SW0001-MP030804RIVERCHASE SIDEWALK
SW 00-01
PACHECO KOCH ENGINEERING
ID Task Name
1 DESIGN PHASE
2
i Design
3
Advertisement
4
Bid Opening
5
City Council
6
PERMITS
7
TAS
8
RIGHT -OF -WAY
9
City of Irving
10
Response Received
11
Approved
12
Dallas Water Utilities
13
Approved
14
TXU Electric
15
Response Received
16
Response Received
17
Acquired by City
18
Lot 11 River Ridge Addition
19
Acquired by City
20
HOA River Ridge Addition
21
Acquired by City
22
CONSTRUCTION
23
Preconstruction Meeting
24
Notice to Proceed
25
Construction
Mar I Apr1 May i Jun i Jul Aug SeF
Project: SW OD-01 Task Milestone . Summary ^ Deadline
Date: Mon 8/4A3
Page 1
RIVERCHASE SIDEWALK
SW 00-01
PACHECO KOCH ENGINEERING
2 Design
On October 9, 2001 TXU decided not to approve the permit. Sidewalk will need to be redesigned to avoid conflict with TXU transmission lines. Working with TXU to resolve issue.
7 TAS
Plans were submitted by Pacheco Koch. Minor comments were incorporated into the final bid set.
9 City of Irving
First request sent on September 12, 2001. Second letter sent with revised plans on May 7, 2002.
10 Response Received
City of Irving did not approve permit - would not allow elevated portion of sidewalk within their easement.
12 Dallas Water Utilities
First letter sent on September 12, 2001. Second letter send with revised plans on May 7, 2002.
14 TXU Electric
TXU denied request for use of easement. The sidewalk must cross beneath the wires within a 50 -foot radius of the transformer tower. TXU sent letter dated March 20, 2002 which provided acceptable
areas for the crossing of the TXU easements. City sent letter March 22 with exhibit showing two options for the sidewalk layout.
15 Response Received
Did not approve the permit.
16 Response Received
Did not approve the permit.
17 Acquired by City
September 9, 2002 - TXU requested revised plat, wrong page number. PKCE revised.
23 Preconstruction Meeting
Contractor requested that the Notice to Proceed be delayed. The work limits are not easily accessible because of all the recent rain.
25 Construction
WEEK 1 (Apr. 21 -25)
No activity.
WEEK 2 (Apr. 28 - May 2)
Graded area for the concrete on -grade sidewalk along Starleaf Drive.
WEEK 3 (May 5 - 9)
No activity.
WEEK 4 (May 12 -16)
No activity.
WEEK 5 (May 19 -23)
No activity.
WEEK 6 (May 26 - 30)
Subcontractor for the elevated sidewalk started work on May 31.
WEEK 7 (June 2 - 6)
No activity.
WEEK 8 (June 9 -13)
Contactor started the installation of the helical piers - installed approximately three - fourths of the piers.
WEEK 9 (June 16 - 20)
Installed the joists, 4"x4" posts, and decking, starting from Starleaf to the 2nd turn in the sidewalk.
WEEK 10 (June 23 - 27)
Worked on the installation of the horizontal rails.
WEEK 11 (June 30 - July 4)
Worked on the installation of the horizontal rails and 4X4 wiring.
WEEK 12 (July 07 -11)
Worked on the installation of the horizontal rails and 44 wiring.
WEEK 13 (July 14 -18)
Worked on the installation of piers, headers, and joists from 2nd PI to 40 feet west of Bradford. Received information from the engineer for the installation of a 2x6 on top of the 44 posts.
WEEK 14 (July 21 - 25)
Poured the five foot concrete sidewalk along Starleaf. Constructed the handicapped ramps.
WEEK 15 (July 28 - Aug. 1)
Page 2
RIVERCHASE SIDEWALK
SW 00-01
PACHECO KOCH ENGINEERING
Poured the eight foot sidewalk. Worked on the installation of the elevated sidewalk. Complete to within 40 feet of Bradford.
Page 3