SS9901-EM021122DEFOREST ROAD
LIFT STATION IMPROVEMENTS
FORCE MAIN LINE D
CONSTRUCTION COST ESTIMATE
11/22/02
Item No.
Description
Unit
Quantity
Unit Price
Total
1
30" DI Force Main by open cut
LF
6178
$90
$556,020
2
30" DI Force Main by bore / no encasement
LF
857
$150
$128,550
3
30" DI Force Main by bore with 48" steel encasement
LF
1658
$300
$497,400
4
Ductile Iron Fittings
TN
18.825
$4,000
$75,300
5
4" Combination A/V Valve with manhole
EA
10
$5,000
$50,000
6
Bore under exist tree / no encasement
EA
15
$750
$11,250
7
Hydromulch seeding
SY
5424
$1
$5,424
8
Traffic Control
LS
1
$2,500
$2,500
9
Storm Water Pollution Prevention
LS
1
$2,500
$2,500
Sub -Total $1,328,944
10% Contingency $132,894
Total $1,461,838