ST0001-CS020918 (2)Suzan Ta for - RE: Pa Estimate Pa e 1
From: "Schnitger, Chris" <cschnitger @sradesign.com>
To: 'Suzan Taylor' <staylor @ci.coppell.tx.us>
Date: Wed, Sep 18, 2002 9:14 AM
Subject: RE: Pay Estimate
Great! I guess you aren't planning on going out for the walk through this
morning? For the most part everything looked really good yesterday. The
sod was all down with a few exceptions and the street was clean. Now we
just need to deal with "the letters ".
Chris Schnitger, P.E.
Schrickel, Rollins & Assoc.
1161 Corporate Dr. W.; Ste. 200
Arlington, Texas 76006
(817) 649 -3216
(817 649 -7645 FAX
- - - -- Original Message---- -
From: Suzan Taylor [ mailto :staylor @ci.coppell.tx.us]
Sent: Wednesday, September 18, 2002 9:10 AM
To: cschnitger @sradesign.com
Subject: RE: Pay Estimate
It is in Ken's office and finance knows to expect it. They did get it
here yesterday before 5:00.
>>> "Schnitger, Chris" <cschnitger @sradesign.com> 09/18/02 08:31AM >>>
Do you know if ISI got their estimate in and if it looks like it is
going to
go through today?
Chris
Chris Schnitger, P.E.
Schrickel, Rollins & Assoc.
1161 Corporate Dr. W.; Ste. 200
Arlington, Texas 76006
(817) 649 -3216
(817 649 -7645 FAX
- - -- Original Message---- -
From: Suzan Taylor [ mailto :staylor @ci.coppell.tx.us]
Sent: Tuesday, September 17, 2002 4:15 PM
To: cschnitger @sradesign.com
Subject: RE: Pay Estimate
Tell them they can get it here around 7:30 tomorrow morning. Paula
comes in at that time so she can be here to get it. They do not have
to
worry about getting it here by 5:00.
>>> "Schnitger, Chris" <cschnitger @sradesign.com> 09/17/02 03:57PM >>>
The dates shouldn't change if Estimate No. 6 was paid. Estimate No.6
goes
up to 7/15/02.
1 just got the latest revised copy and I am going to check it quickly
Suzan Ta for - RE:�Pay Estimate � n � � _ �� � Pale 2 �'
and
call ISI back so they can send Billy with the original.
Chris
Chris Schnitger, P.E.
Schrickel, Rollins & Assoc.
1161 Corporate Dr. W.; Ste. 200
Arlington, Texas 76006
(817) 649 -3216
(817 649 -7645 FAX
- - - -- Original Message---- -
From: Suzan Taylor [ mailto :staylor @ci.coppell.tx.us]
Sent: Tuesday, September 17, 2002 3:48 PM
To: cschnitger @sradesign.com
Subject: Re: Pay Estimate
Did you receive a faxed copy of the revised estimate #7? Larry
thought
the dates were supposed to change. The current payment due is the
same
as the previously submitted estimate. I am going to check the
numbers.
>>> " Schnitger, Chris" <cschnitger @sradesign.com> 09/17/02 08:37AM >>>
Suzan,
I looked over Pay Estimate No. 7 and I have a few comments.
According to the sidewalk that we measured last week I came up with
2122 SY
of 5" sidewalk (Item No. 109). ISI is charging for the entire bid
item
of
2300 SY. We need to change that. On the other hand ISI is only
charging
for 887.67 SY of HMAC (Item No. 108) and we measured 1456 SY. I also
notice
that ISI is only charging for one Type A Manhole (Item No. 202), Larry
would
know for sure but they should have installed two of these. They
haven't
charged for any buttons as of yet. I also noticed that they haven't
charged
for the Sanitary Sewer Manhole Adjustment (Item No. 401). The only
other
quantity that I had a problem with was 2" Sch. 40 PVC (Item No. 602).
ISI
sent a letter dated August 9th that states that they ran an extra 155
linear
feet of conduit for the street lights. The bid quantity was 4755 LF,
if you
add 155 LF you get a total of 4910 LF not the 4971.75 LF that they are
asking for.
Chris