RE: Coppell Road - Project Schedule
Ken also noticed that you have a contract award for May 2004. The project is scheduled to start
construction in June 2005. This gives us another year for design.
>>> "Roberts, Ken" <kar@Huitt-Zollars.com> 07/14/03 02:51 PM >>>
Suzan,
Before I revise the schedule I a couple of questions.
How long do you need for the right-of-way acquisition?
Is 2 or 3 months reasonable for utility relocations?
Thanks for the input.
Kenneth Roberts, PE
Huitt-Zollars, Inc.
> -----Original Message-----
> From: Suzan Taylor fSMTP:stavlor@cLcoppell.tx.usl
> Sent: Monday, July 14, 2003 9:28 AM
> To: kar@huitt-zollars.com
> Subject: Coppell Road - Project Schedule
>
> Kenneth:
> It takes more than two months to acquire the right-of-way. It is
> probably not realistic to think that we could advertise for bids in
> April if we get the legals and plats in February. We may also have
> franchise utilities that will need to be relocated once the ROW is
> acquired.
> We will start copying the existing plans associated with Coppell Road
> and I will let you know when we are complete.
>
> Suzan Taylor