St Joseph-CN030312~ `~ CITY OF COPPELL ~! CHANGE OR EXTRA WORK ORDER ~ `~ PROJECT: ST. JOSEPH'S VILLAGE CONTRACTOR: ST. JOSEPH'S VILLAGE, INC. OWNER: City of Coppell CHANGE ORDER NO.: TWO (2) DATE: 3/12/03 Description Total ADD: Starleaf Improvements: 1. Demo Existing Sidewalk $195 2. Install New Sidewalk to match existing $225 3. Administrative Fees $67 Total Revision to Contract Amount $4g7 Previous contract amount $690,132 Net increase in contract amount ~ 487 Revised contract amount $690,619 The contractor hereby accepts this Contract adjustment as a final and complete adjustment in full accord and satisfaction of all past and future liability originating under any clause in the Contract by reason of this revision to the Contract. r 3 • l2.3 City Engineer Date 3/303 Agreed to b Contractor Date ~~-°~ <rJ °%~~ A~~pted by Owner Date 03/11/2003 08:54 9724711499 CENTEX ST. JOSEPH CENTEX March 11, 2003 CONSTRUCTION COMPANY 1201 b Sandy Luke Road Coppell, Tcxav 75019 Mr. Garreth Campbell The Cit}• of Coppell );agineenng 25~ Parkway Blvd. Coppell, TX 75019 RE: St. 7oseph Village SLJBJ: Proposal # 1061 Demo Existing Sidewalk & Replace Sidewalk at South End to tie into existing. Dear Mr_ Campbell: PAGE 01/04 We are submitting, herewitL, our Request for Change Order (Proposal) # 1061 in the amount of Four T•Tundred Eighty Seven Dollazs ($4S7) to provide for Demolition of Existing Sidewalk & Installation of new Sidewalk at South End of Star Leaf Road to tie into existing. Please notify Centex of your acceptance of this proposal as soon as possible. This proposal covers only the changes to the specific work as set forth in the attached Proposal breakout. Changes in the work and associated price adjustments other than those noted in our Proposal are not included. Please execute the attached Approval Form and return to us as soou as possible. Should them be any questiors pertaitdng to this Proposal, please feel free to reach us the job-site office. Sin e y, V/ Ryan Robe s Asst. Project Manager T A.S RCO #23 dated 03/07/03 `_ ~lJe lrv,~ -I~ ~~- s ~r 3. , Z-o 3 VLIY 1 LT ~ 1 JUUtYH CENTEX C®NSTRUCTION CQMI~'ANY Proposal Recap PAGE e2iea Proposal Number 1061 Owner's Reference Number PR-1061 Description Demo Existing Sidewalk & Replace Sidewalk at South End bo Yie into existing. General Contractor -Direct Costs $D.00 $0.00 $0.00 $0.00 rYw p„ irl II , ~)LN n w ~ ~ '~I > ~:• RY Y Y ~ I -~ r r'.•' i I i•iM Ylr I 'J r qo IW I G~~~tiAccount+' 1' ~' ~(i',! ~ ~~'pig!~Des~Crip~l;an~li~~~"(i~,lya %^ , ~'^!TI ~"~ ~~Yr~lil;'i'~ ~,, iSubcorttk~;~tor~,R', ~';!f. , . ^ ~ `'t ~ 'I ;+To~ati~,'~;R~ -- ". x W.... ~,...„ .....M J....J. k~. 1 a. l 027510-5 Concrete Paving and Walks T.A.S. Commeraal Concrete Construction $420.00 Subcontracting Subtotal... $420.00 ~ i 117IIi 10 °` T I 14 ii 1 AI ~•1 Vir're lli rl .., i ir,• ii r i 1 I' ~'tl ~ ~ ~~ ~lTDtah '., ~,.Y~~ ~ ii 1 ~'I "~ IL. Il~~'iili !' !, I~~,it)~ ftl ~d ~~ 1 I~lili{~~': L rr ~i '! a ,~ t {~,~,~i~li,i~ ~I ~Ily,y~ 1 Cd ~i 1 ~I~ltl,; t`B~IS, ';: ~~I 'i'i~ ~ 1, i, h~ ti II !I,~~.Ill ~.~..1_,1::.,~. ~ '! Q. ~ C4,~.. ~ 1 yl.~i i.~«.~ ~~JJ,.,14!':r.1_ i~t~l Ld i r• ~....a.._.~...__ ~ ...:4 196600 A Genera! Liability 0.791 $420.00 $3.00 196100 A Subguard 1.1 $420.00 $5.00 ~ 95000 A Builders Risk G.005 $420.00 $0.00 191000 Overhead 10 $420.00 $42.00 Overhead Subtotal... $50.00 ! 4 1 11 ' {~'~`~.~~W..:i:.-.~._...~.....r.w.... •~` FB~,. 6.'_..~~~'ulililll'i!1'." ~.:Y^._ ~1~' ~~-.~;^~ii ~iel~i`%~i 1 nW ~~_..rg8$IS~.: ~ Iii11~~,~TOtdJh ~~i~ ~'ji 001955 A IT 0.35 $470.00 $2.00 001772 A Safety 0.3 $470.00 $1.00 999990 C Change Order Fee 3 $470.00 $14.00 Fees Subtotal... $17.00 PROPOSAL GRAND TOTAL.., 5487.00 __. __. _,,,,,, ,,,,,,,~ ~,~..,li.,» l;tNltx ST. JOSEPH PUGE 63104 St. Joseph Village PROPOSA)r # 1061 +Y+++rt++++++f+w+++*++++++rts+#wsw***3•r+++r+k++rtsrtx+++s***+•+++++h+»+w*+*++rt+x•+k :tYf+x+*~k*+*+++#+ The following additional work completed by Centex Construction Companyis hereby approved: Costs: The total Cost to perform the work as described above is an ADD oFxour Hundred Eighty Seven Aollars ($487}. Please indicate youz acceptance and approval of this additional work in the space provided below C Reviewed by lrre}~eet: Date: Autlwrization Crranted bye Date: Proposal # 1061 Filc __._, v,__,.._ „ ~t+vitn 5i. JUStYH PAGE 84104 SEN1 s7"ETAS CUNSTRUCT1on 1NC. 3-10- 3 ~ ~-54PM T.a.S. CO>rSTRUCT1on~ s72a'11499.~ li i Fax Transmittal To~ Canbx Constryctlon Company Date' 03,~g7/p3 120t E. Sandy Lake Road CoppeU, TX. 75019 Attn: Ryan R. / PnlhOny t.. Phase 972 471.444 Fax: 972 471-1499 Project; St. Joseph Vdlflge TAS #~ 20163 Subject: RCO ii23 Request For Change Order Domo d Replace Sidewalk at South End of 3hr Leaf 7A5 Commercal GOncret0 Constructon, t. P. is pleased to submit tho following cost proposal. The proposed cost break down is as follows. Item Equip. Phase No. Description Quantity Unit Labor Material Svb Total 2300 1 Demo Existing Sidewalk 60.00 sf $0.00 50.D0 $195.00 5195.1N1 2J00 2 tnstatl New Sltleh'alk to Match Existing 109.00 5f $156.00 $67.00 SO.00 5225.00 Total Sd20.00 Quallfica!ions: Nona ExGusiors Non« Fleece issue a Change Order at your aarGe61 convenience. Sincerely, TAS Commercial Concreto Construction, L•P. J Y P Projotl Manager cc File 20163 Red Flannagan ,l:~ck Clapp RGO iop3mDJ