550.00 15% $ 82.50 Sub -Total $ 632.50 Subcontractors $ 5% $ Sub -Total $ Bond 2% $ 29,491.40 Sub -Total $ 589.83 Total Price 30,081.23 U 4— �t Infrastruat0 servicMs, ice. August 14, 2002 Mr. Ken Griffin, P.E. City of Coppell 255 Parkway Blvd. Coppell, TX 75019 Project: Creekview Drive and Freeport Project Contract No: ST 00 -01 Dear Mr. Griffin, This request for consideration of equitable compensation pertains to labor and equipment to remove trees, haul dirt, and compact dirt on the northeast comer of Ruby and State Road. To be able to install the new fence, ISI was directed by the City of Coppell to fill in the stock pond in that area in compacted lifts and remove existing trees to provide access to work. We request equitable compensation required for the extra costs and markup incurred to complete the task. ISI is also requesting 10 days for duration associated with this item. Item No. Description Stock Pond Work Unit CQuan Price Total LS $17,894.95 $17 If you have any questions or desire any additional information, please feel free to call me at 972- 399 -8001. Sincerely, Dennis Hammock 1306 LEYFAIR DRIVE GRAND PRAIRIE, TEXAS 76050 (972) 399 -8001 Request for Change Order #2 Project: City of Coppel Ceekview and Freeport Parkway Re: RFI Description: Tree removal and dirt hauling into pond area Regular Overtime Qty Days Rate Hours Hours Total Operator 2 10 $ 16.00 8 $2,560.00 Labor 2 10 $ 12.00 8 $1,920.00 4.480.00 EQUPMENr Daily aty Days Rate Total Dozer 1 10 $ 350.00 $3,500.00 Railer compactor 1 10 $ 325.00 $3,250.00 RENTALS 6,750. MATERIALISUPPLIES Unit Qy Price Total 0 SUBCONTRACTORS FUnd Qty Price Total Trucking hrs 48 40.00 $1,920.00 1,920.00 Base Labor $ 4,480.00 Burden 55% $ 2,464.00 Markup 15% $ 672.00 Sub -Total $ 7,616.00 Equipment $ 6,750.00 Markup 15% $ 1,012.50 Sub -Total $ 7,762.50 Materials, Supplies $ 15% $ Sub -Total $ - Subcontractors $ 1,920.00 15% $ 288.00 Sub -Total $ 2,208.00 Bond 2% $15,422.66 Sub -Total $ 308.45 Total Price 1 ,884.85 U� Ndrastruaturo aNVtces, inc. August 14, 2002 Mr. Ken Griffin, P.E. City of Coppell 255 Parkway Blvd. Coppell, TX 75019 Project: Creekview Drive and Freeport Project Contract No: ST 00 -01 Dear Mr. Griffin, This request for consideration of equitable compensation pertains to labor required for additional mobilizations due to phasing not indicated by the contract documents but directed by the City of Coppell. We request equitable compensation required for the extra costs and markup incurred to complete the task. ISI is also requesting 6 days for duration associated with this item. Item No. Description Unit Qmm Price Total 1 Extra Mobilization LS 1 $23,332.84 $23,332.84 If you have any questions or desire any additional information, please feel free to call me at 972- 399 -8001. Sincerely, Dennis Hammock 1306 LEYFAIR DRIVE GRAND PRAIRIE, TEXAS 75060 (972) 399 -8001 ►.v iw +m www wwww Request for Change Order #1 Project City of Coppei Ceekview and Freeport Parkway Re: RFI Description: Extra Mobilization Due to phasing not shown in plans LABOR Regular Overtime Days Rate Hours Hours Trial Forernan 1 6 $ 25.00 8 $ 1,200.00 Labor 4 6 $ 12.00 S $ 2,304.00 S 3,604.00 EQUIPMENT Daily City Days Rate Total RENTALS MATERIAJSUPPLIES r ' Unit0ty Price Tafal SUBCONTRACTORS Unit Qty Price Total lime Subcontractor ce 3 5000.00 $15,000.00 S 16,000.00 Base Labor $ 3,504.00 Burden 55% $ 1,927.20 Markup 15% $ 525.60 Sub -Toted $ 5,956.80 Equipment $ Markup 15% $ Sub -Total $ Materials, Supplies $ 15% $ Sub -Trial $ Subcontractors $15,000.00 15% $ 2,250.00 Sub -Total $17,250.00 Bond 2% $ 6,301.80 Sub -Total $ 126,04 Total Price $ 23,332.84