ST0001-CS020826$12b/z Equitable Compensation Claims - Creekview Drive: Item Additional No. Description Total Cost Time (Days) Contractor's Explanation 1 Temporary Roads $14,286.53 24 Labor and equipment required to instal remove and maintain temp. roads (flex base) not originally phased in contract. General Conditions � $52,620.37'" Barricade Maintenance P $9,399.72 Concrete Labor Inefficiency Y $30,081.23 Extra Mobilization P $23,332.84 2 Extra Excavations t,5 $18,041.01 — 3 Excess Dirt Haul Off -Site L $68,121.98 4 Stock Pond Work X 17 894.95 TOTAL $233, 778.63 16 14 6 7 35 10 112 Contract Time: 150 Cal. Days SRA's Comments t, Contractor submitted one Phasing Plan on 2/7/02. Temp. pvmt. required for ingress and egress. Compensation for labor and equipment for additional time due to phasing. Compensation for labor and equipment due to phasing. Pouring of concrete. Mobilization due to phasing. Additional excavation for sidewalk and There are bid quantities for this for relocating existing stockpile. work. Required to take excavated materials off -site. Addendum No. 1 addressed this issue. Removal of trees at stock pond. I don't recall that ISI was instructed to do this work. Ute 6. 4 a w "De vv, o Lr-e Co„CN&� s d4'V zz aT 3 dam X11 b 23 332. $4 pvxxs;, W y� �" W W U 1b 39R 1 7 1 1 - 44 N N N coo ssi �ssb3� NOO �h as oaa N C4 44 N C4 C4 X11 b 23 332. $4 1 4- ' 00131,2 2 -4- 14 Z9b .S3 1b 39R 1 7 1 1 - 44 1 TL� �ssb3� Cxcaudlkg uvDL-40 7 1 e� 041 .0 1 3 Gib, 121,C.N% 9 — /67• T 1Q �S Z. 200 �OZ� r w S �' /o