ST9602-CS030826DALLAS COUNTY
PUBLIC WORKS
August 26, 2003
Suja Mathew, P.E.
Texas Department of Transportation
4777 East Highway 80
Mesquite, Texas 75150
Subject: Congestion Mitigation Air Quality (CMAQ) Program
Certifications - Project 10
Dear Ms. Mathew:
✓ I l 4 _
Dallas County certifies that all has been completed as per the attached certifications. Please
proceed with submitting this project for Austin review and TxDOT letting.
If you have any other questions or concerns about this matter, please call me at 214 - 653 -7460 or
Sam Wilson at 214- 653 -6421.
Sincerely,
L �� �� % ✓�.G2n•'c�l'1
Craig J. Goodroad
Program Manager
Attachments: (1.) Right of way certification
(2.) Relocation assistance certification
(3.) Utility adjustment certification
(4.) Encroachment certification
cc: Sam Wilson, P.E., Assistant Director, Transportation and Planning, w/o attachments
Sam Moghadassi, P.E., TxDOT Roadway Design, w/o attachments
Kenneth Griffin, P.E., City of Coppell, w/ attachments
Scott Young, P.E., USA Professional Services Group, Inc., w/o attachments
S:\ General \G04CORR \G4- 10UT\TXDOT\2003 \1078_ P10 project certifications.doc
411 Elm Street, 4th Floor Dallas, Texas 75202 C14 -DDJ - i 1 0
interoffice
MEMORANDUM Texas
Department
of Transportation
DALLAS DISTRICT
To:
Suja Mathew, P.E.
From:
Charles R. Tucker, P.E.
Date:
August 21 , 2003
R
Certifications
County: Dallas
Project: CM 96(907)
C -S -J: 0918 -45 -321
Highway: CS
Limits: From: MACARTHUR AT BELT LINE RD
To: IN CITY OF COPPELL
The following certifications have been furnished as you requested.
If you have any questions, please contact Mr. Travis Henderson at (214) 320 -6263.
Thank you.
\ Charles R. Tucker, P.E.
Director of Transportation Planning and Development
County.
Dallas
Project:
CM 96(907)
C -S -J.•
0918 -45 -321
Highway:
CS
Limits:
From: MACARTHUR AT BELT LINE RD
To: IN CITY OF COPPELL
UTILITY ADJUSTMENT CERTIFICATION
This is to certify that utility adjustments were not required or have been completed for this
project.
7ZR441
'�'-7 District Engineer
Dallas District
Date: August 21 , 2003
County:
Dallas
Project:
CM 96(907)
C -S -J:
0918 -45 -321
Highway. CS
Limits: From: MACARTHUR AT BELT LINE RD
To: IN CITY OF COPPELL
ENCROACHMENT CERTIFICATION
This is to certify that no right -of -way encroachments existed within the limits of this project or
all removal of encroachments has been completed.
TWA
District Engineer
Dallas District
Date: August 21 , 2003
County: Dallas
Project: CM 96(907)
C -S -J.• 0918 -45 -321
Highway: CS
Limits: From: MACARTHUR AT BELT LINE RD
To: IN CITY OF COPPELL
RIGHT OF WAY CERTIFICATION
This is to certify that acquisition of right -of -way was not required for this project.
. District Engineer
Dallas District
Date: August 21 , 2003
County:
Dallas
Project:
CM 96(907)
C -S -J.•
0918 -45 -321
Highway:
CS
Limits:
From: MACARTHUR AT BELT LINE RD
To: IN CITY OF COPPELL
RELOCATION ASSISTANCE CERTIFICATION
This is to certify that this project did not cause any displacements and the steps relative to
relocation advisory assistance and payments under the current FHWA directive(s) covering the
administration of the Highway Relocation Assistance Program were not required.
'District Engineer
Dallas District
Date: August 21, 2003
County:
Project:
C -S -J:
Highway:
Limits:
CMAQ Project 10
0918 -45 -321 (off system)
Various Intersections
Beltline @ Mac Arthur
Dallas
ENCROACHMENT CERTIFICATION
This is to certify that no right -of -way encroachments existed within the limits of this project or all
removal of encroachments has been completed.
Ce Date:
Recommended for Approval
Craig J. Goodroad
CMAQ Program Manager
Dallas County
County:
Dallas
Project:
CMAQ Project 10
C -S -J:
0918 -45 -321 (off system)
Highway:
Various Intersections
Limits:
Beltline @ Mac Arthur
RIGHT OF WAY CERTIFICATION
This is to certify that all the right -of -way has been acquired in accordance with the current
FHWA directives covering the acquisition of real property, except the parcels listed below which
will be acquired in accordance with FHWA directives.
PARCEL NUMBER
DOMAI
DATE
NO RIGHT -OF -WAY IS REQUIRED ON THESE INTERSECTIONS
��lit Date: z d a 3
Recommended for Approval
Craig J. Goodroad
CMAQ Program Manager
Dallas County
County:
Dallas
Project:
CMAQ Project 10
C -S -J:
0918 -45 -321 (off system)
Highway:
Various Intersections
Limits:
Beltline @ MacArthur
RELOCATION ASSISTANCE CERTIFICATION
This is to certify that this project did not cause any displacements and the steps relative to
relocation advisory assistance and payments under the current FHWA directive(s) covering the
administration of the Highway Relocation Assistance Program were not required.
!y ✓y Date: A"),)o 3
Recommended for Approval
Craig J. Goodroad
CMAQ Program Manager
Dallas County
County:
Dallas
Project:
CMAQ Project 10
C -S -J:
0918 -45 -321 (off system)
Highway:
Various Intersections
Limits:
Beltline @ Mac Arthur
UTILITY ADJUSTMENT CERTIFICATION
This is to certify that all utilities have been adjusted in accordance with the appropriate
directives covering the adjustment of utilities, except those utilities listed below which will be
adjusted in accordance with the appropriate directives.
OWNER UTILITY AND LOCATION EXPECTED DATE OF
COMPLETION OF
ADJUSTMENT
Date:
Recommended for Approval
Craig J. Goodroad
CMAQ Program Manager
Dallas County