SW0001-CN030808CITY OF COPPELL
CHANGE OR EXTRA WORK ORDER
PROJECT: Riverchase Elevated Sidewalk Project # SW00 -01
CONTRACTOR: Green Scaping
OWNER: City of Coppell
CHANGE ORDER NO.: ONE (1)
DATE: August 8, 2003
Item
Description
Quantity
Unit
Unit Price
Total
No.
ADD: I -I
Earth & Borrow
52
CY
$30
$1,560.00
I -4
Concrete Sawcut
15
LF
$10
$150.00
I -5
4" concrete Sidewalk
111
SY
$36
$3,996.00
I -6
Barrier Free Ramp
1
EA
$1200
$1,200.00
Total Revision to Contract Amount
$6
Install 200' of 5' sidewalk on the east side of the 300 block of
South MacArthur Blvd. This will complete the sidewalk along the
east side of MacArthur from Riverchase Dr. to Starleaf Dr., the
location of Riverchase Elementary School.
Previous contract amount $1359737.00
Net increase in contract amount
Revised contract amount
Net increase in contract time of completion
$6,906.00
$142,643.00
10 Days
Revised Contract time of completion 100 Calendar Days
The contractor hereby accepts this Contract adjustment as a final and complete adjustment in full
accord and satisfaction of all past and future liability originating under any clause in the Contract by
reason of this rgyision to the Contract.
S•'�•3
City Engineer Date
1B W 03 9 / 1063
Jim Witt, City Manager Date eed to y ontractor Date