Freeport NIP(7.0)-LR030314Ro gineers 8908 Ambassador Row Dallas, Texas 75247-4510 (214) 630-9745 (214) 630-98~9 (fax) REPORT OF WATER INJECTION INSPECTION Client: Duke Realty Services, LP Arm: Mr. Jeff Langston 5495 Belt Line Road, Suite 360 Dallas TX 75254 Project: Freeport 10 500 Freeport Parkway C0ppell, TX Services: Water Injection Inspection Report No.: 172430 Project No.: 037333 Date of Service: 03/10/2003 Report Date: 03/14/2003 Report of Inspection On this date, a Rone Engineers, Ltd. representative(s) was on site to perform Water Injection Inspection. The results are attached. Technician Time: 6:30 a.m. - 2:30 p.m. Page 1 of 3 Technician: Lanny Gist Report Distribution: (1) Duke Realty Services, LP (1) Duke Realty Services, LP (1) City of Coppell Engineering Dept. (1) Pacheeo Koch Consulting Engineers (1) Engineering Analyst (1) City of Coppell Engineering Dept. K. Scott Watson CMT Operations Manager LIMITATIONS: The test results presented herein were prepared based upon the specific samples provided for testing. We assume no responsibility for variation in quality (composition, appearance, performance, etc.) or any other feature of similar subject matter provided by persons or conditions over which we have no contml. Our letters and repons are for the exclusive use of the clients to whom they are addressed and shall not be repmduced except in full without the written appmval of Rone Engineers, Ltd. 99DD PaRe 1 of 1 WATER INJECTION OBSERVATION Client: Duke Realty Services, LP Report No.: 172430 Project No.: 037333 Project: Freeport 10 Date of Service: 3/10/2003 500 Freeport Parkway Page 2 of 3 · DESCRIPTION/EXPLANATION YES NO NIA · Specific gravib/of lime was checked and found to be 1.14 and 1.17 N/A 2. Lime slurry was continuously agitated N/A 3. Surfactant was added to each load X ~,. The injection pressure was kept between 50 to 100 psi at point of injection X 5. Intervals of 12" were achieved during iniection process until refusal x 6. Total depth of iniection -- 10 feet X 7. Max. spacing of iniection probes was recorded to be 5 ft. X 8. Free lime on surface N/A 9. Square feet injected on this date 129,500 10. Location of iniection Building Pad C-3 Remarks: completed 5th pass, began 6th pass See attached for sketch of injected area, pass number for each area, dimension of injection area, and amount of lime used on this date. Time: Technician: 6:30 a.m. - 2:30 p.m. L. Gist LIMITATIONS: The test results presented herein were prepared based upon the specific samples provided for testing. We assume no responsibility for variation in quality (composition, appearance, performance, etc.) or any other feature of similar subject matter provided by persons or conditions over which we have no control. Our letters and reports are for the exclusive use of the clients to whom they are addressed and shall not be reproduced except in full without the written approval of Rone Engineers, Inc. --H-I-FI RoneEngineers 8908 Ambassador Row Dallas, Texas 75247-4510 (214} 630-9745 (214) 630-9819 (fax) IN-PLACE DENSITY TESTING Client: Project: Services: Duke Realty Services, LP Attn: Mr. Jeff Langston 5495 Belt Line Road, Suite 360 Dallas TX 75254 Freeport 10 500 Freeport Parkway Coppell, TX Perform In-Place Density Test in accordance with ASTM Standards. Report No.: 172525 Project No.: 037333 Date of Service: 03/11/2003 Report Date: 03/14/2003 PROJECT DATA CONTRACTOR: Duke Realty Services, LP Test Methods: ASTM D-2922 ASTM D-3017 M/D No. Description Gauge: Troxler 3430 Moisture Gauge Serial No: 32720 Current: 656 Test Mode: DT Previous: 654 MOISTURE DENSITY RELATIONS Maximum Moisture % Density pcf Tan Grayish Brown Clay w/Traces of Sand 21.5 103.5 Standard Counts Density Current: 3055 Previous: 3092 Project Requirements Moisture Density Optimum +4 95 min FIELD DENSITY TESTS TEST PROBE NO TEST LOCATION DEPTH M/D MOISTURE WET DENSITY DRY DENSITY DENSITY No. (%) (pcf) (,pc0 (% max) Backfill Storm drain, Line 1, Station 2+00, 1 st lift 6" 1 22.9 Backfill Storm drain, Line 1, Station 1+75, 2nd lift 6" 1 21.8 Test results on this report meet project specification. Technician: Lanny Gist Report Distribution: (1) Duke Realty Services, LP (1) Duke Realty Services. LP (1) City of Ceppell Engineering Dept. (I) Paeheco Koch Consulting Engineers Started: 12:00p (1) Engineering Analyst (1) City of Coppell Engineering Dept. 123.6 100.6 97 123.4 101.3 98 CMT Operations Manager Finished: 2:00pm LIMITATIONS: The test results presented heroin were prepared based upon the specific samples provided for testing. We assume no responsibility for variation in quality (composition, appearance, performance, etc.) or any other feature of similar subject matter provided by persons or conditions over which we have no control. Our letters and reports am for the exclusive use of the clients to whom they are addressed and shall not be reproduced except in full without the written approval of Rone Engineers, Ltd. 07DD Page 1 of 1 gineers 8908 Ambassador Row Dallas, Texas 75247-4510 (2114) 630-9745 (214) 630-9819 (fax) REPORT OF WATER INJECTION INSPECTION Client: Duke Realty Services, LP Attn: Mr. JcffLangston 5495 Belt Line Road, Suite 360 Dallas TX 75254 Project: Freeport 10 500 Freeport Parkway C0ppell, TX Services: Water Injection Inspection Report No.: 172526 Project No.: 037333 Date of Service: 03/11/2003 Report Date: 03/14/2003 Report of Inspection On this date, a Rone Engineers, Ltd. representative(s) was on site to perform Water Injection Inspection. The results are attached. Technician Time: Page 1 of 3 Technician: Lanny Gist Report Distribution: (1) Duke Realty Services, LP (1) Duke Realty Services, LP (1) City of Coppell Engineering Dept. (1) Pacheco Koch Consulting Engineers 6:30 a.m.'- 12:00 p.m. (1) Engineering Analyst (1) City of Coppell Engineering Dept. K. Scott Watson CMT Operations Manager LIMITATIONS: The test results presented herein were prepared based upon the specific samples provided for testing. We assume no responsibility for variation in quality (composition, appearance, performance, etc.) or any other feature of similar subject matter provided by persons or conditions over which we have no control. Our letters and reports are for the exclusive use of the clients to whom they are addressed and shall not be reproduced except in full without the written approval of Rone Engineers, Ltd. 99DD Page 1 of 1 WATER INJECTION OBSERVATION Client: Duke Realty Services, LP Report No.: 172526 Project No.: 037333 Project: Freeport 10 Date of Service: 3/11/2003 500 Freeport Parkway Page 2 of 3 · DESCRIPTION/EXPLANATION YES NO N/A · Specific ~ravit)/of lime was checked and found to be 1.14 and 1.17 N/A ;~. Lime slurr~ was continuously a~litated N/A 3. Surfactant was added to each load X ~. The injection pressure was kept between 50 to 100 psi at point of injection x 5. Intervals of 12" were achieved during iniection process until refusal x !6. Total depth of injection -- 10 feet x 7. Max. spacing of injection probes was recorded to be 5 ft. X 8. Free lime on surface N/A 9. Square feet iniected on this date 123,500 10. Location of iniection Building Pad C-3 Remarks: completed 6th pass water See attached for sketch of injected area, pass number for each area, dimension of injection area, and amount of lime used on this date. Time: 6:30 a.m. - 12:00 p.m. Technician: L. Gist LIMITATIONS: The test results presented herein were prepared based upon the specific samples provided for testing. We assume no responsibility for variation in quality (composition, appearance, performance, etc.) or any other feature of similar subject matter provided by persons or conditions over which we have no control. Our letters and reports are for the exclusive use of the clients to whom they are addressed and shall not be reproduced except in full without the written approval of Rone Engineers, Inc. RoneEn gineers 8908 Ambassador Row Dallas, Texas 75247-4510 (214) 630-9745 (214) 630-9819 (fax) REPORT OF REINFORCING STEEL INSPECTION Client: Duke Realty Services, LP Attn: Mr. JeffLangston 5495 Belt Line Road, Suite 360 Dallas TX 75254 Project: .Freeport 10 500 Freeport Parkway Cbppell, TX Services: Reinforcing Steel Inspection Report No.: 172530 Project No.: 037333 Date of Service: 03/11/2003 Report Date: 03/14/2003 Report of Inspection On this date, a Rone Engineers, Ltd. representative(s) was on site to perform Reinforcing Steel Inspection. The results are attached. Technician Time: Page 1 of 2 Technician: Lanny Gist Report Distribution: (1) Duke Realty Services, LP (1) Duke Realty Services, LP (1) City of Coppell Engineering Dept. (1) Pacheco Koch Consulting Engineers 2:00 p.m. - 2:30 p.m. (1) Engineering Analyst (1) City of Coppell Engineering Dept. Watson CMT Operations Manager LIMITATIONS: The test results presented herein were prepared based upon the specific samples provided for testing. We assume no responsibility for variation in quality (composition, appearance, performance, etc.) or any other feature of similar subject matter provided by persons or conditions over which we have no control. Our letters and reports am for the exclusive use of the clients to whom they are addressed and shall not be reproduced except in full without the written approval of Rone Engineers, Ltd. 99DD Pa~e 1 of 1 8908 Ambassador Row Dallas, Texas 75247 (214) 630-9745 121 North Rayner Fort Worth, Texas 76111 (817) 831-6211 Client: Project: Report of Reinforcing Steel Inspection Report No.: Project No.: Date of Service: Page Locations and Items Inspected: /D~', ,~? /tPqfc~ q~- J'7~,.~-~ g/~e' 5'- / Items Inspected: Conforming Non Items Inspected: Conforming Non Items Inspected: Conforming Non Conforming Conforming Conforming Placing Drawings Bar Length Column Ties Properly Approved ~ and Sha~e ~ Tied and Spaced Bar Size ~ Proper Bar Placement ~ Stirrup Spacing and Type Bar Grade ~ Properly Tied ~ Lapped Splices L~ Bars Clean ~ Dowel Bars in Place ~ Welded Splices ~ Form Clean t~ Proper Bar Supports ~ Mechanical Splices __ Number Bars ~ Proper Cover ~ Discrepancies/Comments: Inspector's Signature: Time: to Client/Contractor Signature: Client/Contractor Copied with Results: Yes / No RoneEng neers 8908 Ambassador Row Dallas, Texas 7524%4510 (214) 630-9745 (214) 630-9819 (fax) REPORT OF REINFORCING STEEL INSPECTION Client: Duke Realty Services, LP Atto: Mr. JeffLangston 5495 Belt Line Road, Suite 360 Dallas TX 75254 Project: Freeport 10 500 Freeport Parkway C0ppell, TX Services: Reinforcing Steel Inspection Report No.: 172471 Project No.: 037333 Date of Service: 03/10/2003 Report Date: 03/14/2003 Report of Inspection On this date, a Rone Engineers, Ltd. representative(s) was on site to perform Reinforcing Steel Inspection. The results are attached. Technician Time: Page 1 of 2 Technician: Lanny Gist Report Distribution: (I) Duke Real~y Services, LP (1) Duke Realty Services. LP (1) City of Coppell Engineering Dept. (1) Pacheco Koch Consulting Engineers 2:30 p.m. - 3:00 p.m. (1) Engineering Analyst (1) City of Coppell Engineering Dept. 3tt Watson CMT Operations Manager LIMITATIONS: The test results presented herein were prepared based upon the specific samples provided for testing. We assume no responsibility for variation in quality (composition, appearance, performance, etc.) or any other feature of similar subject matter provided by persons or conditions over which we have no control. Our letters and reports are for the exclusive use of the clients to whom they are addressed and shall not be reproduced except in flag without the written approval of Rone Engineers, Ltd. 99DB Pa.e 1 of 1 8908 Ambassador Row Dallas, Texas 75247 (214) 630-9745 121 North Rayner Fort Worth, Texas 76111 (817) 831-6211 Report of Reinforcing Steel Inspection Client: ~0~/~ Report No.: [ 7 2 ~!'7 { Project No.: Project: /t~co~,~ ./~la Date of Service: Page 0'37333 [ of / Locations and Items Inspected: Items Inspected: Conforming Non Items Inspected: Conforming Non Items Inspected: Conforming Non Conforming Conforming Conforming Placing Drawings Bar Length Column Ties Properly Approved ~/ and Shape IL~ Tied and Spaced ~ Bar Size ~/ Proper Bar Placement ~ Stirrup Spacing and Type _ Bar Grade ~ Properly Tied I~ Lapped Splices ~,~ Bars Clean t,/ Dowel Bars in Place ~ Welded Splices ,.--...--~ Form Clean ~ Proper Bar Supports ~ Mechanical Splices , , - Number Bars L~ Proper Cover ~ Inspector's Signature: ~. ~;~/~ Time: to Client/Contractor Signatur .~. ~-~/~ Client/Contractor Copied with Results: Yes / No