Pre Punch List:
1. Complete all backfill along Creekview Drive, State Road, and Ruby Road according
to the plans.
2. Complete the placement of the solid sod and the hydro mulch seeding.
3. Adjust and appropriately identify all water valves, and adjust and paint all fire
hydrants.
4. Replace all damaged irrigation and complete final grading along Creekview Drive,
adjacent to Craftmade International, Inc.
5. Repair concrete paving and damaged curb throughout the limits of the project.
6. Clean up all trash and debris within the project limits.
7. Check modular wall displacement.
8. Check paving grade deflections throughout the limits of the project.
9. There is standing water in the gutter at the intersection of Creekview Drive and
Freeport Parkway. (See No. 8)
10. There is standing water in the gutter on the north side of Creekview Drive and west of
Freeport Parkway. (See No. 8)
11. Clean storm drain and inlets.
12. Complete air relief installation.
13. Clean paving on Freeport Parkway, Creekview Drive and State Road.
14. Replace tree adjacent to Craftmade International, Inc.
15. Provide marked -up set of plans noting any construction changes to the engineer of
record.
16. Missing the word "ONLY" on all turn lanes.
17. Cracks in both concrete and HMAC pavement need to be sealed.