Freeport NIP(7.0)-LR030805RoneEngineers to A LEIGH COMPANY Client: Duke Realty Services, LP Attn: Mr. Jeff Langston 5495 Belt Line Road, Suite 360 Dallas TX 75254 Project: Services: Page 1 of 3 Freeport 10 500 Freeport Parkway Coppell, TX Structural Steel Inspection Report of Inspection On this date, a Rone Engineers, Ltd. representative(s) arrived on site as scheduled to perform Structural Steel Inspection. The results are attached. Technician Time: 11:45 AM 3:30 PM Technician: D, Wilcher CAWI- 02040654 Report Distribution: (1) Duke Realty Services, LP (1) Duke Realty Services, LP (1) City of Coppell Engineering Dept. (1) Pacheco Koch Consulting Engineers (1) Engineering Analyst (1) City of Coppell Bldg. Inspections 8908 Ambassador Row, Dallas, TX 75247 2696 Gravel Drive, Fort Worth, TX 76118 6300 Rothway, Ste. 150, Houston, TX 77040 Corporate Phone: (214) 630 -9745 REPORT OF STRUCTURAL STEEL INSPECTION Report No.: Project No.: Date of Service: Report Date: 601726 037333 07/14/2003 08/05/2003 Rone Engineers, Lt M. Tupa, C 94030831 Certified Welding Inspector ICBO# 97537531 LIMITATIONS: The test results presented herein were prepared based upon the specific samples provided for testing. We assume no responsibility for variation in quality (composition, appearance, performance, etc.) or any other feature of similar subject matter provided by persons or conditions over which we have no control. Our letters and reports are for the exclusive use of the clients to whom they are addressed and shall not be reproduced except in full without the written approval of Rone Engineers, Ltd. 99DF Page 1 of 1 Client: Duke Realty Services, LP Report 601726 Project: Freeport 10 Project 037333 500 Freeport Parkway Date of Service: 07/14/03 Coppell, TX RoneEngineers to A LEIGH COMPANY Drawings Utilized: *Discrepancies Comments: Mike Tupa Certified Welding Inspector CWI #94030831 REPORT OF STRUCTURAL STEEL INSPECTION 8908 Ambassador Row Dallas, Texas 75247 214.630.9745 FAX 214.630.9819 Service: Perform a Structural Steel Inspection as detailed below. Structural Locations and Items Inspected: 1. Bar joist inspection at grid location A.3 to H and 10 through 15 2. W.Q.T.'s review documentation Rone Engineers arrived at the above location as per the request of Michael Cox, the superintendent for Duke Construction Company, the general contractor, to begin monitoring the steel erection by Ramco Steel Erectors. The results of today's inspection are listed as follows: I. W.Q.T.'s not on file for review. After conversation with the steel erection superintendent, the W.Q.T.'s will be provided on the next inspection. Rone will carry this item as open until such time as proper W.Q.T.'s are provided for review. (non compliant) II. Bar joist inspection of the roof framing at grid location A.3 to H and 10 through 15 is as follows; A. *At this time, all joist seat welds were not de- slagged which is non compliant with AWS D1.1 -02 code requirements. After a conversation with the superintendent for Duke Construction Company and the structural engineer, Steve Burns with Engineering Analysts and Ramco Steel Erectors who stated that the welds at the joist bearing plates will not be de- slagged as per written directive by the structural engineer. Rone has been instructed by the structural engineer to simply verify that there appears to be fillet welds installed on each side of the joist seat. Rone has agreed to inspect per the inspection criteria given as long as written documentation is provided by the structural engineer accepting the responsibility for visual acceptance criteria that can not be performed by Rone Engineers as per AWS D1.1 -02. Until documentation has been received and Page 2 of 3 LIMITATIONS: The test results presented herein were prepared based upon the specific samples provided for testing. We assume no responsibility for variation in quality (composition, appearance, performance, etc.) or any other feature of similar subject matter provided by persons or conditions over which we have no control. Our letters and reports are for the exclusive use of the clients to whom they are addressed and shall not be reproduced except in full without the written approval of Rone Engineers, Ltd. Client: Duke Realty Services, LP Report 601726 Project: Freeport 10 Project 037333 500 Freeport Parkway Date of Service: 07/14/03 Coppell, TX RoneEngineers A LEIGH COMPANY REPORT OF STRUCTURAL STEEL INSPECTION 8908 Ambassador Row Dallas, Texas 75247 214.630.9745 FAX 214.630.9819 reviewed, this item will be open per AWS D1.1 -02 code and specification requirements. (non compliant) III. The horizontal bridging was installed and welded as per the job specifications and SJI specifications and AWS D1.1 -02, compliant. IV. The diagonal x- bracing was installed and welded as per the SJI specifications and AWS D1.1 -02 code requirements, and AISC specifications for the snug -tight tensioning method concerning the bolted connection locations, compliant. V. The perimeter edge angle was installed and field welded. The welds were not de- slagged in all locations. Rone is simply verifying there appears to be welded attachments to the bar joist and embeds. RFI documentation is required from the structural engineer of record on the non deslagging of the fillet field welds to determine the visual weld profile per A.W.S. code requirements. This item of concern will remain an open issue until documentation is received and reviewed. *Note: Rone is in receipt of the RFI's for bar joist wall pockets that were field modified to accept the bar joists.The RFI's are included in today's report. Mike Tupa Certified Welding Inspector CWI #94030831 Page 3 of 3 LIMITATIONS: The test results presented herein were prepared based upon the specific samples provided for testing. We assume no responsibility for variation in quality (composition, appearance, performance, etc.) or any other feature of similar subject matter provided by persons or conditions over which we have no control. Our letters and reports are for the exclusive use of the clients to whom they are addressed and shall not be reproduced except in full without the written approval of Rone Engineers, Ltd. MAIN HS:IMMr.aro IVI n