Wynnpage North 1-CS030129
From:
To:
Date:
Subject:
Teresa Turner
Ken Griffin
1/29/0310:43:24 AM
Wynnpage
Ken:
Mark Wainscott and Marc Bentley are asking me for a solution to their drainage situation. Mark W. is
adament that we have had utility information throughout the process and that - since no inlets were shown
on the site plan - we should have assumed what they were planning to do with the runoff.
In looking through the file, the timeline is as follows:
ORC Dates - 9/26/02 and 10/3/02
P&Z Meeting - 10/17/02
Preliminary Utilities Received - 10/29/02
CC Meeting - 11/12/02
Additionally, I sent James Bratton (with Wainscott) a letter on 12/27/02 regarding early grading and the
fact that we still did not have detailed drainage information.
They submitted full plans for engineering review on 1/22/03.
I have the highlighted copies of the staff reports. ORC comments, and the letter in my office if you would
like to see them.
How should I proceed?
fteresa Ti.ii'~@V c WY1illp~gEr~'-"c ' .
I~, -' . '''''~' ",,-'
_"- .._J.c_',. ,__,',.....__.,-.~"'=_.."_.c-'",'"'..'"'."""::-::::;- .
/;"';'",:;;;;'."""""-'
. . Page'1;
,.." - '..-..,'~. --"
--,-",',~.~"-~~",~,"""~~~",""-~-~,_..,,..;~,",.,"",,
From:
To:
Date:
Subject:
Teresa Turner
Ken Griffin
1/29/03 11 :05:32 AM
Wynnpage
I forgot to mention that they still don't know how they will get sewer services to Lots 2 & 3. Apparently
there is a high pressure gas line in the Lone Star Gas Easement that is only 4' deep. They are looking at
doing gravity flow across Lot 1 and then adding a lift station on the other side of the gas easement for Lots
2 & 3. Is this allowed??
Also, they cannot construct a manhole in the easement so they are asking to stub the sewer as shown
with a cleanout Oust short of the property line), Thoughts?