Suzan,
I'll have to check the plans and take a look at the cut sheets. We did not
plan on placing any fill on the property to the East of Freeport Parkway
when we did our quantities.
Chris
..... Original Message .....
From: Suzan Taylor [mailto:staylor@ci.coppell.tx.us]
Sent: Monday, December 03, 2001 1:42 PM
To: cschnitger@sradesign.com
Subject: Creekview Drive & Freeport Parkway
Chris:
Larry met with the contractor today. The contractor says their cut sheets
indicate approximately 11,000 CY of excavation on the project as opposed to
the 6500 CY as shown on the bid sheet. The contractor will send a copy of
their cut sheets to you and let you determine whether they have a bust in
their grades or there is a mistake in the bid quantity.
Does the 3000 CY of roadway fill shown in the bid quantities include the
fill on the east side of Freeport Parkway. It is not indicated as
compacted fill on Sheet 8 of the plans. The contractor thinks that it is
not included.
Thanks
Suzan