SS9901-EM021122DEFOREST ROAD
LIFT STATION IMPROVEMENTS
FORCE MAIN LINES A & B
CONSTRUCTION COST ESTIMATE
11/22/02
Item No.
Description
Unit
Quantity
Unit Price
Total
1
20" DI Force Main by open cut
LF
3602
$60
$216,120
2
20" DI Force Main by bore / no encasement
LF
208
$130
$27,040
3
20" DI Force Main by bore with 36" steel encasement
LF
888
$250
$222,000
4
30" DI Force Main by open cut
LF
708
$90
$63,720
5
30" DI Force Main by bore with 48" steel encasement
LF
102
$300
$30,600
6
Ductile Iron Fittings
TN
17.25
$4,000
$69,000
7
4" Combination A/V Valve with manhole
EA
8
$5,000
$40,000
8
Bore under exist tree / no encasement
EA
2
$750
$1,500
9
Hydromulch seeding
SY
3813
$1
$3,813
10
Traffic Control
LS
1
$2,500
$2,500
11
Storm Water Pollution Prevention
LS
1
$2,500
$2,500
12
Connect to Exist Manhole
EA
1
$5,000
$5,000
Sub -Total
$683,793
10% Contingency
$68,379
Total
$752,172