PROJECT STATUS
SANDY LAKE ROAD AND DENTON TAP IMPROVEMENTS
1. Sandy Lake Road - Dallas City Limits to Carrollton City
Limit (Approximately 1800 feet East of the Trinity River
Bridge to Old Denton Road)
Extent of DWU Involvement - Unknown at this time. Designs
are very preliminary.
Estimate July, 1994 until detailed paving plans are
available.
Schedule of Roadway Improvements
Begin Construction June 1996
Completion June 1997 °'
Pro~ect Originator Dallas County 1991 Bond Program
Contact Person Mr. Bill Jessup 653-6424
Consultant Kimley .Horn (Mr. Paul Hames 386-
7007)
2. Sandy Lake Road - Coppell City Limits to Carrollton City
Limit (Approximately 200 feet West of the Trinity River
Bridge to Approximately 1800 feet East of Trinity River
Bridge)
Extent of DWU Involvement - Unknown at this time. Designs
are very preliminary.
Consultant indicated that DWU involvement is minimal.
Estimate August, 1994 until detailed paving plans are
available.
Schedule of Roadway Improvements
Begin Construction Februar7 1996
Completion February 1997
Pro~ect Originator Dallas County 1991 Bond Program
Contact Person Mr. Bill Jessup 653-6424
Consultant Charles Goyer, Inc. (Mr. Bill
Becker 340-1199)
3. Sandy Lake Road - MacArthur Boulevard to Coppell E. City
Limits (Approximately 200 feet West of the Trinity River
Bridge to MacArthur Boulevard)
Extent of DWU Involvement - Unknown at this time
Designs are very preliminary, Consultant indicated very
little DWU involvement, if any.
Estimate July, 1994 until detailed paving plans are
available.
Schedule of Roadway Improvements
Begin Construction Decembe~ 1996.
Completion December 1997 ~
Project Originator Dallas County 1991 Bond Program
Contact Person Mr. Bill Jessup 653-6424
Consultant Sverdrup (Mr. Phil Weston 520-2116)
Sandy Lake Road and Denton Tap Improvements Continued
4. Sandy Lake Road - MacArthur Boulevard to Denton Tap Road
Extent of DWU Involvement - Based on preliminary grades,
Estimate July, 1994 until detailed paving plans are
available. Design of DWU's 30 inch water relocations are
included in Coppell's Consultant's contract.
Schedule of Roadway Improvements
Begin Construction February 1995
Completion February 1996'
Project Originator City of Coppell'
Contact Person Mr. Steve Gorman 462-8495
Consultant Rady and Associates (Mr. Greg
Saunders 817-654-4266)
5. Denton Tap Road - Hiqhland Drive to SH 121
Extent of DWU involvement - Approximately 500 LF of existing
30 inch water main will require relocation at a cost of
$100,000~ Paving plans have been received from consultant
and Pipeline Design has begun the design for relocations.
Schedule of Roadway Improvements
Begin Construction March 1996
Completion March 1997
Project Oriainator City of Lewisville
Contact Person Mr. Tom Dingler 219-3491
Consultant Albert H. Halff (Mr. Jerry Roberts
817-429-9975)