ST9905-CS030512
THE.CITY.OF
May 12,2003
EXPLORER PIPELINE
Patrick Nwakoby
6846 S Canton
Tulsa, OK 74136
RE: Bethel Road I
ST 99-05
Utility Relocations
Dear Mr. NWakoby:
In March 2002, 60% complete plans were provided to your utility company to aid in the relocation of
facilities along Bethel Road. The plans are adequate for relocations along the north side of the
proposed roadway. Storm drain improvements are currently under design for the south side of the
proposed roadway. Enclosed please find a schematic showing the location, number, and size of
the box culverts along the south side. Plans for the storm drain improvements will be forwarded
to you when they are adequate for utility relocations. Right-of-way has not been acquired on
either side of the proposed roadway. Relocations along the north side may remain under the
pavement in those areas where the right-of-way has not been acquired. The project is scheduled to
start construction in April 2004.
Your consideration of this matter is appreciated. Should you have any questions or need any additional
information, please feel free to contact rne at 972-304-7019.
Sincerely,
:~iU,'~.>{lll\ -fe, "I Lc);/
Suzan C. aylor
, .
CIP Co mator
Enclosure
255 PARKWAY * P.O BOX 478 * COPPELL TX 75019 * TEL 972/462 0022 * FAX 972/304 3673
THE.CITY.OF
May 12,2003
TOUCH AMERICA
Mark Paffhausen
130 N. Main Street
Butte, MT 59701
RE: Bethel Road I
ST 99-05
Utility Relocations
Dear Mr. Paffhausen:
In March 2002, 60% complete plans were provided to your utility company to aid in the relocation of
facilities along Bethel Road. The plans are adequate for relocations along the north side of the
proposed roadway. Storm drain improvements are currently under design for the south side of the
proposed roadway. Enclosed please find a schernatic showing the location, number, and size of
the box culverts along the south side. Plans for the storm drain improvements will be forwarded
to you when they are adequate for utility relocations. Right-of-way has not been acquired on
either side of the proposed roadway. Relocations along the north side may remain under the
pavernent in those areas where the right-of-way has not been acquired. The project is scheduled to
start construction in April 2004.
Your consideration ofthis matter is appreciated. Should you have any questions or need any additional
infonnation, please feel free to contact me at 972-304-7019.
Sincerely,
('~..\-:-"-
~ft~[I.'V' \ C'-"ILo(....
SuzaJ;1 Taylor
CIP CO dinator
Enclosure
255 PARKWAY * P,Q BOX 478 * COPPELL TX 75019 * TEL 972/462 0022 *
FAX 972/304 3673
THE.CITY.OF
COPPELL
May 12, 2003
ONCOR
Doug Brewer, Project Mgmt.
4200 N. Belt Line Road
Irving, TX 75038
RE: Bethel Road I
ST 99-05
Utility Relocations
Dear Mr. Brewer:
In March 2002, 60% complete plans were provided to your utility company to aid in the relocation of
facilities along Bethel Road. The plans are adequate for relocations along the north side of the
proposed roadway. Storm drain improvements are currently under design for the south side of the
proposed roadway. Enclosed please find a schematic showing the location, number, and size of
the box culverts along the south side. Plans for the storm drain improvements will be forwarded
to you when they are adequate for utility relocations. Right-of-way has not been acquired on
either side of the proposed roadway. Relocations along the north side may remain under the
pavement in those areas where the right-of-way has not been acquired. The project is scheduled to
start construction in April 2004.
Your consideration of this matter is appreciated. Should you have any questions or need any additional
information, please feel free to contact me at 972-304-7019.
Sincerely,
'-.......
\~).l~. u..V\ \Z;.. \ Lu.-
Suzap . Taylor
CIP Co dinator
Enclosure
255 PARKWAY * P.O BOX 478 * COPPELL TX 75019 * TEL 972/462 0022 * FAX 972/304 3673
THE.CITY.OF
8
May 12,2003
VERIZON COMMUNICA nONS
Bob Holland
2094 McGee Lane
Lewisville, TX 75077
RE: Bethel Road I
ST 99-05
Utility Relocations
Dear Mr. Holland:
In March 2002, 60% complete plans were provided to your utility company to aid in the relocation of
facilities along Bethel Road. The plans are adequate for relocations along the north side of the
proposed roadway. Storm drain improvements are currently under design for the south side of the
proposed roadway. Enclosed please find a schematic showing the location, number, and size of
the box culverts along the south side. Plans for the storm drain improvernents will be forwarded
to you when they are adequate for utility relocations. Right-of-way has not been acquired on
either side of the proposed roadway. Relocations along the north side may remain under the
pavement in those areas where the right-of-way has not been acquired. The project is scheduled to
start construction in April 2004.
Your consideration of this matter is appreciated. Should you have any questions or need any additional
information, please feel free to contact me at 972-304-7019.
Sincerely,
S~1';~I::;+'/
CIP Co~inator
Enclosure
255 PARKWAY * P.O.BOX 478 * COPPELL TX 75019 * TEL 972/462 0022 * FAX 972/304 3673
THE.CITY,OF
COPPELL
~~~~
"~ q
"5 ' \ ~
May 12, 2003
TXU Communication Services
Mark Wilson
115 W Seventh St.
Suite 308
Fort Worth, TX 76102
RE: Bethel Road I
ST 99-05
Utility Relocations
Dear Mr. Wilson:
In March 2002, 60% complete plans were provided to your utility company to aid in the relocation of
facilities along Bethel Road. The plans are adequate for relocations along the north side of the
proposed roadway. Storm drain improvements are currently under design for the south side of the
proposed roadway. Enclosed please find a schematic showing the location, number, and size of
the box culverts along the south side. Plans for the storm drain improvements will be forwarded
to you when they are adequate for utility relocations. Right-of-way has not been acquired on
either side of the proposed roadway. Relocations along the north side may remain under the
pavement in those areas where the right-of-way has not been acquired. The project is scheduled to
start construction in April 2004.
Your consideration of this rnatter is appreciated. Should you have any questions or need any additional
information, please feel free to contact me at 972-304-7019.
Sincerely,
c--:-I -,.-,.,._-
\,~2i...., >'~""\ \ C _\ ~.\..~
Suzan Taylor
CIP Co rdinator
Enclosure
255 PARKWAY * P,D.BOX 478 * COPPELL TX 75019 * TEL 972/462 0022 * FAX 972/304 3673
THE.CITY.OF
May 12, 2003
OnFIBER CARRIER SERVICE
Tim Norris, Operations Mgr.
1820 N Glenville Drive, Suite 114
Richardson, TX 75081
RE: Bethel Road I
ST 99-05
Utility Relocations
Dear Mr. Norris:
In March 2002, 60% complete plans were provided to your utility company to aid in the relocation of
facilities along Bethel Road. The plans are adequate for relocations along the north side of the
proposed roadway. Storm drain improvements are currently under design for the south side of the
proposed roadway. Enclosed please find a schematic showing the location, number, and size of
the box culverts along the south side, Plans for the storm drain improvements will be forwarded
to you when they are adequate for utility relocations. Right-of-way has not been acquired on
either side of the proposed roadway. Relocations along the north side may remain under the
pavement in those areas where the right-of-way has not been acquired. The project is scheduled to
start construction in April 2004.
Your consideration of this rnatter is appreciated. Should you have any questions or need any additional
infonnation, please feel free to contact me at 972-304-7019.
Sincerely,
c' -....,.
\.. '\.... (, ." lc<~\l,y'
, '.J.M-~"-'" ,
Suzan!c. Taylor
CIP Coo inator
Enclosure
255 PARKWAY * P.O BOX 478 * COPPELL TX 75019 * TEL 972/462 0022 * FAX 972/304 3673
THE.CITY,OF
May 12, 2003
QWEST COMMUNICATIONS
Paul Gonzales, Relocation Mgr.
1860 Lincoln Street, Suite 200
Denver, CO 80295
RE: Bethel Road I
ST 99-05
Utility Relocations.
Dear Mr. Gonzales:
In March 2002, 60% complete plans were provided to your utility company to aid in the relocation of
facilities along Bethel Road. The plans are adequate for relocations along the north side of the
proposed roadway. Storm drain improvements are currently under design for the south side of the
proposed roadway. Enclosed please find a schematic showing the location, number, and size of
the box culverts along the south side. Plans for the storm drain improvements will be forwarded
to you when they are adequate for utility relocations. Right-of-way has not been acquired on
either side of the proposed roadway. Relocations along the north side may remain under the
pavernent in those areas where the right-of-way has not been acquired. The project is scheduled to
start construction in April 2004.
Your consideration of this matter is appreciated. Should you have any questions or need any additional
information, please feel free to contact me at 972-304-7019.
Sincerely,
(~,I.~[\"A1\T(~"I~W~
Suzap . Taylor
CIP C rdinator
Enclosure
255 PARKWAY * P.D.BOX 478 * COPPELL TX 75019 * TEL 972/462 0022 * FAX 972/304 3673
THE,CITY.OF
COPPELL
May 12,2003
COSERV
Brian Tomlinson
7701 S Stemmons
Corinth, TX 75065
RE: Bethel Road I
ST 99-05
Utility Relocations
Dear Mr. Tornlinson:
In March 2002, 60% complete plans were provided to your utility company to aid in the relocation of
facilities along Bethel Road. The plans are adequate for relocations along the north side of the
proposed roadway. Storm drain improvements are currently under design for the south side of the
proposed roadway. Enclosed please find a schematic showing the location, number, and size of
the box culverts along the south side. Plans for the storm drain improvements will be forwarded
to you when they are adequate for utility relocations. Right-of-way has not been acquired on
either side of the proposed roadway. Relocations along the north side may remain under the
pavement in those areas where the right-of-way has not been acquired. The project is scheduled to
start construction in April 2004.
Your consideration ofthis matter is appreciated. Should you have any questions or need any additional
information, please feel free to contact me at 972-304-7019.
Sincerely,
21:~::;,lO'"
CIP tdc,rdinator
Enclosure
255 PARKWAY * P,Q sox 478 * COPPELL TX 75019 * TEL 972/462 0022 * FAX 972/304 3673
THE.CITY.OF
COPPELL
~~t~"~ (p]"N. ....~
~~' ~'k~~, ,~
r, "-. ,. /
l' ~"'~' ""'''''''''' ' "
e " '" ~ q
.!' 0'\ S \ ~
May 12,2003
MARTINEZ BROWER GROUP, INe.
Charles B. Martinez
1208 West Executive Dr.
Richardson, TX 75081
RE: Bethel Road I
ST 99-05
Utility Relocations for AT&T Local Services, SBC, and MFN
Dear Mr. Martinez:
The permit for the relocation of the above referenced utilities was approved today. The utilities
will be relocated along the north side of the proposed roadway, however they do cross to the south
at the intersection of Freeport Parkway. Storm drain improvements are currently under design for
the south side of the proposed roadway. Enclosed please find a schematic showing the location,
number, and size of the box culverts along the south side. As previously discussed, please review
the schematic to ensure there are no utility relocation conflicts with the proposed improvements.
Your consideration of this matter is appreciated. Should you have any questions or need any additional
information, please feel free to contact me at 972-304-7019.
Sincerely,
()U"i\<^/\i\ TQ:~Il0v
Suz~ 5. Taylor
CIP Coordinator
Enclosure
255 PARKWAY * P.D.BOX 478 * COPPELL TX 75019 * TEL 972/462 0022 * FAX 972/304 3673
THE.CITY.OF
COPPELL
.~ j~ tj ,co- c.
-,
'" s
May 12, 2003
SWP CONSULTANTS, LLC
Phillip W. Porter
5443 S. 99"' East Ave.
Tulsa, OK 74146
RE: Bethel Road I
ST 99-05
Utility Relocations
Dear Mr. Porter:
You recently submitted relocation plans for the Qwest fiber system along Bethel Road. The utility
will be relocated along the north side of the proposed roadway, however it does cross to the south
at the intersection of Freeport Parkway. Storm drain improvements are currently under design for
the south side of the proposed roadway. Enclosed please find a schematic showing the location,
number, and size of the box culverts along the south side. As previously discussed, please review
the schematic to ensure there are no utility relocation conflicts with the proposed improvements.
Your consideration of this rnatter is appreciated. Should you have any questions or need any additional
information, please feel free to contact me at 972-304-7019.
Sincerely,
,\oil y~",1'\ Tl\"llc ,./
Suzan ~ Taylor
CIP Coordinator
Enclosure
255 PARKWAY * P,D BOX 478 * COPPELL TX 75019 * TEL 972/462 0022 * FAX 972/304 3673
THE'CiTY'OF
COPPELL
May 12, 2003
COMCAST
Kevin Mullaney, Construction Supervisor
1565 Chenault Street
Dallas, TX 75228
RE: Bethel Road I
ST 99-05
Utility Relocations
Dear Mr. Mullaney:
In March 2002, 60% complete plans were provided to your utility company to aid in the relocation of
facilities along Bethel Road. The plans are adequate for relocations along the north side of the
proposed roadway. Storm drain irnprovements are currently under design for the south side of the
proposed roadway. Enclosed please find a schematic showing the location, number, and size of
the box culverts along the south side. Plans for the storm drain improvements will be forwarded
to you when they are adequate for utility relocations. Right-of-way has not been acquired on
either side of the proposed roadway. Relocations along the north side may remain under the
pavement in those areas where the right-of-way has not been acquired. The project is scheduled to
start construction in April 2004.
Your consideration of this matter is appreciated. Should you have any questions or need any additional
information, please feel free to contact me at 972-304-7019.
Sincerely,
(_.~\
I,,-,),\.., ~.,J/'"\ 16 ~l L.~'1/
SuzanlC. aylor
CIP Coo inator
Enclosure