SW0001-CS021104 (2)Pacheco Koch Consulting Engineers WEEKLY PROJECT STATUS REPORT DATE: November 4 - November 8, 2002 PROJECT NO.: CLIENT: City of Coppell BY: PROJECT: Riverchase Elementary School REVIEWED BY: 2230 - 01.148 Bradley J. Moss Steve A. Markussen Date Item 11/08 1. BJM called Suzan Taylor and informed her that the references for the low bid contractor were acceptable and could be recommended if the 90 -day completion schedule is acceptable with the City. Suzan requested a rough draft of the letter of recommendation and will get back with BJM on the issue. cc: City of Coppell — Kenneth Griffin BJM /slt 2230 -35