WA9701-CS020821d
Suzan Ta for - Re: Denton Ta Water Line Pa a 1
From: "Gary Hendricks" <GHendricks @BHCLLP.COM>
To: <staylor @ci.coppell.tx.us>
Date: 8/21/02 5:12PM
Subject: Re: Denton Tap Water Line
Suzan
It is good to here from you. I hope all is well with you in Coppell. We stand ready to meet with you at your
earliest convenience to discuss the S.H. 121 Water Line and its completion schedule. Regarding the
Denton Tap Road Water Line, we have completed most of the design surreys and are moving into plan
production this week. I would like to arrange to get the development plans (water and sewer) along the
west side of Denton Tap Road for the project limits. Perhaps we can pick those up when we meet to
discuss S.H. 121 waterline.
Please do not hesitate to give me a call if you need further clarification regarding either project.
GCH
Gary C. Hendricks, P.E.
Birkhoff, Hendricks & Conway, L.L.P.
7205 Greenville Ave., Suite 220
Dallas, Texas 75231
214.361.7900
>>> "Suzan Taylor" <staylor @ci.coppell.tx.us> 08/21/02 10:09AM >>>
Gary:
We are nearly finished with our review of the SH 121 water line plans
and should get the comments back to you in the next week or so. Can you
tell me the status of the Denton Tap water line, when do you expect to
send over preliminary plans for review?
Thanks