Teresa Turner- Re`. BankOne -Natches Trace Addition Page 1
From: Travis Attanasio <Tattanasio@bddeng.com>
To: Teresa Turner <tturner@ci.coppell.tx.us>
Date: 7/18/03 3:17:03 PM
Subject: Re: Bank One -Natches Trace Addition
Teresa,
We should have them to you by noon on Monday at the latest.
-Travis
Teresa Turner wrote:
> Travis -
> Answers:
> 1. Page SD7 of our specs. call for No. 3 reinforcing steel on 18"
> centers longitudinally, 24" centers transversly, and shall conform to
> the requirements of ASTM-615, Grade 60.
> 2. I believe this comment was generated by the inspector and can
> likely be addressed in the field. No changes to the plans are required
> for this comment.
> Let me know if you have any other questions. By the way, the project
> manager would like some idea of when you will get the revised plans to
> the city. Do you have an expected day and, if so, when? I'll call her
> and let her know. Thanks.
> Teresa
> »> Travis Attanasio <Tattanasio@bddeng.com> 7/18/03 9:10:58 AM »>
> Teresa,
> A couple of questions have come up from the latest set of city
> markups.
> 1. On sheet C7, instead of using a WWF (welded wire frame) for the
> sidewalks you had requested #3 on 18"x24" centers, which direction are
> the centers supposed to go? We assume that the 24" centers are in
> the
> direction of travel.
> 2. On sheet C7, What is meant by the quoted text "Sanitary Tee"?
> All other comments have been addressed and we will get you a new set
> of
> plans for your approval as soon as possible.
> Thank you,
> Travis Attanasio
> Graduate Engineer