Loading...
Bank One-CS030610• BROCKETTE • DAVIS • DRAKE, inc. consulting engineers June 10, 2003 Ms. Teresa Turner, E.I.T. City of Coppell 255 Parkway PO box 478 Coppell, Texas 75019 Re: Natches Trace Addition, Lot 1 Block A Bank One Construction Plan Review Comments BDD Project No. C02364 Dear Ms. Turner: We are returning the marked-up set and two sets of the revised plans to the City for review. We have made the following revisions and/or corrections in accordance with your comments letter dated June 5 2003: Cover Sheet: The legal plat title has been included on the cover sheet. Plat: We have shown the sidewalk easement that is included throughout the plan set on the north side of the mutual access onto Denton Tap Road. 2. We have provided a copy of the legal description for the 20' sanitary sewer easement as was a condition of the Planning and Zoning Commission's approval on 4/17/2003. Site Plan: We have provided the revised site plan including the pavement markings and signage for the one-way driveway on the south side of the building (as received by the Planning Department on 6/2/2003). 2. The 5' brick paver sections in the driveways have been changed to 8' stamped concrete, as per the city's subdivision ordinance and construction details. Paving & Horizontal Control Plan: The strength of the concrete has been increased to 4000 psi. 2. Note #5 has been revised to reflect the city's construction standards and subdivision ordinance. 3. A note was added to our plans stating that any lane closures required for the construction of the driveways can only occur between 9:00 a.m. - 4:00 p.m., or as specified by the engineering department. Additionally, if constriction extends into the 1003-2004 school year, additional time restrictions may be required. Civil & Structural Engineering • Surveying 4144 North Central Expressway, Suite 1100 Dallas. Texas 75204 (214) 824-3647 • CivillSurvey Fax (214) 824-7064 • Structural Fax (214) 824-2566 Ms. Teresa Turner, E.I.T. City of Coppell Re: Arbor Woods City File No. S023-024 File No. 311T-6962 BDD Project No. C02364 June 10, 2003 Page 2 of 2 Gradins~ Plan Note #10 has been revised to reflect the city's construction standards and subdivision ordinance. 2. Top-of-curb and spot elevations along the north side of the property have been provided. 3. The 0.80% Swale drains towards inlets on Denton Tap Road to keep offsite water from draining onto the site. Erosion Control Plan A note has been added that the contractor will need to provide a construction site notice in accordance with TCEQ General Permit Number TXR 150000. Details All details are specific to this project. A note has been added that the contractor is required to have on-site, at all times, a copy of the City of Coppell's Construction Details. I trust that these revisions will meet your approval. Please review and contact me with any questions or further comments. Sincerely, BROC~KjETsT~E-DAVIS-DRAKE, INC. Brandon O'Donald, P.E. Project Manager M:10asa\Civil\2002\C02360 Bank One - Coppell\Comsnents & Responses\06 10 Ol responses.doc