REPORT OF DRILLED PIER INSPECTION
CHent:
Duke Realty Services, LP
Attn: Mr. JeffLangston
5495 Belt Line Road, Suit~ 360
Dallas TX 75254
Report No.: 176540
Project No.: 037333
Date of Service: 05/09/2003
Report Date: 05/14/2003
Project: Freeport 10
500 Freeport Parkway
Coppell, TX
Services: Drill~d Pier Inspection
Report of Inspection
On this date, a Rone E~gineers, Ltd. representative(s) was on site to perform
Drilled Pier Inspection. The results are attached.
Technician Time:
Page 1 of 5
Technician: Rick Smith
Report Distribution:
(1) Duke Realty S~rvicea, LP
(1) ~ Renlty Services, LP
(1) City of Copp~ll BuildinE Dept.
(1) Pacheco Koch Consulting Engineers
6:30 a.m. - 4:15 p.m.
(1) Engine~xing Analyst
(1) City of Coppell Englncezin
CMT Operations Manager
LIMITATIONS: The test results pres~mtecl herein were prepared bszed upon the specific samples provided for test/nE. We assume no responsibility for variation in qual/ty
(composition, appearance, performance, etc.) or any other feature of similar subject matter provided by persons or conditions over which we have no control. Our lette~ and
reports are for the exclusive use of the clients to whom they are addressed and shall not be reproduced except in full without the written approval of Ron¢ Engineers, Ltd.
99DD Pa~e 1 of I
RONE ENGINEERS, Ltd.
REPORT OF
BELLED PIER INSPECTION
Client: Duke Realty Services, LP Report No.: 176540
Project No.: 037333
Project:' Freeport 10 Date of Service: 5/9/2003
500 Freeport Parkway Page 2 of 5
Driller: Liberty
Pier Identification PP-6 NN-6 MM-6 LL-6 KK-6
Pier Diameter (in) 24 24 24 24 24
Bell Diameter (in) 66 66 66 66 66
Required Minimum Depth (fi) 12.00 12.00 12.00 12.00 12.00
Depth of Pier Prior to Underreaming (ft) 12.70 12.30 12.80 12.90 12.90
Depth of Pier After Underreaming (ft) * 12.80 12.60 12.80 13.20 13.60
Condition of Bottom (wet / dry) Dry Dry Dry Dry Dry
Plumb Within Tolerance (yes / no) Yes Yes Yes Yes. Yes
Casing Diameter (in) / Casing Length (1~) NA NA NA NA NA
Number of Bars / Reinforcing Bar Size (#) 6/#6 6/g6 6/#6 6/#6 6/g6
Length of Reinforcing Steel (ft) 11.9 11.6 11.8 12.2 12.6
Time Drilling was Completed (am / pm) 8:23 AM 8:53 AM 9:37 AM 10:03 AM 10:28 AM
Time Concrete was Placed (am / pm) 12:10 PM 12:14 PM 12:20 PM 1:20 PM 1:28 PM
Depth of Pier From Top of Concrete (fi) t2.40 12.10 12.50 12.80 13.10
Elevation: Surface (ft)** 99.40 99.50 99.30 99.40 99.50
Elevation: Top of Pier (fi)** 99.00 99.00 99.00 99.00 99.00
Elevation: Bottom of Pier (ft)** 86.60 86.90 86.50 86.20 85.90
Bearing Stratum (description) Tan & Gray Sandy Clay
qote: See report # 176541 for Compressive Strength Test Specimens.
· Additional Penetration not requested unless noted.
Remarks: Section 4
· * - Elevation data not supplied to Rone Engineers. Noted surface, top of bearing stratum, and bottom
of pier elevation data calculated using specified top of pier elevations as shown on the project drawings
and measurement of actual top of concrete from existing surface elevation.
LIMITATIONS: The test results presentdd herein were prepemd based upon the specific samples provided for testing. We assume no responsibility for variation in
:lUallty (composition, apeeamnce, performance, etc.) or any other feature of similar subject metier provided by persons or conditions over which we have no control.
Dur letters and reports are for the exclusive use of the clients to whom they am addressed and shall not he reproduced except in full without the written approval of
Ro~e Engineers, Ltd.
RONE ENGINEERS, Ltd.
REPORT OF
BELLED PIER INSPECTION
Client: Duke Realty Services, 12 Report No.: 176540
Project No.: 037333
Project: Freeport 10 Date of Sen, ice: 5/9/2003
500 Freeport Parkway Page 3 of 5
Driller: Liberty
Pier Identification . JJ-6 PP-5 NN-5 MM-5 LL-5
Pier Diametvr (in) 24 24 24 24 24
Bell Diameter (in) 66 66 66 66 66
Required Minimum Depth (ft) 12.00 12.00 12.00 12.00 12.00
Depth of Pier Prior to Underreaming (fi) 12.80 12.60' 12.90 12.80 13.00
Depth of Pier After Underreaming (ft)* 13.00 13.00 12.90 12.80 13.10
Condition of Bottom (wet / dry) Dry Dry Dry Dry Dry
Plumb Within Tolerance (yes / no) Yes Yes Yes Yes Yes
Casing Diameter (in) / Casing Len~_h (fi) NA NA NA NA NA
Number of Bars / Reinforcing Bar Size (#) 6/#6 6/f~6 6/#6 6/#6 6/#6
Len~h of Reinforcing Steel (ft) 12.0 12.0 12.0 11.8 12.2
Time Drilling was Completed (am / pm) 10:52 AM 1:38 PM 11:57 AM 11:32 AM 1:08 PM
Time Concrete was Placed (am / pm) 1:32 PM 1:40 PM 1:47 PM 1:50 PM 1:54 PM
Depth of Pier From Top of Concrete (ft) 12.50 12.50 12.50 12.30 12.60
Elevation: Surface (ft)** 99.50 99.50 99.40 99.50 99.50
Elevation: Top of Pier (f0** 99.00 99.00 99.00 99.00 99.00
Elevation: Bottom of Pier (ftc)** 86.50 86.50 86.50 86.70 86.40
Bearing Stratum ~description) T~an & Gray Sand~ Clay
Note: See report # 176541 for Compressive Strength Test Specimens.
* Additional Penetration not requested unless noted.
Remarks: Section 4
**, Elevation data not supplied to Rone Engineers. Noted surface, top of bearing stratum, and bottom
of pier elevation data calculated using specified top of pier elevations as shown on the project drawings
and measurement of actual top of concrete from exisfmg surface elevation.
.IMITATIONS: The test results presented herein were prepared based upon the specific samples provided for testing. We assume no responsibility for vaflation in
luallty (composition, appea, rance, performance, etc.) or any other feature of similar subject m
RONE ENGINEERS, Ltd.
REPORT OF
BELLED PIER INSPECTION
Client: Duke Realty Services, LP Report No.: 176540
Project No.: 037333
Project: Freeport 10 Date of Service: 5/9/2003
500 Freeport Parkway Page 4 of 5
Driller: Liberty
Pier Identification KK-5 JJ-5 PP-4 NN-4 MM-4
Pier Diameter (in) 24 24 24 24 24
Bell Diameter (in) 66 66 66 66 66
Required Minimum Depth (fi) 12.00 12.00 12.00 12.00 12.00
Depth of Pier Prior to Underreamin$ (ft) 12.70 12.70 12.90 12.80 12.50
Depth of Pier After Underreamin~ (ii)* 12.70 12.80 12.90 12.90 12.50
Condition of Bottom (wet / dry) Dr~ Dr~ Dv Dr~ Dr~
Plumb Within Tolerance (yes / no) Yes Yes Yes Yes Yes
Casin~ Diameter (in) / Casint Length (fi) NA NA NA NA NA
Number of Bars / Reinforcin~ Bar Size (#) 6/g6 6/#6 6/#6 6/#6 6/g6
Len~h of Reinforcin~ Steel (fi) 11.7 11.9 12.0 12.0 11.5
Time Drillin~ was Completed (am / pm) 11:47 AM 11:18 AM 1:51 PM 2:01 PM 1:46 PM
Time Concrete was Placed (am / pm) 2:16 PM 2:19 PM 3:30 PM 2:57 PM 3:02 PM
Depth of Pier From Top of Concrete (ft) 12.20 12.30 12.50 12.40 12.10
Elevation: Surface (ft)** 99.50 99.50 99.40 99.50 99.40
Elevation: Top of Pier (ft)** 99.00 99.00 99.00 99.00 99.00
Elevation: Bottom of Pier (ft)** 86.80 86.70 86.50 86.60 86.90
Bearin~ Stratum (description) Tan & Gray Sandy Clay
Note: Sc¢ report # 176541 for Compressive Swength Test Specimens.
* Additional PeneU~ti°n not requested unless noted.
Remarks: Section 4
** - Elevation data not supplied to Rone Engineers. Noted surface, top of bearing stratum, and bottom
of pier elevation data calculated using specified top of pier elevations as shown on the project drawings
and measurement of actual top of concrete from existing surface elevation.
LIMITATIONS: The test results presented herein were prepared based upon the specific samples provided for testing. We assume no responsibility for vadation in
quality (composition, appearance, pa~formance, etc.) or any other feature of similar subject m
RONE ENGINEERS, Ltd.
REPORT OF
BELLED PIER INSPECTION
Client: Duke Realty Services, LP Report No.: 176540
Project No.: 037333
Project: Freeport 10 Date of Service: 5/9/2003
500 Freeport Parkway Page 5 of 5 -
Driller: Liberty
Pier Identification LL4 KK-4 JJ-4
Pier Diameter (in) 24 24 24
Bell Diameter (in) 66 66 66
Required Minimum Depth (it) 12.00 12.00 12.00
Depth of Pier Prior to Underreaming (it) 12.90 12.80 12.90
Depth of Pier After Underreaming (it)* 12.90 13.00 13.00
Condition of Bottom (wet / dry) Dry Dry Dry
Plumb Within Tolerance (yes / no) Yes Yes Yes
Casing Diameter (in)/Casing Length (it) NA NA NA
Number of Bars / Reinforcing Bar Size (#) 6/#6 6/g6 6/g6
Length of Reinforcing Steel (it) 12.0 12.0 12.0
Time Drilling was Completed (am / pm) 1:45 PM 1:14 PM 12:00 PM
Time Concrete was Placed (am / pm) 2:51 PM 2:47 PM 2;24 PM
Depth of Pier From Top of Concrete (f~) 12.40 12.50 12.50
Elevation: Surface (it)** 99.50 99.50 99.50
Elevation: Top of Pier (it)** 99.00 99.00 99.00
Elevation: Bottom of Pier (it)** 86.60 86.50 86.50
Bearing Stratum (description) Tan & Gray Sandy Clay
Note: See report # 176541 for Compressive Stxength Test Specimens.
* Additional Penetration not requested unless noted.
Remarks: Section 4
** - Elevation data not supplied to Rone Engineers. Noted surface, top of bearing stratum, and bottom
of pier elevation data calculated using specified top of pier elevations as shown on the project drawings
and measurement of actual top of concrete from existing surface elevation.
LIMITATIONS: The test results Presented herein were prepared based upon lhe specific samples provided for testing. We assume no responsibility for variation in
quality (composition, appearance, performance, atc.) or any other feature of similar subject m
8908 Ambassador Row, Dallas, TX 75247
2696 Gravel Drive, Fort Worth, TX 76118
6300 Rothway, Ste. 150, Houston, TX 77040
Corporate Phone: (214) 630=9745
REPORT OF DRH. LED PIER INSPECTION
Client:
Duke Realty Sen, ices, LP
Attn: Mr. JeffLangston
5495 Belt Line Road, Suite 360
Dallas TX 75254
Project: Freeport 10
500 Freeport Parkway
Coppell, TX
Services: Drilled Pier Inspection
Report No.: 176371
Project No.: 037333
Date of Service: 05/07/2003
Report Date: 05/14/2003
Report of Inspection
On this date, a Rone Engineers, Ltd. reFresentative(s) was on site to perform
Drilled Pier Inspection. The results are attached.
Technician Time:
Page 1 of 4
Technician: Rick Smith
Report Distribution:
(1) Duke Realty Services, LP
(1) Duke R~alty Services, LP
(1) C_ity of Ceppell Building Dept.
(1) Panheeo Koch Consulting Engineers
6:30 a.m. - 4:45 p.m.
(1) Engineering Analyst
(1) City o£Ceppen EnNneering Dept.
K. Scott Watson
CMT Operations Manager
LIMITATIONS: The test results presented heroin were prepared based upon the specific samples provided for testing. We assume no responsibility for variation in quality
(composition, appearance, performance, etc.) or any other feature of similar subject matter provided by persons or conditions over which w~ have no control. Our letters and
reports are for the exclusive use oftha clients to whom they are addressed and shall not be re'produced except in full without the written approval of Rone Engineers, Ltd.
99DD Page 1 of 1
RONE ENGINEERS, Ltd.
REPORT OF
BELLED PIER INSPECTION
Client: Duke Realty Sendces, LP Report No.: 176371
Project No.: 037333
ProjeCt: Freeport 10 Date of Service: 5/7/2003
500 Freeport Parkway Page 2 of 4
Driller: Liberty
Pier Identification JJ-13 JJ-12 KK-12 LL-12 MM-12
Pier Diameter (in) 24 24 24 24 24
Bell Diameter (in) 66 66 66 66 66
Required Minimum Depth (It) 12.00 12.00 12.00 12.00 12.00
Depth of Pier Prior to Underreamin~ (It) 12.80 12.80 12.70 12.80 12.90
Depth of Pier After Underreaminl~ (It)* 13.20 12.80 12.90 13.20 12.90
Condition of Bottom (wet / dry) Dry Dry Dry Dry Dry
Plumb Within Tolerance (yes / no) : Yes Yes Yes Yes Yes
Casin~ Diameter (in) / Casin~ Length (It) NA NA NA NA NA
iNumber of Bars / Reinforeial~ Bar Size (#) 6/#6 6/#6 6/#6 6/#6 6/g6
Len~h of Reinforcint~ Steel (It) 12.2 11.8 12.0 12.2 12.0
Time Drillin~ was Completed (a~ / pm) 8:55 AM 9:25 AM 9:57 AM 10:26 AM 11:29 AM
Time Concrete was Placed (am / pm) 11:56 AM 12:13 PM 12:18 PM 1:06 PM 1:13 PM
Depth of Pier From Top of Concrete (It) 12.80 12.30 12.40 12.70 12.40
Elevation: Surface (fi)** 99.40 99.50 99.50 99.50 99.50
Elevation: Top of Pier (fi)** 99.00 99.00 99.00 99.00 99.00
Elevation: Bottom of Pier (It)** 86.20 86.70 86.60 ' 86.30 86.60
Bearin~ Stratum (descril?tion) Tan & Gray Sandy Clay
Not~: See report #176372 for Compressive SWength Tcst Spccimcas.
* Add/fional Penetration not requested unless noted. .
Remarks: ** - Elevation data not supplied to Ronc Engineers. Noted surface, top of bearing stratum, and bottom
of pier elevation data calculated using specified top of pier elevations as shown on thc project drawings
and measurement of actual top of concrete from existing surface elevation.
LIMITATIONS: The test results presented herein were prepared based upon the specific sempla~ provided for testing. We assume no responsibility for variation In
quality (composition, appearance, parforrnanco, etc.) or any other feature of similar subject matter provided by persons or conditions over which we have no control.
Our letters and reports are for the exclusive use of the clients to whom they are addressed end shall not be reproduced excep~ In full without the written approval of
Rone Engineers, Ltd.
RONE ENGINEERS, Ltd.
REPORT OF
BELLED PIER INSPECTION
Client: Duke Realty Services, LP Report N°.: 176371
Project No.: 037333
Project: Freeport 10 Date of Service: 5/7/2003
500 Freeport Parkway Page 3 of 4
Driller: Liberty
Pier Identification NN-12 PP-12 GG-14 PP-11 NN-11
Pier Diameter (in) 24 24 24 24 24
Bell Diameter (in). 66 66 66 66 66
:Required Minimum Depth (ft) 12.00 12.00 12.00 12.00 12.00
Depth of Pier Prior to Underreaming (ft) 13.10 13.00 12.70 12.60 12.90
Depth of Pier After Underreaming (fi)* 13.60 13.30 13.00 13.00 13.20
Condition of Bottom (wet / dry) D~ Dry D~ Dry Dry
Plumb Within Tolerance (yes / no) Yes Yes Yes Yes Yes
Casing Diameter (in) / Casing Length (ft) NA NA NA NA NA
Number of Bars / Reinforcing Bar Size (#) 6/g6 6/#6 6/#6 6/#6 6/g6
Length of Reinforcing Steel (ft) 12.6 12.4 12.0 12.0 12.3
Time Drilling was Completed (am / pm) 1 t :08 AM 11:45 AM 10:10 AM I 1:57 AM 12:53 PM
Time Concrete was Placed (am / pm) 3:15 PM 3:23 PM ll:50AM 3:28 PM 3:33 PM
Depth of Pier From Top of Concrete (ft) 13.10 12.80 12.50 12.60 12.70
Elevation: Surface (ft)** 99.50 99.50 99.50 99.40 99.50
Elevation: Top of Pier (ft)** 99.00 99.00 99.00 99.00 99.00
Elevation: Bottom of Pier (ft)** 85.90 86.20 86.50 86.40 86.30
Bearing Stratum (description) Tan & Gray Sandy Clay
Note: See report #176372 for Compressive Strength Test Specimens.
* Additional Penetration not requested unless noted.
Remarks: ** - Elevation data not supplied to Rone Engineers. Noted surface, top of bearing stratum, and bottom
of pier elevation data calculated using specified top of pier elevations as shown on the project drawings
and measurement of actual top of concrete from existing surface elevation.
LIMITATIONS: The test results presented herein were prepared based upon the specific samples provided for testing. We assume no responsibility for variation In
quality (composiflo~, appearance, pedormance, etc.) or any other feature of similar subject m
RONE ENGINEERS, Ltd.
REPORT OF
BELLED PIER INSPECTION
Client: Duke Realty Services, LP Report No.: 176371
Project No.: 037333
Project: Freeport l0 Date of Service: 5/7/2003
500 Freeport Parkway Page 4 of 4
Driller: Liberty
Pier Identification MM-Il LL-11 KK-11 $J-ll JJ-lO
~ier Diameter (in) 24 24 24 24 24
Bell Diameter (in) 66 66 66 66 66
Required Minimum Depth (ft) 12.00 12.00 12.00 12.00 12.00
Depth of Pier Prior to Underreaming (ft) 12.70 12.40 12.70 12.60 12.80
Depth of Pier After Underreaming (ft)* 13.40 13.30 13.00 12.70 13.30
Condition of Bottom (wet / dry) Dry Dry Dry Dry Dry
Plumb Within Tolerance (yes / no) Yes Yes Yes Yes Yes
Casin~ Diameter (in) / Casinl~ Len~h (ft) NA NA NA NA NA
Number of Bars / Reinforcin~ Bar Size (#) 6/#6 6/#6 6/#6 6/#6 6/g6
Length of Reinforcin~ Steel (ft) 12.5 12.4 12.0 11.8 12.3
Time Drilling was Completed (am / pm) I:41PM ! l:18PM 12:56PM 11:51AM 2:38PM
Time Concrete was Placed (am / pm) 3:37 PM 3:41 PM 3:45 PM 3:49 PM 3:55 PM
Depth of Pier From Top of Concrete (fi) 13.00 12.80 12.50 12.30 12.90
Elevation: Surface (fi)** 99.40 99.50 99.50 99.40 99.40
Elevation: Top of Pier (fi)** 99.00 99.00 99.00 99.00 99.00
Elevation: Bottom of Pier (ft)** 86.00 86.20 · 86.50 86.70 86.10
Bearing Stratum (description) Tan & Gray Sandy Clay
Note: See report #176372 for Compressive Strength Test Specimens.
* Additional Penetration not requested unless noted. .
Remarks: ** - Elevation data not supplied to Rone Engineers. Noted surface, top of bearing stratum, and bottom
of pier elevation data calculated using specified top of pier elevations as shown on the project drawings
and measurement of actual top of concrete from existing surface elevation.
LIMITATIONS: The test results presented herein were prepared based upon the specific samples provided for testing. We assume no responsibility for variation in
:luallty (composition, appearance, performance, etc.) or any other feature of similar subject m
8908 Ambassador Row, Dallas, TX 75247
2696 Gravel Drive, Fort Worth, TX 76118
6300 Rothway, Ste. 1S0, Houston, TX 77040
Corporate Phone: (214) 630=9745
REPORT OF DRILLED PIER INSPECTION
Client:
Duke Realty Sexvices, LP
Attn: Mr. J~ff Langston
5495 Bolt Line Road, Suite 360
Dallas TX 7~254
Project: Freeport 10
500 Freeport Parkway
Coppell, TX
Services: Drilled Pier Inspection
Report No.: 176275.
Project No.: 037333
Date of Service: 05/06/2003
Report Date: 05/14/2003
Report of Inspection
On this date, a Rone Engineers, Ltd. representative(s) was on site to perform
Drilled Pier Inspection. The results are attached.
Technician Time:
Page 1 of 4
Technician: Rick Sl~th
Report Distribution:
(I) Duke Realty Servlcc% LP
(1) Duke Remlty S~*vices, LP
(1) City of Coppell Building Dept.
(1) Pacheeo Koch Consulting Engineers
6:30 a.m. - 4:15 p.m.
(1) Engineering Analyst
(1) City of Coppell Engineering Dept.
K. Scott Watson
CMT Operations Manager
LIMITATIONS: Thc test ~suim pr'-,~nted herein were prepared based upon the specific samples provided for testing We assume no responsibility for variation in quality
(composition, appearance, performance, ~c.) or any oth~ f~atur~ of similar subject matter pmvidad by persons or conditions ova which we have no controL Our letters and
reports are for the exclusive use of the clients to whom they are addressed and shall not be reproduced except in full without the writtan approval of Rone Engineers, Ltd.
99DD Paoe 1 of 1
RoNE ENGINEERS, Ltd.
REPORT OF
BELLED PIER INSPECTION
Client: Duke Realty Services, LP Report No~: 176275
Project No.: 037333
Project: Freeport 10 Date of Sera. ice: 5/6/2003
500 Freeport Parkway Page 2 of 4
Driller: Liberty
Pier Identification JJ-14 KK-14 LL-14 MM-14 NN-14
:Pier Diameter (in) 24 24 24 24 24
Bell Diameter (in) 66 ' 66 66 66 66
Required Minimum Depth (fi) 12.00 12.00 12.00 12.00 12.00
Depth of Pier Prior to Underreaming (ft) 12.00 12.70 13.00 12.50 12.50
Depth of Pier After Underreaming (i~)* 12.20 12.70 13.50 13.00 13.00
Condition of Bottom (wet / dry) D~ Dry D~ Dry D~
Plumb Within Tolerance (yes / no) Yes Yes Yes Yes Yes
Casing Diameter (in) / Casing Len~h (fi) NA NA NA NA NA
Number of Bars / Reinforcing Bar Size (#) 6/#6 6/#6 6/#6 6/#6 6/~6
Length of Reinforcing Steel (fi) 11.2 11.8 12.5 12.0 12.0
Time Drilling was Completed (am /pm) 9:30 AM 9:47 AM 10:22 AM 10:51 AM 11:19 AM
Time Concrete was Placed (am / pm) 1:05 PM 1:09 PM 1:14 PM 1:40 PM 1:46 PM
Depth of Pier From Top of. Concrete (ft) 11.70 12.20 13.00 12.50 12.60
Elevation: Surface (fi)** 99.50 99.50 99:50 99.50 99.40
Elevation: Top of Pier (fi)** 99.00 99.00 99.00 99.00 99.00
Elevation: Bottom of Pier (i~)** 87.30 86.80 86.00 86.50 86.40
Bearing Stratum (description) Tan & Gray Sandy Clay
Note: See report #176276 for Compressive Strength Test Specimens.
* Additional Penetration not requested unless noted.
Remarks: Section 7
** - Elevation data not supplied to Rone Engineers. Noted surface, top of bearing stratum, and bottom of
pier elevation data calculated using specified top of pier elevations as shown on the project drawings and
measurement of actual top of concrete firom existing surface elevation.
LIMITATIONS: The test results presented herein were prepared based upon the specific samples provided for testing. We assume no msponsibil~ for variation in
quality (composition, appearance, performance, etc.) or any other feature of similar subject matter provided by parsons or conditions over which we have no control.
~)ur k~ters and reports am for the exclusive use or the cJlents to whom they are addressed and shell not be reproduced except in full without the written approval or
Pone Engineers, Ltd.
RONE ENGINEERS, Ltd.
REPORT OF
BELLED PIER INSPECTION
Client: Duke Realty Services, LP Report No.: 176275
Project No.: 037333
Project: Freeport 10 Date of Service: 5/6/2003
500 Freeport Parkway Page 3 of 4
Driller: Liberty
Pier Identification PP-14 PP-I5 PP-13 NN-13 MM-13
Pier Diameter (in) 24 24 24 24 24
Bell Diameter (in) 66 66 66 66 66
Required Minimum Depth (ii) 12.00 12.00 12.00 12.00 12.00
Depth of Pier Prior to Underreaming (ft) 12.80 12.50 12.70 12.70 12.60
Depth of Pier After Underreaming (ii)* 13.00 13.10 12.80 12.80 13.00
Condition of Bottom (wet / dry) Dry Dry Dry Dry Dry
Plumb Within Tolerance (yes / no) Yes Yes Yes Yes Yes
Casin$ Diameter (in) / Casin~ Len~h (ii) NA NA NA NA NA
Number of Bars / Reinforcing: Bar Siz~ (#) 6/#6 6/#6 6/#6 6/~a5 6/~5
L~n~h of Reinforcin~ Steel (ii) 12.0 12.2 11.9 11.9 12.0
Time Drillin~ was Completed (am / pm) 1:23 PM 1:49 PM 12:55 PM 11:30 AM 10:55 AM
Time Concrete was Placed (am / pm) 1:50 PM 2:15 PM 2:19 PM 2:34 PM 3:05 PM
Depth of Pier From Top of Concrete (ii) 12.50 12.60 12.30 12.30 12.50
Elevation: Surface frO** 99.50 99.50 99.50 99.50 99.50
Eleyation: Top o£Pier (ii)** 99.00 99.00 99.00 99.00 99.00
Elevation: Bottom of Pier (fi)** 86.50 86.40 86.70 86.70 86.50
Bearing Stratum (description) Tan & Gray Sandy Clay
Note: See report #176276 for Compressive Strength Test Specimens.
*Additional Peuetr~fion not requested unless noted.
Remarks: ** - Elevation data not supplied to Rone Engineers. Noted surface, top of bearing stratum, and bottom of
pier elevation data calculated using specified top of pier elevations as shown on the project drawings and
measurement of actual top of concrete from existing surface elevation.
LIMITATIONS: The test results pmsanted herein were prepared based upon the specific samples provided for testing. We assume no responsibility for variation in
:luality (composition, appearance, performance, etc.) or any other feature of similar subject m
RONE ENGINEERS, Ltd.
REPORT OF
BELLED PIER INSPECTION
Client: Duke Realty Services, LP Report No.: 176275
Project No.: 037333
Project: Freeport 10 Date of Service: 5/6/2003
500 Freeport Parkway Page 4 of 4
Driller: Liberty
Pier Identification LL- 13 KK-13
Pier Diameter (in) 24 24
Bell Diameter (in) 66 66
Requirext Minimum Depth (ii) 12.00 12.00
Depth of Pier Prior to Underreaming (ii) 12.90 12.60
Depth of Pier After Underreaming (fi)* 13.10 12.80
Condition of Bottom (wet / dD,) Dr7 Dr7
Plumb Within Tolerance (),es / no) Yes Yes
Casing Diameter (in) / Casing Len~h (ii) NA NA
Number of Bars / Reinforcing Bar Size (#) 6/#6 6/#6
Len~h of Reinforcing Steel (ft) 12.2 12.0
Time Drilling was Completed (am / pm) 10:31 AM 2:44 PM
Time Concrete was Placed (am / pm) 3:32 PM 3:40 PM
Depth of Pier From Top of Concrete (ii) 12.70 12.30
Elevation: Surface (ii)** 99.40 99.50
Elevation: Top of Pier (ft)** 99.00 99.00
Elevation: Bottom of Pier (ii)** 86.30 86.70
Bearinl~ Stratum (description) Tan & Gray Sandy Clay
Not~: See report #176276 for Compressive Strength Test Specimeas.
* Additional Pcaetntion not r~qu~sted unless noted.
Remarks: **-- Elevation data not supplied to Rone Engineers. Noted surface, top of bearing stratum, and bottom of
pier elevation data calculated using specified top of pier elevations as shown on the project drawings and
measurement of actual top of concrete from existing surface elevation.
.IMITATIONS: The test results presented herein were prepared based upon the specific samples provided for tesUng. We assume no responsibility for variation In
quality (composition, appearance, pedon'nance, etc.) or any other feature of similar subject m
RoneEng, nle
890~ Ambassador Row, Dallas, TX 7S247
2696 Gravel DHve, Fort Worth, TX 76118
6300 Rothway, Ste. 150, Houston, TX 77040
Corporate Phone: (214) 630=9745
REPORT OF DRILLED PIER INSPECTION
Client:
Duke Realty Services, LP
Aaa: Mr. Jeff Langston
5495 Belt Line Road, Suite 360
Dallas TX 75254
Project: Freeport 10
500 Freeport Parkway
Coppell, TX
Services: Drilled Pier Inspection
Report No.:
Project No.:
Date of Servtee:
Report Date:
176456
037333
05/08/2O03
05/14/2003
Report of Inspection
On this date, a Rone Engineers, Ltd. representative(s) was on site to perform
Drilled Pier Inspection. The results are attached.
Technician Time:
Page 1 of 6
Technician: Rick Smith
Report Distribution:
(1) Duke Realty Sem4eea, LP
(1) Duke RImlty Se~deas, LP
(l) City of Coppell BuJ. Idlng Dept.
(l) Pacheen Koch Conmdfing Eng/neers
6:30 a.m. - 5:00 p.m.
(1) Engineering Analyst
(1) City of Coppell Engineering Dept,
K. Sc
Watson
CMT Operations Manager
LIMITATIONS: The test r~suha presented herein were prelnm~ based upon the specific samples pwvlded for testing. We assume no responsibility for variation in quality
(composition, appearance, performance, etc.) or any other feature of simiinr subject matter provided by persons or conditions over which we have no control. Our letters and
reports are fi)r the exclusive use of the clients to whom they are addressed and shall not ha reproduced except in full without the written appwval of Rone Engineers, Ltd.
99DD PaRe l of ]
RONE ENGINEERS, Ltd.
REPORT OF
BELLED PIER INSPECTION
Client: Duke Realty Setwices, LP Report No.: 176456
Project No.: 037333
Project: Freeport 10 Date of Service: 5/8/2003
500 Freeport Parkway Page 2 of 6
Driller: Liberty
Pier Identification ICK-10 LL-10 MM-10 NN-10 PP-10
Pier Diameter (in) 24 24 24 24 24
Bell Diameter (in) 66 66 66 66 66
Required Minimum Depth (fi) 12.00 12.00 12.00 12.00 12.00
Depth of Pier Prior to Underreamint (fi) 12.50 12.90 12.70 12.80 12.50
Depth of Pier After Underreaminfg (it)* 13.20 13.60 12.90 12.80 12.70
Condition of Bottom (wet / dry) Dry Dry Dry Dry Dry
Plumb Within Tolerance (yes / no) Yes Yes Yes Yes Yes
Casini Diameter (in) / Casint Length (it) NA NA NA NA NA
Number of Bars / Reinforcint Bar Size (#) 6/#6 6/#6 6/#6 6/#6 6///6
Len~h of Reinforcint Steel (it) 12.2 12.7 12.0 11.9 11.8
l~ime Drillint was Completed (am / pm) 8:58 AM 9:20 AM 9:48 AM 10:20 AM 10:07 AM
Time Concrete was Placed (am / pm) 12:46 PM 12:52 PM 1:00 PM 1:05 PM 2:38 PM
Depth of Pier From Top of Concrete (it) 12.70 13.20 12.40 12.30 12.20
Elevation: Surface (fi)** 99.50 99.40 99.50 99.50 99.50
Elevation: Top of Pier (fi)** 99.00 99.00 99.00 99.00 99.00
Elevation: Bottom of Pier (it)** 86.30 85.80 86.60 86.70 86.80
Bearin~ Stratum (description) Tan & Gray Sandy Clay
Note: See report # 176457 for Compressive Strength Test Specimens. l-
* Additional Penetration not requested unless noted.
Remarks: Section 7
** - Elevation data not supplied to Roue Engineers. Noted surface, top of bearing stratum, and bottom
of pier elevation data calculated using specified top of Pier elevations as shown on the project drawings
and measurement of actual top of concrete from existing surface elevation.
LIMITATIONS: The test results pmsanted herein were prepared based upon the spoc~c samples provided for testing. We assume no responsibility for vaflatlen In
quality (composition, appearance, performance, etc.) or any other feature of similar subject matter provided by pe~ons or conditions over which we have no control.
Our letters and reports are for the exduslve use of the clients to whom they are addressed and shall not be reproduced except in full without the written approval of
Rone Engineers, Ltd.
RONE ENGINEERS, Ltd.
REPORT OF
BELLED PIER INSPECTION
Client: Duke Realty Services, LP Report No.: 176456
Project No.: 037333
Project: Freeport 10 Date of Service: 5/8/2003
500 Freeport Parkway Page 3 of 6
Driller: Liberty
Pier Identification PP-9 NN-9 MM-9 LL-9 KK-9
Pier Diameter (in) 24 24 24 24 24
Bell Diameter (in) 66 66 66 66 66
Required Minimum Depth (It) 12.00 12.00 12.00 12.00 12.00
Depth of Pier Prior to Underreaming (It) 12.40 12.80 13.00 12.60 12.60
Depth of Pier After Underreaming (it)* 12.70 12.90 13.00 12.60 12.80
Condition of Bottom (wet / dry) Dry Dry Dry Dry Dry
Plumb Within Tolerance (yes / no) Yes Yes Yes Yes Yes
Casing Diameter (in) / Casing Lensth (it) NA NA NA NA NA
Number of Bars/Reinforcing Bar Size (#) 6/g6 6/86 6/#6 ' 6/g6 6/#6
Len~h of Reinforcing Steel (it) 11.7 12.0 12.0 11.6 12.0
Time Drilling was Completed (am / pm) 10:31 AM 10:56 AM 10:54 AM 11:21 AM 11:42 AM
Time Concrete was Placed (am / pm) 2:42 PM 2:47 PM 2:51 PM 2:55 PM 3:02 PM
,Depth of Pier From ToP of Concrete (It) 12.20 12.50 12.50 12.10 12.40
Elevation: Surface (It)** 99.50 99.40 99.50 99.50 99.40
Elevation: Top of Pier (fi) ** 99.00 99.00 99.00 99.00 99.00
Elevation: Bottom of Pier (ft)** 86.80 86.50 86.50 86.90 86.60 .
Bearing Stratum (description) Tan & Gray Sandy Clay
Note: See report # 176457 for Compressive Strength Test Specimens.
* Additional Penetration not requested unless noted.
Remarks: Section 4
** - Elevation data not supplied to Rone E~neers. Noted surface, top of bearing stratum, and bottom
of pier elevation data calculated using specified top of pier elevations as Shown on the project drawings
and measurement of actual top of concrete fi.om existing surface elevation.
LIMITATIONS: The test results presented herein were prepared based upon the specific samples provided for testing. We assume no responsibility for variation in
quality (composition, appearance, performance, etc.) or any other feature of similar subject m
RONE ENGINEERS, Ltd.
REPORT OF
BELLED PIER INSPECTION
Client: Duke Realty Services, LP Report No.: 176456
Project No.: 037333
Project: Freeport 10 Date of Service: 5/8/2003
500 Freeport Parkway Page 4 of 6
Driller: Liberty
'Pier Identification JJ-9 PP-8 NN-8 MM-8 LL-8
Pier Diameter (in) 24 24 24 24 24
Bell Diameter (in) 66 66 66 66 66
Required Minimum Depth (f0 12.00 12.00 12.00 12.00 12.00
Depth of Pier Prior to Underreamint~ (ft) 12.90 12.70 13.00 12.50 12.90
Depth of Pier After Underreamin~ (ft)* 13.00 12.80 13.40 12.60 13.30
Condition of Bottom (wet / dry) Dry Dry Dry Dry Dry
Plumb Within Tolerance (yes / no) Yes Yes Yes Yes Yes
Casin~ Diameter (in) / Casin~ Length (ft) NA NA NA NA NA
Number of Bars / Reinforcin~ Bar Size (#) 6/#6 6/#6 6/#6 6/#6 6/#6
Length of Reinforeinlg Steel (ft) 12.0 11.8 12.5 11.6 12.4
Time Ddllinl~ was Completed (am / pm) 11:24 AM 12:00 PM 1:14 PM 1:05 PM 1:41 PM
Time Concrete was Placed (am / pm) 3:07 PM 3:42 PM 3:37 PM 3:33 PM 3:29 PM
Depth of Pier From Top of Concrete (ft) 12.50 12.30 13.00 12.10 12.80
Elevation: Surface (ft)** 99.50 99.50 99.40 · 99.50 99.50
Elevation: Top of Pier (ft)** 99.00 99.00 99.00 99.00 99.00
Elevation: Bottom of Pier (ft)** 86.50 86.70 86.00 86.90 86.20
Bearinl~ Stratum (description) Tan & Gray Sandy Clay
Note: See report # 176457 for Compressive Strength Test Specimens.
· Additional Penetration not requested unless noted.
Remarks: Section 4
· * - Elevation data not supplied to Rone Engineers. Noted surface, top of bearing stratum, and bottom
of pier elevation data calculated using specified top of pier elevations as shown on the project drawings
and measurement of actual top of concrete from existing surface elevation.
LIMITATIONS: The test msult~ presented herein w~e prepared based upon the specific samples provided f~' testing. We assume no responsibility for variation in
quality (composition, appearance, performance, etc.) or any other feature of similar subject m
RONE ENGINEERS, Ltd.
REPORT OF
BELLED PIER INSPECTION
Client: Duke Realty Services, LP Report No.: 176456
Project No.: 037333
Project: Freeport 10 Date of Service: 5/8/2003
500 Freeport Parkway Page 5 of 6
Driller: Liberty
Pier Identification KK-8 JJ-8 PP-7 NN-7 MM-7
Pier Diameter (in) 24 24 24 24 24
Bell Diameter (in) 66 66 66 66 66
Required Minimum Depth (fi) 12.00 12.00 12.00 12.00 12.00
Depth of Pier Prior to Underreaming (fi) 12.80 13.00 13.00 12.70 12.80
Depth of Pier After Underreaming (fi)* 13.00 13.30 13.00 12190 13.00
Condition of Bottom (wet / dry) Dr~ I~ Dry Dry Dry
Plumb Within Tolerance ()res / no) Yes Yes Yes Yes Yes
Casing Diameter (in) / Casing Len~h (fi) NA NA NA NA NA
Number of Bars / Reinforcing Bar Size (#) 6/#6 6/g6 6/#6 6/#6 6/#6
Lenff~h of Reinforcing Steel (fi) 12,0 12.4 12.0 12.0 12.0
Time Drilling was Completed (am / pm) 1:33 PM 1:57 PM 2:10 PM 2:40 PM 2:24 PM
Time Concrete was Placed (am / pm) 3:12 PM 3:08 PM 3:48 PM 3:52 PM 3:56 PM
Depth of Pier From Top of Concrete (fi) 12.60 12.80 12.60 12.40 12.50
Elevation: Surface (it)** 99.40 99.50 99.40 99.50 99.50
Elevation: Top of Pier (fi)** 99.00 99.00 99.00 99.00 99.00
Elevation: Bottom of Pier (fi)** 86.40 86.20 86.40 86.60 86.50
Bearing Stratum (description) Tan & Gray Sandy Clay
Note: See report # 176457 for Compressive Strength Test Specimens.
* Additional Penetration not requested unless noted.
Remarks: Section 4
** - Elevation data not supplied to Rone Engineers. Noted surface, top of bearing stratum, and bottom
of pier elevation data calculated using specified top of pier elevations as shown on the project drawings
and measurement of actual top of concrete from existing surface elevation.
LIMITATIONS: The test results presented herein were prepared based upon the specific samples provided for testing. We assume no responsibility f~' vaflaflon in
quality (composition, appearance, parforrnenco, etc.) or any other feature of similar subject m
RONE ENGINEERS, Ltd.
REPORT OF
BELLED PIER INSPECTION
Client: Duke Realty Services, LP Report No.: 176456
Project No.: 037333
Project: Freeport 10 Date of Service: 5/8/2003
500 Freeport Parkway Page 6 of 6
Driller: Liberty
,Pier Identification LL-7 KK-7 J J-7
Pier Diameter (in) 24 24 24
Bell Diameter (in) 66 66 66
Required Minimum Depth (ft) 12.00 12.00 12-00
Depth of Pier Prior to Underreaming (ft) 13.00 13.10 13.10
Depth of Pier After Underreaming (fi)* 13.00 13.20 13.30
Condition of Bottom (wet / dry) Dry Dry Dry
Plumb Within Tolerance ()'es / no) Yes Yes Yes
Casin~ Diameter (in) / Casing Length (i~) NA NA NA
Number of Bars / Reinforcing Bar Size (#) 6/#6 6/g6 6/g6
Len~h of Reinforcing Steel (ft) 12.0 12.2. 12.4
Time Drilling was Completed (am / pm) 2:06 PM 2:44 PM 3:14 PM
Time Concrete was Placed (am / pm) 4:02 PM 4:08 PM 4:16 PM
Depth of Pier From Top of Concrete (ft) 12.60 12.70 12.80
Elevation: Surface (ft)** 99.40 99.50 99.50
Elevation: Top of Pier (ft)** 99.00 99.00 99.00
Elevation: Bottom of Pier (it)** 86.40 86.30 86.20
Bearing Stratum (description) Tan & Gray Sandy Clay
Note: See report # 176457 for Compressive Strength Test Specimens.
* Additional Pene~ation not requested unless noted.
Remarks: Section 4
** - Elevation data not supplied to Rone Engineers. Noted surface, top of bearing stratum, and bottom
of pier elevation data calculated using specified top of pier elevations as shown on the project drawings
and measurement of actual top of concrete from existing surface elevation.
LIMITATIONS: The test results presented herein were prepared based upon the spaoiflc samples provided for testing. We assume no responsibility for variation In
quality (composition, appesrence, performance, etc.) or any other feature of similar subject m
8908 Ambassndor Row, Dallas, TX 75247
2696 Gravel Drive, Fort Worth, TX 76118
6300 Rothwoy, Ste. 150, Houston, TX 77040
Corporate Phone: (214) 630=9745
REPORT OF REINFORCING STEEL INSPECTION
Client:
Duke Realty Services, LP
Aaa: Mr. JeffLangston
5495 Belt Line Road, Suite 360
Dallas TX 75254
Project: Freeport 10
500 Freeport Parkway
Coppell, TX
Services: Reinforcing Steel Inspection
Report No.: 176502
Project No.: 037333
Date of Service: 05/08/2003
Report Date: 05/14/2003
Report of Inspection
On this date, a Rone Engineers, Ltd. representative(s) was on site to perform
Reinforcing Steel Inspection. The results are attached.
Technician Time:
Page i of 2
Technician: Lanny Gist
Report Distribution:
(1) Duke Realty Services, LP
(1) Duke Realty Services, LP
(1) City of Coppell Building Dept.
(I) Pscheco Koch Consulting Engine.s
2:30 p.m. - 4:00 p.m.
(1) Engineering Analyst
(I) City of Cuppell Engineering Dept.
Scott Watson
CMT Operations Manager
LIMITATIONS: The test results presented he.in were prepared based upon the specific samples provided for testing. We asstone no responsibility for variation in quality
(composition, appearance, performance, etc.) or any other feature of similar subject matter provided by persons or conditions over which we have no control. Our l~ae~s and
repoxts are for the exclusive use of the cheats to whom they are addressed and shall not be reproduced except in full without the written approval of Rone Engineers, Ltd.
99DD Page I of 1
RoneEn gineers
8908 Ambassador Row
Dallas, Texas 7S247
(214) 630-9745
121 North Rayner
Fort Worth, Texas 76111
(817) 831.-6211
Client:
Project:
Report of
Reinforcing Steel Inspection
Report No.:
Project No.:
Date of Service:
Page
'~ of ~
Locations and Items Inspected:
Item lnspe~ed: Coaformlu~ Non Item l~q~qed: Confomlug Non Item h]q~:ted: ~ N~
Co~lng Confombg Coub~ug
Pl~ ~ B~ L~ ~ ~o1~ ~ ~
A~ ~ ~ s~ n~ ~ s~ ~
B~ S~ ~ ~ B~ Pl~t ~ ~fi~p S~ ~d ~ ~
~ CI~ ~ ~1 ~ ~ P~ ~ ~ Spli~ ~
F~ C~ ~ p~ ~ ~ ~ ~h~ Spli~
Inspector's Signature:
Time: to
Client/Contractor Signature: Client/Contractor Copied with Results: Yes / No
8908 Ambassador Row, Dallas, TX 75247
2696 Gravel Drive, Fort Worth, TX 76118
6300 Rothway, Ste. 150, Houston, TX 77040
Corporate Phone: (214) 630-9745
REPORT OF REINFORCING STEEL INSPECTION
Client:
Duke Realty Services, LP
Arm: Mr. Jeffl. angston
5495 Belt Line Road, Suite 360
Dallas TX 75254
Project: Freepor~ 10
500 Freeport Parkway
Coppeil, TX
Services: Reinforcing Steel Inspection
Report No.: 176439
Project No.: 037333
Date of Service: 05/07/2003
Report Date: 05/14/2003
Report of Inspection
On this date, a Rone Engineers, Ltd. representative(s) was on site to perform
Reinforcing Steel Inspection. The results are attached.
Technician Time:
Page 1 of 3
Technician: Lanny Gist
Report Distribution:
(1) Duke Realty Services, LP
(1) Duke Realty Sen, ices, LP
(1) City of Coppell Building Dept.
(I) Pacheco Koch Consulting Engineers
4:00 p.m. - 5:00 p.m.
(I) Engineering Analyst
(1) City of Coppell Engineering Dopt.
CMT Operations Manager
LIMITATIONS: The test results prasanted here/n were prepared based upon the specific samples provided for te~ting. We assume no responsibility for variation in quality
(composition, appearance, performance, etc.) or any other feature of similar subject maim' provided by persons or conditions over which we have no conlrol. Our letiem and
reports are for the exclusive use of the clients to whom they are ~ and shall not be reproduced except in full without the written approval ofRone Enginecl~, Ltd;
99DD Page 1 of 1
R=ne, Enugineers
8908 Ambassador Row
Dallas, Texas ?524?
(214) 630-9745
121 North Rayner
Fort Worth, Texas 76111
(817) a314211
Report of
Reinforcing Steel Inspection
Client: r-~ o V-. & Report No.:
Project No.:
Project: ~ceeDor¥ /o
Date of Service:
Page
175q3 ?
LoeafionsandItemsInspected: '"T'~e ~e~ /_~;ne .JTJ. bJ ,q~ dJne, q 7t~,$'-
Itm~s Inspected: Conforming Non [*ems Impectmi: Cum%;~;ng Non Items la~.~..;~,~; C~.I'v. --;-S Hca
Onnfflrulng ConformlBg Couforming
Placing Drawings Bar Length Column T~es
~si~ ~ P,o~ s~r Pb~=eme~ t,,-- surruv s~clns nd ~
Ba~s ele~n ~ Dowel Bars in Place ~ W¢ldcd Splices
Form Clan (./ Proper Bm' Supjxxts ~ Mechanical Splices
D~.repancies / CoTrb-nents:
Inspector's Signature: Z. ~ ,'5 /: Time: to
Client/contractor Signature: Client/Contractor Copied with Results: Yes / No
RoneEn gineers
8908 Ambassador Row
Dallas, Texas 75247
(214) 630-9745
121 North Rayner
Fort Worth, Texas 76111
(817) 831-6211
Report of
ReinforCing Steel Inspection
Client: fJ///<~e' Report No.:
Project No.:
Project: /~cee,,Oa/~ !,~ Date of Service:
Page
Locations and Items Inspected:
Items Inspected: Conforming Non Items Inspected: Conforming Non Items ln~l~cted: Conforming Non
Conforming Conforming Conforming
Placing Drawings Bar Length Column Ties Properly
A~oved ~ and Sha~e ~ Tied and Spaced .~
Bar Size ~ Proper Bar Placement ~ Stirrup Spacing and Typa ~
[~ar Grade ~ Properly Tied ~ Lapped Splices ~
[~am Clean ~ Dowel Bars in Place ~ Welded Splices ~
Form Clean ~ Proper Bar Supports ~ Mechanical Spline~ . _
Number Bars ~ Proper Cover ~
Discrepancies / Comments: ;',~ ~,o.~,~.~
Inspector's Signature: Z, ~,'!f
Time: to
Client/Contractor Signature: Client/Contractor Copied with Results: Yes /No
,:lneers
8908 Ambassador Row, Dallas, TX 75247
2696 Gravel Drive, Fort Worth, TX 76118
6300 Rothwny, Ste. 150, Houston, TX 77040
Corporate Phone: (214) 630=9745
REPORT OF REINFORCING STEEL INSPECTION
Client:
Duke Realty Services, LP
Arm: Mr. feffLangston
5495 Belt Line Road, Suite 360
Dallas TX 75254
Project: Freeport 10
500 Freeport Parkway
Coppell, TX
Services: Reinforcing Steel Inspection
Report No~: 176501
Project No.: 037333
Date of Service: 05/08/2003
Report Date: 05/14/2003
Report of Inspection
On this date, a Rone Engineers, Ltd. representative(s) was on site to perform
Reinforcin9 Steel Inspection. The results are attached.
Technician Time:
Page 1 of 3
Technician: Lanny Gist
Report Distribution:
(1) Duke R~alty Services, LP
(l) Duke Pcealty Services, LP
(1) City of Coppell Building Dept.
(1) Pacheoo Koch Cousuiting Engineers
2:00 p.m. - 2:30 p.m.
(1) Engineering Analy~
(1) City of Coppeu Enginez~ing Dept.
K. Scott Watson
CMT Operations Manager
LIMITATIONS: The ~t results presented herein were prepared based upon thc specific samples provided for testing. We assume no responsibility for variation in quality
(composition, appearance, performance, etc.) or any other feature of similar subject matter provided by persons or conditions over which we have no contwl. Our letters and
reports are for the exclusive use of the clients m whom they are addrnssed and shall not be r~procinced except in full without the written approval ofRone Enginesrs, Ltd.
99DD Pave 1 of 1
8908 Ambassador Row
DaRas, Texas 75247
(214) 63O-9745
121 North Rayner
Fort Worth, Texas 76111
(817) 831-6211
Report of
Reinforcing Steel Inspection
Client: D,d< ~" Report No.:
Project No.:
Project: ~'r e C jgo f7z / c2 Date of Service:
Page
Locationsandltemslnspected: -'7--;e /~e~.~/ d/,~e /-/f/ q-J-~','~
Items lmpeeted: Conforming Non It~a~ lmspeetecl: Conforrain~ Non
Coaforminj Conforming C~fomi~
Fo~ C~ ~ ~ ~ S~ ~ M~ Spli~ _
Discrepancies/Comments:
Inspector's Signature:
Time: to
Client/Contractor Signature: Client/Contractor Copied with Results: Yes / No
RoneEngineers
8908 Ambassador Row
Dallas, Texas 75247
(214) 630-9745
121 North Rayner
Fort Worth, Texas 76111
(817) 831~211
Client:
Project:
Report of
Reinforcing Steel Inspection
Report No.: 17~g-o/
Project No.: O 37333
Date of Service: ~-~_ ~o_ ~_~
Page ~ of ~;
Locations and Items Inspected:
Discrepancies / Comments:
Inspector's Signature:
Time: to
Client/Contractor Signature: Client/Contractor Copied with Results: Yes / No
Client:
Duke Realty Services, LP
Attn: Mr. JeffLangston
5495 Belt Line Road, Suite 360
Dallas TX 75254
Project:
Services:
Freeport 10
500 Freeport Parkway
Coppell, TX
Perform In-Place Density Test in accordance with AS'I'M Standards.
8908 Ambassador Row, Dallas, TX 75247
2696 Gravel Drive, Fort Worth, TX 76118
6300 Rothway, Ste. 150, Houston, TX 77040
Corporate Phone: (214) 630-9745
IN-PLACE DENSITY TESTING
Report No.: 176455
Project No.: 037333
Date of Service: 05/08/2003
Report Date: 05/14/2003
CONTRACTOR:
Test Methods:
Duke Realty Services, LP
ASTM D-2922
ASTM D-3017
M]n No.
Description
PROJECT DATA
Gouge: Troxler 3430
Gouge Serial No: 32720
Test Mode: DT
MOISTURE DENSITY RELATIONS
Maximum
Moisture % Density pcf
Moisture
Current: 657
Previous: 656
Standard Counts
Density
Current: 3082
Previous: 3065
Project Requirements
Moisture Density
1 Dark Brown Clay
19.5
104.5 Optimum +4
95 rain
FIELD DENSITY TESTS
TEST
NO TEST LOCATION
· Backfill
1 Sanitary sewer trench, Line 3 at Line K, 3'
below grade
Backfifl
2' Sanitary sewer trehch, Line 3 at Line N, 3'
below grade
Backfill
3 Sanitary sewer trench, Line 3 at Line IL 3'
below rgade
Technician: Lanny Gist
Report Distribution:
(1) Duke Realty Se~ices, LP
(1) Duke Reelty services, LP
(1) City of Coppell Building Dept.
(1) Pacheco Koch Consulting Engineers
PROBE
DEPTH
M/D MOISTURE WET DENSITY DRY DENSITY DENSITY
No. (%) (pc0 (p~0 (% max)
6" 1
6" 1
6" 1
22.6 124.2 101.3 97
22.9 123.6 100.6 96
21.0 120.6 99.7 95
Test results on this report meet project specification.
Started: 6:30am
(1) Engineering Analyst
(1) City of Coppell Enginecring Dept.
Finished: 2:00pm
CMT Operations Manager.
LIMITATIONS: The te~t results presanted herein were prepared based upon the specific samples provided for testing. We azsume no rnsponsibility for varialion in quality
(composition, appearance, performance, etc.) or any other feature of similar subject matter provided by persons or conditions over which we have no control. Our leRers and
reports are for the exclusive use of the clients to whom they are addressed and shall not be reproduced except in full without the written approval of gone Engineers, Ltd.
07DD Page 1 of 1
8908 Ambassador Row, Dallas, TX 75247
2696 Gravel Drive, Fort Worth, TX 76118
6300 Rothway, Ste. 150, Houston, TX 77040
Corporate Phone: (214) 630-9745
IN-PLACE DENSITY TESTING
CHent: Duke Realty Services, LP
Atln: Mr. JeffLangston
5495 Belt Line Road, Suite 360
ProjeCtr Freeport 10~~
/ 5~.~rt Parkway
~ ~'E"dppell, TX
Services:
Perform In-Place Density Test in accordance with ASTM Standards.
PROJECT DATA
Report No.: 176539
Project No.: 037333
Date of Service: 05/09/2003
Report Date: 05/14/2003
zt,
Project Requirements
Moisture Density
CONTRACTOR: Duke Realty Services, LP Standard Counts
Te~t Methods: ASTM D-2922 Gauge: Troxler 3430 Moisture Density
ASTM D-3017 Gouge Serial No: 32720 Current: 660 Current: 3066
Test Mode: DT
Previous: 657 Previous: 3082
MOISTURE DENSITY RELATIONS
Maximum
M~D No. Description~Moisture % Density pcf
1 . Dark Brown Clay 10~ 4.5 Optimum +4
MOISTURE DRY DENSITY
Backfill
1 Sanitary' sewer trenc~ Line L at Line 3, 2' 6" 1 19.7 124.0 103.6
below grade
Backf'ffi
2 Sanitary sewer trench, Line M at Line 3, 2' 6" 1 20.7 123.0 101.9
below grade
Backf'fll
3 Sanitary sewer trench, Line R at Line 3, 2' 6" I 23.0 126.7 103.0
below grade
Backf'ffi
4 Sanitary sewer trench, Line M at Line 3, i' 6" 1 20.3 121.4 100.9
below grade
Baekf'ffi
5 Sanitary sewer trench, Line P at Line 3, 1' 6" 1 19.6 124.9 104.4
below grade
95
TEST DENSITY
NO (% max)
99
98
99
97
100
LIMITATIONS: The test results presented herein were p~pared based upon the specific samples provided for testing. We assume no responsibility for variation in quality
(composition, appearance,, perfonnance~ etc.) or any other feature of similar subject mat~er provided by persons or conditions over which we have no control. Our lelters and
reports are for the exclusive use of the clients to whom they are addressed and shall not be reproduced except in foil without the writtsa approval of Rone Engineers, Ltd.
07DD Page 1 of 2
Report No.: 176539
Project No.: 037333
Client: Duke Realty Services, LP
RoneEn~lineers
TEST
NO
TEST LOCATION
PROBE
DEPTH
M/D MOISTURE WET DENSITY DRY DENSITY DENSITY
1~o. (%) (1~0 (P~0 (% m~x)
Bacldill
Sanitar~ sewer trench, Line S at Line 3, 1'
below grade
Technician: Lanny Gist
Report Distribution:
(l) Duke Realty Services, LP
(l) Duke Realty Services, LP
(1) City of C°pPell Building Dept.
(1) Pacheco Koch Consulting Engineels
6' 1 23.4 129.0 104.5 100
Started: 6:30am Finished: 2:00pm Ro~l~~
(1) City of Coppell Engineering Dept. K. Scott Watson
CMT Operations Manager
LIMITATIONS: The test results presented herein were prepared based upon the specific samples provided for testing. We assume no responsibility for variation in quality
(composition, appearance, performance, etc.) or any other feature of similar subject mailer provided by persons or cond/tions over which we have no control. Our letters and
reports are for thc exclusive use of the clients to whom they are addressed and shall not be reproduced except in full without the written approval of Rone Engineers, Ltd.
07DD Page 2 of 2