ST9304-CS 990430 BELTLINE ROAD PROJECT 490-403.1/94,r829
k ,nton Tap Road to MacArthur Boule ~d) 9oac~
Project Status Report c;,
April 30, 1999
PROJECT ENGINEER: John L. Meats
PROJECT LOCATION: District 1; Coppell, Dallas
FUND 490403 FUND 418-829 FUND 418-830
PROJECT DOLLARS
Authorization = $ 4,250,000 $6,100,000 $1,500,000
Available = $ 501,237
**BELT LINE RD.(91-829) AND SANDY LAKE RD.(91-830) IN 1991 BOND FUNDING AT $7.6 MIL
County Construction = $ 6,132,184
Contingencies (5%) = $ 306,609
ROW Acquisition = $ Coppell; Dallas 75,000
Administrative Costs = $ 400,000
Design = $ 336,640
Materials Testing (1.0%) = $ 61,322
TOTAL PROJECT COST = $ 7,311,755
IPlus Sandy Lake Brg. 91-838(from 91-830) = $ I 482,501 I
iTotal F,,sfirnated = $ 8,064,256 I
lDallas County Participation = $ 8,101,237 ~
IF.s~m~t~l Surplus = $ 36,981 I "
3F_.SIGlq: Consultant/Award/Work Order/Contract Total
Albert H. Halff Associates/8-30-94/8-31-94I$316,040/contract amendment pending approval
Status = 95%
Issues/Conflicts = TUE RR spur; traffic signals/City, DART
Completion = JUN 99
ROW: Number of Parcels = 18 (mostly slope easements)
Status =
Status of Acquisition = by City of Coppell; Dallas County for City of Dallas
Issues/Conflicts = DART
Completion = SEP 99
UTILITIES: Utility Release = NOV 96 COi~ISTRIJCTIOI~,I: Advertisement = SEP 99
Utilities to be Cleared Contractor/Award/Work
Status Order/Total Contract
Issues/Conflicts Working Days
Completion = SEP 99 Status
Issues/COnflicts
Completion = EARLY 2001
490.403.1/829.PSR