ST9304-CS 980323 BELTLINE ROAD PROJECT 490-403.1/91-829
(Denton Tap Road to MacArthur Boulevard)
t
March 23'. 1998
PROJECT ENGINEER: John ~ef.Meats ~1
FUND 490-403 FUN][/418-829 FUND 8-830
PROJECT DOLLARS
Authorization = $ 4,250,000 $6,100,000 $1,500,000
Available = $ 501,237 $6,100,000 $ 750,000
**TOTAL PROJECT 1985 BOND FUNDS MAY BE COMBINED WITH SANDY LAKE ROAD FOR
1991 BOND FUNDING
County Construction = $ 5,223,853
Contingencies (5 %) = $ 261,193
ROW Acquisition = $ by City
' Administrative Costs (8%) = $ 417,908
, Design = $ 336,640
Materials Testing (1.5%) = $ 78,358
Total Project Cost = $ 6,317,752
DESIGN: Consultant/Award/Work Order/Contract Total
Albert H. Halff Associates/8-30-94/8-31-94/$3 16,040/contract amendment pending approval
Status = Revising preliminary plans/entering pre-~nal stage
Issues/Conflicts = RR spur agreement between City of Dallas and TUE; traffic signals/City
funding
Completion -- JUN 98
ROW: Number of Parcels = 18 (mostly slope easements)
Status of Acquisition = by City
Issues/Conflicts = 12 parcels from TU Elec., 5 from DART, I from developer
Completion = SEPT 98
UTILITIES: Utility Release = NOV 96 CONSTRUCTION: Advertisement = OCT 98
Utilities to be Cleared Contractor/Award/Work
Status Order/Total Contract
Issues/Conflicts Working Days
Completion = NOV 98 Status
Issues/Conflicts
Completion = JUL 2000
490.403.1/829 .PSR