ST0001-MP020906CREEKVIEW DRIVE 8 FREEPORT PARKWAY
ST 00-01
Schrlckel Rollins 8 Associates
ID
1
Task Name
- -
DESIGN PHASE
Design
Advertisement
Bid Opening
City Council
PERMITS
TAS
Response Received
THC
Approved
Flood Plain Permit
RIGHT -OF -WAY
Coppell Industrial LTD.
Acquired
Texas Dugan Limited
UTILITY RELOCATIONS
TXU Electric 3 Gas
On -Site Meeting
Relocation Time
Verizon I GTE
On -Ske Meeting
Relocation Time
TESTING MATERIALS
Rone Engineers
Contract Executed
CONSTRUCTION
Notice to Proceed
Construction (work days)
Construction (over work days)
Feb 1 Mar
Qtr 2, 2000 _
Apr May J Jun
Qtr 3, 2000 _
Jul Aug Sep
4tr 4, 2000 _
Oct Nov Dec
Qtr 1, 2
Jan ] Feb __Mar
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
2D
21
22
23
24
25
26
27
28
29
Project: ST 00-01
Date: Fri 916/02
Task Milestone . Summary ^ Deadline -Jl
Page 1
CREEKVIEW DRIVE & FREEPORT PARKWAY
ST 00-01
Schrickel Ro ins & Associates
Qtr 2, 200 Qtr 3, 2001 Qtr 4, 200 Qtr 1, 2002 _ Qtr 2, 200 Qtr 3, 200 Qtr 4, 200
Apr_ _ May _� _Jun Jul [ — Aug —. Sep Oct 1 Nov j Dec — _ dan Feb I Mar _ —Apr 1 May ] __Jun — Jul I Aug . l_ — Se Oct
0
♦ 8121
. 91118
CREEKVIEW DRIVE & FREEPORT PARKWAY
ST OD-01
Schrickel Rollins & Associates
e Response Received
Nonconforming items have been noted. SRA to address.
n Construction (work days)
Week 1 & 2 - (Nov. 12 - 23)
Clearing and grubbing of Creekview & Freeport right -of -way.
Week 3 - (Nov. 26 - 30)
Creekview: staked offsets to back of curb
Week 4 - (Dec. 03 - 07)
Creekview: staked right-of -way
Freeport: staked right -of -way
Set hortrontal and vertical control and staking for excavation and fill
Rone Engineers was contacted on Dec. 5 for densities to be taken at 2:00 on the east side of State Road on the fill area
Contractor requested laboratory be set up for Dec. 6 at 11:00 and 3:00 and on Friday on Dec. 7 at 11:00 and 3:00 at the above said location
Contractor requested one month time extension on contract time
Made contact with Leisure Services about the addtional fill In stock pond- they will get back with Engineering in future
isi contacted both Verzlon and TXU to discuss the status of the utility relocations
Week 6 - (Dec. 10 -14)
Excavation and fill on east side of State Road
Rained - ooud not work Wednesday, Thursday or Friday
Week 6 - (Dec. 17 - 21)
Verizon is installing underground utilities
Pumping water due to rain over the weekend
Submitted traffic control plan - needed to be revised
Week 7 - (Dec. 24 - 28)
Excavation - contractor has no location to haul excess fill - only worked until 1:30 on 12 -28 -01.
Week 8 - (Dec. 31 - Jan. 4)
Excavation - contractor has found location to haul excess fill. Did not work on 12 -31 -01.
Contractor is aproximately 3 weeks behind - partially due to rain and holidays.
Week 8 - (Jan. 7 -11)
Contractor Is excavating Creekview. Utility contactor is installing 12 -inch water line.
Removing and installing steel and cable fence. Gabion contractor started work.
TXU utilites found in subgrade along State Road - need to be relocated. TXU notified.
Week 10 - (Jan. 14 -18)
Worked on the Installation of gabions. Finished laying 8 -Inch water stub -outs and installing fire hydrants. Excavation on Creekview Drive. Glen is supposed to get with Brad Reid to discuss the 84nch
water line and requested DC vault, as per conversation with Larry Davis on Jan. 18, 2002.
Week 11 - (Jan. 21 - 26)
Liming on Freeport Pkwy. adjacent to the steel & cable fence. Installing the storm drain.
Estimate #1 was received by Larry Davis on Jan. 22, 2002 - in the late afternoon. After reviewing the estimate it was apparent that the request for payment and the line items had increased over the
previously supplied ISI work copy estimate dated Jan. 16, 2002. Larry contacted Phillip Bennet on the morning of Jan. 23, 2002 to make him aware that because of the apparent changes and the pay
estimate he would need to discuss with SRA (Chris). After placing a telephone call to Chris, Larry was informed that Chris was out for the day - therefore was not able to meet the time stipulation
mentioned to Phillip for the submittal of estimate with signatures to the finance department. It is Larry's intent to have completed the review of Estimate #1 on or before Wednesday, Jan. 30, 2002. (all of
the above information was discussed with Phillip on Jan. 23, 2002)
Page 3
CREEKVIEW DRIVE & FREEPORT PARKWAY
ST 0001
Schrickel Rollins & Associates
The utility contractor exposed the existing 27 -inch RCP at Freeport and Creekview Drive. He has started laying from the connection point of the existing RCP west on Creekview. It was noticed by Larry
Davis that the depth of cut for placement of the proposed RCP will and does require trench safety measures to be taken. He also informed the utility contractor and Billy W. that the proper compaction
equipment to handle the width and the depth of trench over the RCP was not on the job site. Larry's request to Billy W. was to please follow proper acceptable construction methods for the placement of
the RCP in the trench line. Larry also informed Phillip to get in touch with the utility contractor to request them to use the proper equipment in order to reach the density requirements set forth in the
contract and the lift requirements for frequency of testing in the ditch.
The contractor lime stabilized the area between the existing east edge of State Road and the offset just west of the east boundary line of State Road and from the beginning of the transition south to the
north edge of pavement on Ruby Road on Jan. 22, 2002. On Jan. 23, 2002 - Larry Davis had a discussion with Billy W. about being sure of his lime placement location which would be under all paving
and one -foot beyond existing curb. Billy W. Is now veriflying the location of the lime placement. Based on the discussion of Jan. 17, 2002, ISI had proposed to utilize a Type A Flex Base under the
portion identified as the hot mix transition area. Billy inadvertently limed this area.
Billy W. informed Larry Davis that TXU is still working on a schedule for next week to lower the two existing flinch electrical conduits in Creekview Drive at Freeport. Larry Davis discussed with Billy W.,
as with previous dates with Dennis, that TXU does have existing underground electrical crossing Freeport, east to west, from the transformers on the west side of Freeport and between the asphalt
paving on Ruby Road and the existing concrete paving on Freeport. Billy W. was requested to contact TXU once again for utility locates and to expose the above mentioned service. This will verify
whether or not the existing electrical services will conflict with the excavation and paving in this location.
Billy W. was requested to contact Brad Reid and inform him prolr to their scheduling of their saw cutting of the internal paving of widening WW park entrance. (existing electrical sensor wire for gate
operation). Also discussed with Billy to locate all of the existing irrigation parallel to and inside the roadway of Freeport. Larry also discussed with Billy W. placing the proper barricades in and on the
construction site in particular the section of Freeport, Ruby and State. ( i.e. road work ahead, caution and end of construction are not place on the project)
WEEK 12 (Jan. 28 - Feb. 1)
TXU acknowledeged existing utilities along Ruby Road. TXU requested information about Ruby Road necessary for them to relocate/adjust utility pole and underground utilities. They are continuing the
Installation of the storm drain and junction boxes.
WEEK 13 (Feb. 4.8)
Paved the eastern most lane of the northbound lanes on Freeport parkway from north of the Ruby Road intersection to the transition. City met with TXU to detemine location of existing and proposed
underground utilities.
WEEK 14 (Feb. 11 -16)
Continued the paving of Freeport Parkway. Saw cut the area around the Wagon Wheel Park entrance. Poured the bottoms of the inlets and the junction box. Feb. 13- Two Inlets poured and densities
were taken on the remaining portion of the storm drain on the west end of Creekview Drive. Twelve -inch and 8 -inch water main is currently under pressure for psi test - anticipating water samples to be
taken next week. Feb. 13 - ISI Is constructing a temporary roadway along the north edge of existing Ruby Road to allow for detour of traffic of Ruby /State/Freeport. ISI has provided a traffic safety plan
for the proposed reconstruction of intersection. Larry Davis has requested that ISI follow the approved barricade and safety plan and maintain and repair as needed at all times.
WEEK 16 (Feb. 18 - 22)
Feb. 18 - ISI is remixing lime stabilization at the intersection of Freeport/State/Ruby. Rone has took gradations and densities at 1:00 p.m. on Feb. 19. The paving contractor set forms and steel on Feb.
19, in the northbound through lane from existing Freeport Parkway across Ruby Road and tying into previously poured section. The yield right turn island is in this area and we are waiting for design
direction from SRA.
On morning of Feb 18, Larry Davis met with Billy Wisenhunt. Larry Davis discussed once again the possible maintenance issues with the detour and the barricades placed at Freeport/State/Ruby. ISI -
Billy Wisenhunt' a daytime and nighttime contact numbers have been forwarded to the Coppell dispatch, in case any issues come up after normal working hours.
Creekview Drive - Larry Davis discussed with Billy Wisenhunt, his concern about the inlets. LD requested that the inlet tops not be poured until after the paving section Is complete. LD told Billy that
erosion control protection must be placed at each inlet to prevent any silt or debris from entering into the newly placed storm drain.
WEEK 16 (Feb.26 - Mar.1)
Contractor removing the spoil from the utility installation. Pouring the northbound lanes at the intersection of Ruby Road and Freeport Parkway. On Wed. 27, TXU completed the relocation of the conduit
at the intersection of Creekview. The power outage lasted one day.
WEEK 17 (Mar. 4 - 8)
Contractor removed the existing asphalt pavement on State Road. Contactor is excavating State Road. Traffic is routed two-way on the newly constructed northbound lanes from the cross -over at
Creekview to the transition. Electrician is installing conduft crossing on the west end of Creekview. SRA field party shot elevations on the centerline and gabion walls.
WEEK 18 (Mar. 11 -16)
Contractor lime stabilized the southbound lanes of Freeport Parkway. Contractor removed barbed wire fence and trees along Champion property line/right -of -way line along Creekview.
TXU has to relocate two power poles on the west end of Creekview Drive.
Page 4
CREEKVIEW DRIVE & FREEPORT PARKWAY
ST O0-01
Schrickel Rollins & Associates
WEEK 19 ( Mar. 16 - 22)
Approved permit for TXU to relocate power poles. Contractor repaired entrance into W W P, transition from State to Freeport Parkway, and transition to Ruby Road due to heavy rains on the 18th & 19th.
WEEK 20 (Mar. 25 - 29)
Contractor is shaping -up the limed subgrade on State Road. Contractor is balancing the cut and fill and shaping -up the subgrade on Creekview In preparation for the lime stabilization. Larry had a verbal
discussion with Billy Wisenhunt about correcting items on Pay Estimate n13. Oncor is on the job site relocating the power poles on the west end of Creekview.
WEEK 21 (Apr. 1 - 5)
Contractor is lime stabilizing Creekview Drive. Contractor started paving southbound lanes of Freeport Parkway. Oncor is still in the process of relocating power poles on the west end of Creekview.
WEEK 22 ( Apr. 6 -13)
Contractor is setting forms on the eastbound lanes of Creekview Drive.
WEEK 23 (Apr. 15 -19)
Contractor Is setting forms on the eastbound lanes of Creekvlew Drive. Poured a section of the eastbound lanes on the 19th.
WEEK 24 (Apr. 22- 26)
Completed the eastbound lanes on Creekview Drive on the 23. Poring the median noses on Freeport Parkway. Poured the patterned concrete on one side on the Wagon Wheel Park entrance. Pouring
the Inlet throats on the eastbound lanes.
WEEK 25 (Apr. 29- May 3)
Dirt contractor correcting the grades on the westbound side prior to paving. Pouring the inlet throats on the eastbound lanes. Poured the westbound lanes. Sealed the patterned concrete.
Received the preliminary plans for the sidewalk.
WEEK 26 (May 6 -10)
Pouring the Inlet tops - contractor drilled into the 2 -inch water line. Inlets are not In the locations as shown on the plans.
WEEK 27 (May 13 -17)
Contractor poured the concrete on the median noses In preparation for the pavers. Poured the south entrance to Wagon Wheel Park. Poured the stamped concrete. Met with contractor to discuss the
location of the Inlet structures. Requested the contractor to shoot elevations along the gutter line for the length of the vertical curves.
WEEK 26 (May 20 - 24)
Contractor poured the concrete base for the retaining wall along Creekview. Started the construction of the modular brick wall.
WEEK 29 (May 27 - 31)
Worked on the modular brick wall. Poured the intersection at Creekview and Freeport Parkway and the intersection at the west end of Creekview.
WEEK 30 (June 3 -7)
Poured the sidewalk along Freeport Parkway. Removed the stamped concrete on the south side of the Wagon Wheel Park entrance and repoured.
WEEK 31 (June 10 -14)
Pulled forms on the sidewalk. Backfilling on the west end of Creekview in preparation for pouring the sidewalk.
WEEK 32 (June 17 -21)
Started laying the conduit for the electrical wires along Creekview Drive. Started removal of the asphalt transition on State Road and installed the pavers on one of the median noses on Freeport Parkway.
WEEK 33 (June 24 -26)
Poured hot mix asphalt transition on Freeport to State Road. Electrician trenching 7' conduit on west side of Freeport Parkway. Traffic routed from the northbound lanes on Freeport to the southbound
lanes.
WEEK 34 (July t -5)
Installed 2" tap on Irrigation system at WWP. Started beating valves on Creekview Drive for adjustment. Started staking the location of the sidewalk on Creekview.
Page 5
CREEKVIEW DRIVE & FREEPORT PARKWAY
ST 00-01
Schrickel Rollins & Associates
WEEK 36 (JULY 8 -12)
Poured footing for the handrail section located at the gabions. Poured a section of the walk and graded the remaining areas on Creekview Drive.
WEEK 36 (JULY 16 -19)
Worked on placing forms for the sidewalk and pouring sections of the sidewalk.
WEEK 37 (JULY 22 - 26)
Worked on placing forms for the sidewalk and pouring sections of the sidewalk. Oncor installed some of the street lights. Started installation of the handrail.
WEEK 38 (July 29 - August 2)
Started installing traffic buttons. Finished the asphalt transition on Freeport Parkway to State Road. Finished the installation of the brick pavers on the northem -most median nose. Replaced damaged
street light base. Oncor can continue the installation of the street lights. Freeport Parkway /State Road opened to traffic. Started grading of side slopes for the installation of the solid sod and
hydromuloh. Continued installation of the handrail.
WEEK 39 ( Aug. 6 - 9)
Installed remaining streetlights. Sealed joints in the pavement and did clean -up. Worked on the grading of the side slopes for the installation of the solid sod and the hudro mulch seeding. Stained the
handicapped ramps.
WEEK 40 ( Aug. 12 -16)
Worked on the installation of the air release valves and final grading on the side slopes for the installation of the sod and hydro mulch seeding.
WEEK 41 (Aug. 19 -23)
Worked on the installation of the air release valves and did general cleanup around the project. Adjusted the irrigation at the berms at the east end of the project.
WEEK 42 (Aug. 26 - 30)
No work was performed at the site.
WEEK 43 (Sept. 2- 6)
Contactor tilled and started the placement of the solid sod and the hydromulch seeding.
Page 6