Loading...
ST9401-CS 980912SEP 14 '98 09:53~H NIE~ASSOCIATES :;, T cf 1 MEMORANDUM TO: Garreth Campbell FROM: Ulys Lane DATE: 9-12-98 PROJECT: Denton Tapp Road; Coppeil, Texas W&A #: 94093 Regarding the letter from Rebcon, Inc. dated September 1, 1998, I would appreciate a meeting with Mr. Bibby, Martin Ledford, and yourself to discuss this matter before any action is taken. I would like to establish how we will confirm what is the standard of practice for vertical information to be provided on bridge plans. ('If the City in fact determines our plans should have provided this information, we prefer this cost be addressed by our firm and not the City. If this information is found not to be standard information provided in the plans, then we recommend the City not reduce the deck credit.) I would express my view that information provided in TxDOT plans for bridge and roadway projects is not a standard of practice for municipal or private projects. I am clearly aware that Rebcon has not been satisfied with the quality of the bridge plans. ~ think it would be desirable to discuss issues and try to establish a firm understanding of any concerns Rebcon may have. We wish to satisfy the City's needs on this project as their Consultant, and if we need to address any matters, I would like to clarify them at this meeting. If there are any additional concerns regarding the bridge, we need to know immediately so we may address them in a timely manner. Several of the bddge issues came up at a time when Mr. Ledford was out of the state on vacation which delayed several of the responses. Regarding the request for extra pay for the geotextile fabric in the letter dated September 4, 1998, we request other issues regarding the gabions be confirmed before payment is made. We would ask that a comparison of the bid gabion quantity versus the installed quantity be determined along with evaluations regarding the fabric. The exact quantity cannot be determined until the east side of the bridge is installed, If the Carthage Mills fabric is more expensive than the bid fabric, it is a legitimate item for additional payment. We would ask the contractor provide information supporting the net difference in cost. This could be a letter from the supplier from both products to demonstrate the unit cost for the size project involved. Also, we would ask to confirm the bid surface area of gabions versus the as-built area to confirm the quantity difference. There may be less quantity with the as-built surface area based on the changes agreed at the job site meeting three weeks ago. if you prefer that our firm make a determination regarding this matter, please direct the contractor to provide the supporting information discussed above. If you wish, we will make a job site measurement of the as-built gabion area to confirm the quantity after the east bridge is installed. END OF MEMO Copy to: Martin Ledford Ken Griffin 4300 Beltway Place, Suite 130 Arlington, Texas 76010 metro (817) 467-7700 SEP 817 467 7713 14 '98 09:53AM NIE~'~ASSOCIATES " P.1 VI/A WIER & ASSOCIATES, INC ENGINEERING SURVEYING LAND PLANNING 4300 BELTWAY PLACE. SUITE 130 · ARLINGTON TEXAS 71S018-1097 METRO 817/467-7700, FAX ME'FRO 817Y 467-7713 P/ease deliver Name . CompanV ~,---~, .,<'-5---,~--~',".r, APea Code/Number FROM: ( )!~'/~ ( ~'4/1~- /t ~4f' DATE: TOTAL NUMBER OF PAGES r-2 (INCLUDINGTHIS COVER SHE~'i] IF THIS TRANSMISSION IS INCOMPLETE OR UNREADABLE PLEASE CALL METRO 817467-7700 AS SOON AS POSSIBLE ADDITIONAL MESSAGE [] ORIGINAL WIL..L FOLLOW [] Regular Mail [] Hand Deftvery [] Overnight RIGINAL WILL NOT FOLLOW c:\6210%wa_forms%faxcvr97.doc