Community CU-LR020930Hooper Engineering Laboratories, Inc. Construction Materials Testing REPORT OF CONCRETE TESTS JOB NO.: 02.1058 CLIENT: Community Credit Union DATE: 30 September 2002 PROJECT: Community Credit Union-Coppell Branch SUPPLIER: Beall LOCATION OF POUR SET 1: Piers at retaining wall: #2, 3, 4, 5, 6, 7 and bottom 14' of #8 LOCATION OF POUR SET 2: SAMPLE DATA: SET 1 SET 2 MIX N0. 330J1541 Truck No. 121 Cement 400 Type I Ticket No. 89016181 Flyash 70 Time Batched 11:15am Sand 1445 Time Sampled 12:15pm in. Concrete Temp. (ASTM ctosal 86°F 1.0 in. 1850 Air Content (ASrM cz3tl Water 258 Unit Weight IASTM ct3sl Admix #1 MB 300R @ 11.8 oz . Admix #2 AEA COMPRESS/VE STRENGTH TESTS IASTM c3sl (Standard 6 inch x 12 inch cy linder) Cylinder Slump Age Test Total Load Compressive Required Number Inches Days Date Pounds Strength 28-Day IA$TM C143) psi Strength 21 5.25 7 10/07/02 78,000 2760 22 5.25 28 10/28/02 97,600 3450 23 5.25 28 10/28/02 99,00.0 3500 24 5,25 56 11/25/02 28-Day Average 348Q 3000 TECHNICIAN: MFM DISTRIBUTION: 11) Community Credit Union (11 PGAL, Inc. (11 Nelson Consulting, Inc. 111 Mycon General Contractors (2) City of Coppell 2870 Walnut Hill Lane Dallas, Texas 75229 (214) 351-6419 Fax (214) 351-5748 ^. -. Hooper Engineering Laboratories, Inc. Construction Materials Testing STRAIGHT SHAFT PIER INSTALLATION OBSERVATION CLIENT: Community Credit Union DATE: 30 September 2002 PROJECT: Community Credit Union-Coppell Branch JOB NO.: 02.1058 687 Denton Tap Rd., Coppell, TX TIME: 8:OOam-4:OOpm DRILLER: Auger Drilling 8.0 hours PIER SHAFT TOP OF ALIGN/ DEPTH REO'D. ACTUAL TOTAL FINAL WATER MARK DIA. CONC. ELEV. PLUMB TO GREY PENE. PENE. DEPTH POUR IN HOLE Retaining Wall #5 18" -3.3' ok/ok 17,0' 4.0' 5.0' 22.0' 12:32 None #4 18" -3.2' ok/ok 17.5' 4.0' 4.8' 22.3' 12:25 None #3 18" -3.5' ok/ok 17.5' 4.0' 5.7' 23.2' 12:15 None #2 18" -3.3' ok/ok 17.5' 4.0' 6.8' 24.3' 12:05 Trace #6 18" -2.3' ok/ok 16.0' 4.0' 5.2' 21.2' 12:45 None #7 18" -2.8' ok/ok 17.5' 4.0' 4.3' 21.8' 12:53 Trace #8 18" -2.8' ok/ok 17.0' 4.0' 4.6' 21.6' 2:28 -Trace #9 18" -2.8' ok/ok 17.0' 4.0' 5.8' 22.8' 3:10 Trace #10 18" -2.7' ok/ok 16.5' 4.0' 5.5' 22.0' 3:00 Trace #11 18" -2.4' ok/ok 17.0' 4.0' 4.6' 21.6' 2:55 Trace #12 18" -2.6' okJok 16.5' 4.0' 4.0' 20.5' 2:48 None #13 18" -3.0' ok/ok 18.0' 4.0' 4.1' 22.1' 2:40 None #14 18" -2.5' ok/ok 18.5' 4.0' 4.5' 23.0' 2:35 None NOTES: 1) Pier reinforcing verified to be correct in accordance with project plans and specifications, unless noted otherwise. 2) Concrete placed in piers within 8 hours of drilling completion, unless noted otherwise. 31 Depth to Grey and Total Depth were measured from current grade at time piers were drilled. Contractor must furnish actual elevation, if required. 4) Top of Concrete Elevation is relative to grade at time piers were drilled. 5) Each pier was cleaned out a second time just before placing concrete due to slight caving of sand/gravel and some water seepage. 6) Excess penetration not requested by inspector. 7) No tremie used. Contractor using over-turned chute to point concrete down center of pier holes. 8) Retaining wall piers numbered starting at west end with #1. TECHNICIAN: MFM DISTRIBUTION: I1) Community Credit Union (1) PGAL, Inc. (1) Nelson Consulting, Inc. (1) Mycon General Contractors (2) City of Coppell 2870 Walnut Hill Lane Dallas, Texas 75229 (214) 351-6419 Fax (214) 35t-5t48 r• Hooper Engineering Laboratories, Inc. Construction Materials Testing REPORT OF CONCRETING OPERATIONS HE JOB N0. 02.1058 CLIENT: Community Credit Union DATE: 30. September 2002 PROJECT: Community Credit Union-Coppell Branch WEATHER: Clear/Windy CONCRETE SUPPLIER: Bea11 Concrete AIR TEMP: 82-9.Q°F LOCATION OF CONCRETE PLACED: 13 biers at retaining wall (See Pier Report of 9/30./02} Materials Design Mix Cement: MiX330J154t 30OO.psi Brand Cemex Type I Source $in @ Plant #89. (Lewsvillel~ax. Water-Cement Ratio by weight Aggregate Type Source Batch Weights - S. S. Dry Basis: Size F.A. 0 - #4 Sand I.A. C.A. 1~~ - #4 Cr. Stone Actual Batch Computations: Trini M~tls. Martin Marietta Cement 400/70.. F.A. 1445 I.A. C.A. 1850_ Admix 1v1g 3O0R @-11.8 oz/vd % Free Moisture Water Cement F.A. 5.0 72 I.A. C.A. Total Free Water Added at Mixer Total Water Actual Batch Wts. 400/70 1517 1850 albs. 178 lbs. 250 lbs. Time Started: 11;45am Time Finished: 3:15pm Concrete Placed, c.y.: 20. Concrete Temp: Cylinders Made: Z1 - 24 Remarks: ~..d-- Certified Correct MFM Inspector 2870 Walnut Hill Lane Dallas, Texas 75229 (214) 351-6419 Fax (214) 351-5148 Hooper Engineering Laboratories, Inc. Construction Materials Testing REPORT OF CONCRETE TESTS JOB NO.: 02.1058 CLIENT: Community Credit Union DATE: 30 September 2002 PROJECT: Community Credit Union-Coppell Branch SUPPLIER: Beall LOCATION OF POUR SET 1: Piers at retaining wall: #2, 3, 4, 5, 6, 7 and bottom 14' of #8 LOCATION OF POUR SET 2: SAMPLE DATA: SET 1 SET 2 MIX N0. 330J1541 Truck No. 121 Cement 400 Type I Ticket No. 89016181 Flyash 70 Time Batched 11:15am Sand 1445 Time Sampled 12:15pm in. Concrete Temp. (ASrM ciosal 86°F 1.0 in. 1850 Air Content (ASTM C2311 Water 258 Unit Weight (ASTM ci3a1 Admix #1 MB 300R @ 11.8 oz. Admix #2 AEA COMPRESSIVE STRENGTH TESTS (ASTM c3sl {Standard 6 inch x 12 inch cylinder) Cylinder Slump Age Test Total Load Compressive Required Number Inches Days Date Pounds Strength 28-Day (ASTM C1431 p51 Strength 21 5.25 7 10/07/02 22 5.25 28 10/28/02 23 5.25 28 10/28/02 24 5.25 56 1 1 /25/02 TECHNICIAN: MFM DISTRIBUTION: 11) Community Credit Union {1) PGAL, Inc. (1) Nelson Consulting, Inc. (1) Mycon General Contractors (2) City of Coppell 78,000 2760 97,600 3450 99.,000 3500. 110,500 3910 28-Day Average 3480. 3000 ~n,~..R~.~.P ?~. ~n.~ 2870 Walnut Hill Lane Dallas, Texas 75229 (214) 351-6479 Fax (214) 351-5148 Hooper Engineering Laboratories, Inc. Construction Materials Testing REPORT OF CONCRETE TESTS JOB NO.: 02.1058 CLIENT: Community Credit Union DATE: 30 September 2002 PROJECT: Community Credit Union-Coppell Branch SUPPLIER: Beall LOCATION OF POUR SET 1: Piers at retaining wall: #2, 3, 4, 5, 6, 7 and bottom 14' of #8 LOCATION OF POUR SET 2: SAMPLE DATA: SET 1 SET 2 MIX N0. 330J1541 Truck No. 121 Cement 400 Type I Ticket No. 89016181 Flyash 70 Time Batched 11:15am Sand 1445 Time Sampled 12:15pm in. Concrete Temp. IASTM ciosai 86°F 1.0 in. 1850 Air Content IASTM c2st1 Water 258 Unit Weight IASTM ci3a) Admix #1 MB 300R @ 11.8 oz. Admix #2 AEA COMPRESS/VE STRENGTH TESTS IASTM cssl (Standard 6 inch x 12 inch cylinder) Cylinder Slump Age Test Total Load Compressive Required Number Inches Days Date Pounds Strength 28-Day IASTM C743) psi Strength 21 5.25 7 10/07/02 22 5.25 28 10/28/02 23 5.25 28 10/28/02 24 5,25 56 11/25/02 TECHNICIAN: MFM DISTRIBUTION: (1) Community Credit Union (1) PGAL, Inc. 11) Nelson Consulting, Inc. 11) Mycon General Contractors 121 City of Coppell 78,000 2760 28-Day Average 3000 2870 Walnut Hill Lane Dallas, Texas 75229 (214) 351-6419 Fax (214) 351-5148