ST9904-CS021011 TxDOT SH 121 TASK FORCE REPORT
Note: Section numbers in narrative below correspond to numbers on drawings.
I. COMPLETED PROJECTS
Section From To Description Date Completed
1 Tarrant CL Denton CR 4-lane ML w/2-lane FR Jul 1992
2 Denton CR IH 35E 4/6 lane divided highway Nov 1993
3 IH 35E FM 1171 6-lane divided highway Jun 1991
4 FM 1171 Elm Fork 6-lane divided highway Jul 1988
5 Elm Fork BNRR 4-lane divided highway Feb 1994
5B Crider Road FM 423 Eliminate intersection Sep 1995
6 BNRR Legacy 4-lane divided highway Mar 1994
7 Legacy SH 289 4-lane divided highway May 1995
9 Denton CR Denton Tap Road BP: 3-lane frontage roads Oct 1998
10 Denton Tap Road Lake Vista BP: 3-lane frontage roads Jul 1988
11 Lake Vista IH 35E BP: 3-lane frontage roads Jun 1996
12 IH 35E FM 544 BP: 3-lane frontage roads Oct 1999
II. DENTON COUNTY PROJECTS
Section 13: Tarrant County Line to North of Denton Creek (conversion to
freeway)(CSJ 0364-02-017 & 0364-03-064)
The Texas Transportation Commission at their July 2001 meeting under
the Innovative Financing Program advanced this project to Priority 1 in
Category 3A - NHS Mobility.
2. Estimated Construction Costs:
CSJ COUNTY FROM TO Length COST Letting FY
Based on
Projected
Funding Levels
~ T~ant FM~g~ ~nto~:CL 5.2,:00 $~0~00
0364-02-017 Dallas Tarrant CL Denton CL 1.728 $70,100,000 2007
0364-03-064 Denton Dallas CL Denton Crk 0.300 $11,700,000 2007
Total $~)~ ~
TxDOT's Fort Worth District is including this section of the SH 121 Free-
way in an ongoing MIS, Schematic, and EA consultant contract they have
in the area. The Fort Worth District is working closely with the City of
Page 1 of 3
Updated: 10/10/02 5:56 PM
Grapevine to develop the transportation needs in the area. The following
are estimated milestone dates:
DESCRIPTION ESTIMATED DATE
MIS Complete
Public Meeting: Preliminary Schematic and EA findings presented. October 2002
Public Hearing: Final Schematic and Final EA presented. Summer 2003
The Public Meeting and Heating dates have been pushed back to allow the
consultant to address traffic modeling issues and Grapevine and Coppell
ramp location concerns. The Dallas District will handle the PS&E (either
in-house or in partnership with Denton County).
Section 14: Existing SH 121 Near Denton Creek to Existing SH 121 Near
FM 544 (Lewisville Bypass)(Mainlanes)(CSJ 3547-03-003, 3547-02-004, 3547-
01-005, 3547-01-008, & 3547-01-009) Denton County
1. Estimated Construction Costs:
CSJ Designer FROM TO Length COST Letting FY
Based on
Projected
Funding Levels
3547-03-003 Halff SH 121 Dallas CL 0.500 $1,800,000
3547-02-004 Halff Denton CL Denton CL 1.800 ${~.~ 2003
3547-01-005 Halff Dallas CL Lake Vista 1.085 ~i
3547-01-008 Halff Lake Vista IH 35E 0.730 $~ ~
Sub
3547-01-009 C&B Hebron FM 544 3.432 $37,120,000 2004
Total ~
The Halff projects listed above will be combined into one construction
contract.
Co
Section 15: Denton County Portion: FM 544 to DNT
Bridgefarmer Design
The Texas Transportation Commission at their July 2001 meeting under
the Innovative Financing Program advanced these frontage road projects
to Priority I in Category 3A - NHS Mobility.
These mainlanes will be funded with a combination of local funds and
Page 2 of 3
Updated: 10/10/02 5:56 PM
funding from the North Central Texas Council of Governments
(NCTCOG).
3. Construction Costs:
CSJ County FROM TO Length COST Letting FY
Based on
Projected
Funding Levels
0364-03-066 Denton FM 544 Collin CL 4.947 $74,800,000 2004
0364-04-038 Collin Denton CL DNT 0.982 $14,200,000 2004
Total $89,000,000
III. COLLIN COUNTY PROJECTS
A. Section 15: Collin County Portion: DNT to US 75
1. Project Under Construction:
CSJ County FROM TO Length COST LETTING
DATE
0364-04-023 # Collin DNT Interchange $31,000,000 11-27-2001
I IT°tal $31,000,000
# NTTA project with joint funding: NTTA = $19.9M; TxDOT = $11.1M.
2. Current Design Projects:
CSJ County FROM TO Length COST LETTING
DATE
0364-04-037 Collin DNT Custer 4.912 $~ ~Q0 er~2003
0364-04-022 Collin Custer US 75 6.037 $ 7 ~0Q0 11-2002
Total
Note:
Project 0364-04-037 includes mainlanes from the DNT to SH 289 and the 3-level inter-
change at SH 289. Project 0364-04-022 includes the overpass and ramps at Custer Road.
,¸
4. Future Project:
CSJ County FROM TO Length COST
0364-04-024 (ML) Collin SH289 US 75 9.059 $90,000,000
Total $90,000,000
Page 3 of 3
Updated: 10/10/02 5:56 PM