ST0301-UP030930Ken Griffin_ - Project Update clm 09~c Page
5To I
FREESE-NICHOL8
1701 N. Market St., Suite 500
Dallas, TX 75202-2001
Phone: (214) 920-2500
Fax: (214) 920-2565
www.freese.com
Project Number: CPL03243
TO:
FROM:
DATE:
RE:
CC:
Ken Griffin, P.E., Suzan Taylor
Chris Moorman
September 30, 2003
Bethel Road Construction
Tricia Harley, P.E.
Project Updates:
n Met with City personnel and discussed conceptual review comments and hydraulic
findings for the bddge at Grapevine Creek and Bethel Road.
n Began vertical design at east end of project.
n Received a copy of Transystems's electronic flies via cd.
n Initiated geotechnical investigation phase.
Tasks and deliverables for the next two weeks:
n Water Surface Profile of Grapevine Creek.
n Roadway cross sections in bridge area to illustrate impacts on adjacent property.
n Revised downtown layout.
Date:
Oct. 3, 2003
Oct. 16, 2003
Oct. '10, 2003
Nov. 20, 2003
March 3, 2004
Deliverable:
Water surface profiles of Grapevine Creek
Roadway cross sections in bridge area
Revised downtown layout
Final Right-of-Way map
Preliminary Plan Submittal
Additional Issues:
n
n
4+00