SW0001-CS021104 (2)Pacheco Koch Consulting Engineers
WEEKLY PROJECT STATUS REPORT
DATE: November 4 - November 8, 2002 PROJECT NO.:
CLIENT: City of Coppell BY:
PROJECT: Riverchase Elementary School REVIEWED BY:
2230 - 01.148
Bradley J. Moss
Steve A. Markussen
Date Item
11/08 1. BJM called Suzan Taylor and informed her that the references for the low bid contractor
were acceptable and could be recommended if the 90 -day completion schedule is
acceptable with the City. Suzan requested a rough draft of the letter of recommendation
and will get back with BJM on the issue.
cc: City of Coppell — Kenneth Griffin
BJM /slt
2230 -35