Amberpoint BP 2-LR021024REPORT OF LIME PLACEMENT
Report Number: 94021380.0021
Service Date: October 18, 2002
Client: Transwestern Commercial Services
Attn: James Gaspard
5001 Spring Valley Rd Ste 600W
Dallas TX 75244
Report Date:
Project: Staples
201 Northpoint
Coppell, TX
Project Number: 94021380
8901 Carpenter Frwy., Suite #100
Dallas, Texas 75247
(214) 630-1010
October 24, 2002
Services:
Lime placement.
On this date, an HBC Engineering technician arrived at the above referenced jobsite as scheduled for
lime placement. HBC'stechnician observed the lime placement in an area, linesAto J and 4 to 5,
approximately 2, 912 square feet. No weight tickets were obtained on this date.
Technician: Bradford T. Rengstorff
Report Distribution:
(1) Transweslem Commercial Services
(1) Hill &Wilkinson, Ltd.
(1) O'Brien & Associales
(1) TechniStructures
(1) City of Coppell - Bldg Insp
(1) City of Coppell - Constr Insp
(1) HBC Engineering
(1) State Farm Insurance
Reviewed by:
HBC E~
Eugene Harbour
Principal
The tests were performed in general accordance with applicable ASTM, AASHTO, or DOT test methods. This report is exclusively for the use of the client
indicated above and shall not be reproduced except in full without the written approval of Terracon. Test results transmitted herein are only applicable
to the actual samples tested at the Location(s) referenced and are not necessarily indicative of the properties of other apparently similar or identical
materials, Page 1 of 1 ~,-SK~-r,,~K.y
REPORT OF SOIL-LIME MIXTURE PULVERIZATION
IBC
g901 Carpenter Frwy., Suite
Dallas. Texas 75247
Date of Service:
Client No.:
Client:
Contractor:
Test Location:
10/24/02
3181
Transwestern Commercial Services
5001 Spring Valley Rd Ste 600W
Dallas TX 75244
Hill & Wilkinson
Building Pad Subgrade
Test Method: NTCOG
Report No.:
Project No.:
Project:
Specification Requirements:
94021380.0034
94021380
Staples
201 Northpoint
Coppell, TX
Minimum Passing 1 3/4" Sieve: 100%
Minimum Passing #4 Sieve: 60%
Sample Condition: Field Moist
TEST 1-3/4" SIEVE #4 SIEVE
NO. LOCATION % PASSING % PASSING
1 Grid Line G.5/1.2 100 66
2 Grid Line E/1.2 100 69
3 Grid Line B.5/1.2 100 70
NOTE: Remix of lime treated material was stopped due to rain.
Technician: B. Rengstorff
Report Distribution:
(1) Transwestem Commercial Services
(1) Hill & Wilkinson, Ltd.
(1) O'Brien & Associates
(1) TechniStructures
tlw
(1) City of Coppell - Bldg Insp
(1) City of Coppell - Constr Insp
(1) State Farm Insurance
(1) HBC Engineering
Eugene Harbour
Principal
This report is exclusively for the use of the client indicated above and shall not be reproduced in full without written approval of HBC Engineering.