DR0001-MP030606ID j Task Name _
1 TDESIGN PHASE
2
Design
3
Advertisement
4
Bid Opening
5
City Council
6
CONSTRUCTION
7 j
Preconstruction Meeting
Notice to Proceed
8
9
Construction
Project: DR 00-01
Date: Fri 66M
MACARTHUR / SAMUEL DRAINAGE PROJECT
DR OD-01
IN -HOUSE DESIGN
Qtr 1.2003
Task Milestone.
Qtr
Summary ^ Deadline r
Page 1
MACARTHUR / SAMUEL DRAINAGE PROJECT
DR 00-01
IN -HOUSE DESIGN
Notice to Proceed
Contractor to take delivery of precast box culvert the first week in March 2002.
Construction
WEEK 1 (Apr. 21 -25)
Placed the signs. Sawcut DeForest. Installed 36' into the headwall - demolished 36' back to first manhole installed to 20' south.
WEEK 2 (Apr. 28 - May 2)
Installed the 27' storm drain to approximate Sta. 2 +81. Installed the 24" storm drain to approximate Sta. 6+00.
WEEK 3 (May 5 - 9)
Installed the 24' storm drain across the park.
WEEK 4 (May 12 -16)
Installed 24" storm drain across Samuel. Poured the pavement repair. Installed 24" lateral south to MacArthur. Poured one inlet bottom on Samuel and one inlet bottom on MacArthur.
WEEK 5 (May 19 - 23)
Finished the installation of storm drain across MacArthur. Wafting on gas main relocation to pour inlets at Samuel.
WEEK 6 (May 26- 30)
Conflicts with power poles and underground utilities - will delay the construction of inlets at Cribbs Drive. Need to determine the owners of the utilities.
WEEK 7 (June 2 -6)
Construction of project is delayed approximately three weeks while the conflicting utilties are relocated. Project is approximately 85% complete.
Page 2