re: Creekview Drive & Freeport Parkway in the City of Coppell
I just spoke with Jay Simms ( our construction supervisor) who will be
relocating the facilities he advised me he would begin relocation the week of
November 26th. He can be contacted at 972-318-3247.
Thanks,
Olga M Sauseda
Engineer-Network Eng./OSP Eng.
Distribution Planning-North Central
PH.972-434-0817, Fax 972-434-1420
olga.sauseda@verizon.com
.......... Original Text ..........
From: "Suzan Taylor'' <staylor@ci.coppell.tx.us>, on 11/15/01 4:26 PM:
Olga:
The contractor for the above referenced project will stake the project next
week in anticipation of starting excavation the week of November 26th. Can
you tell me the status of the relocation of the Verizon facilities. As
discussed, the utilities will need to be relocated on or before December 1,
2001 in order to avoid any conflicts with the proposed construction.
Thanks